Loading...
HomeMy WebLinkAboutCC AG PKT 2012-02-13 #GAGENDA STAFF REPORT DATE: February 13, 2012 TO: Honorable Mayor and City Council THRU: Jill R. Ingram, City Manager FROM: Sean P. Crumby P.E., Assistant City Manager /Public Works c e CJFORN• : SUBJECT: NOTICE OF COMPLETION FOR SEAL BEACH BOULEVARD STREET IMPROVEMENT PROJECT NO. ST1001 SUMMARY OF REQUEST: It is requested that the City Council: 1. Adopt Resolution No. 6219 accepting the Seal Beach Boulevard Street Improvements by All American Asphalt for Median Project (Task 1) in the amount of $341,407.60 and Resurfacing Project (Task 2) in the amount of $362,876.76; and 2. Direct the City Clerk to record the attached Notice of Completion 35 days after the day of acceptance. BACKGROUND AND ANALYSIS: On September 1, 2009, Caltrans approved the City's funded Federal -aid American Recovery and Reinvestment Act (ARRA) package in the amount of $496,413 for the Seal Beach Boulevard Resurfacing Project (Task 2) between Pacific Coast Highway and Bolsa Avenue. On September 27, 2010, OCTA approved the Transportation Enhancement (TE) 2010 Proposed List of Projects. The City was awarded grant funding for Seal Beach Boulevard Median Project (Task 1) between Pacific Coast Highway and Bolsa Avenue in the amount of $388,000. Both projects were combined (Task 1 and Task 2) into one project, Seal Beach Boulevard Street Improvement Project No. ST1001, to achieve savings of scale and reduce the overall project cost. The chronological sequence of construction, constructing the medians and then paving, alleviates harming the newly paved roadway. Agenda Item G On June 27, 2011, City Council awarded a contract to All American Asphalt for the Seal Beach Boulevard Street Improvement Project No. ST1001 - Task 1 is $361,000 and Task 2 is $409,000 totaling to $770,000. The Seal Beach Boulevard Street Improvement Project No. ST1001 involved construction �f new medians with landscaping and irrigation, replacement of damaged sidewalk, curb & gutter, driveway and paving. In addition, they removed the asphalt parkways that are impervious and placed pavers embedded in sand. Several City initiated change orders were encountered during construction on the project. These include: relocating the irrigation water source connection, asphalt digouts, additional planting and striping. The project is now complete to the satisfaction of the City Engineer. The project was inspected and it meets all standards and requirements within the project specifications. It is required to formally accept the project and file a notice of completion with the Orange County Clerk. ENVIRONMENTAL IMPACT: With both State and Federal funds granted for this project, the City was required to obtain both California Environmental Quality Act (CEQA) and the National Environmental Protection Act (NEPA) compliance. In December 2010, both CEQA and NEPA compliance documents were approved. LEGAL ANALYSIS: No legal analysis is required for this item. FINANCIAL IMPACT: In the approved FY 2011 -12 Budget, City -Wide Grant funds are budgeted for the Seal Beach Boulevard Street Improvement Project No. ST1001. Given that the grant allocations are from two separate funding sources, the accounting will be kept separate for reimbursement reporting purposes. Below is a summary and breakdown of expenses for the projects: Budgeted Funds Task 1 Medians Amount TE Grant Funding $ 388,000.00 City Match (General Fund) $ 80,000.00 Budgeted Funds Total • $ 468,000.00 Page 2 Expenses Amount Design /Environmental $ 70,000.00 Construction $ 330,590.00 Change Orders $ 10,817.60 Construction Engineering $ 14,500.00 California Conservation Corps* $ 2,850.00 Inspection/Testing $ 4,500.00 RECOMMENDATION: SUBMITTED BY: Sean P. Crumby, Assistant City Manager /Public Works Attachments: A. Resolution No. 6219 B. Notice of Completion Total Task 1 $ 433,257.60 Budgeted Funds Task 2 Street Resurfacing Amount Federal ARRA Grant Funds $ 496,413.00 Budgeted Funds Total $ 496,413.00 Expenses Amount Design (In- House) $ Construction $ 315,130.99 Change Orders $ 47,745.77 Construction Engineering $ 14,000.00 Inspection/Testing $ 8,000.00 Total Task 2 $ 384,876.76 *Requirement for Grant Funds The total cost of amount paid to All American Asphalt for construction /change orders for Task 1 is $341,407.60 and Task 2 is $362,876.76 totaling to $704,284.36. It is recommended that the City Council adopt Resolution No. 6219 accepting the Seal Beach Boulevard Street Improvements by All American Asphalt for Median Project (Task 1) in the amount of $341,407.60 and Resurfacing Project (Task 2) in the amount of $362,876.76 and direct the City Clerk to record the attached Notice of Completion 35 days after the day of acceptance. Prepared by: Cesar Rangel, Assistant Engineer Page 3 NOTED AND APPROVED: 3 .1LP • I R. Ingram, ity Manager RESOLUTION NUMBER 6219 A RESOLUTION OF THE SEAL BEACH CITY COUNCIL DECLARING WORK TO BE COMPLETED PER CONTRACT DOCUMENTS FOR THE SEAL BEACH BOULVEVARD STREET IMPROVEMENT PROJECT NUMBER ST1001 WHEREAS, staff combined both projects, Task 1 (Seal Beach Boulevard Median Project) and Task 2 (Seal Beach Boulevard Resurfacing Project) into one project, Seal Beach Boulevard Street Improvement Project No. ST1001, keeping the project accounting separately; and WHEREAS, on June 27, 2011 the City of Seal Beach entered into a contract with All American Asphalt; and WHEREAS, the City Engineer has determined that the work has been substantially completed in accordance with the contract documents. THE SEAL BEACH CITY COUNCIL DOES HEREBY RESOLVE: Section 1. The work required and performed by All American Asphalt has been completed. Section 2. That the total cost of amount to be paid to All American Asphalt for Task 1 is $341,407.60 for the work performed. Section 3. That the total cost of amount to be paid to All American Asphalt for Task 2 is $362,876.76 for the work performed. Section 4. That the work is hereby accepted and approved. Section 5. It is further ordered that a "Notice of Completion" be filed on behalf of the City in the Office of the Orange County Recorder within 10 days of the date of this resolution. PASSED, APPROVED and ADOPTED by the Seal Beach City Council at a regular meeting held on the 13th day of February , 2012 by the following vote: AYES: Council Members NOES: Council Members ABSENT: Council Members ABSTAIN: Council Members ATTEST: City Clerk STATE OF CALIFORNIA } COUNTY OF ORANGE } SS CITY OF SEAL BEACH } I, Linda Devine, City Clerk of the City of Seal Beach, do hereby certify that the foregoing resolution is the original copy of Resolution Number 6219 on file in the office of the City Clerk, passed, approved, and adopted by the Seal Beach City Council at a regular meeting held on the 13th day of February , 2012. City Clerk Mayor RECORDING REQUESTED BY AND WHEN RECORDED MAIL TO CITY OF SEAL BEACH Attn: City Clerk 211 - 8th Street Seal Beach, CA 90740 Space of above this line for Recorder's use. * ** No Recording Fee Pursuant to Government Code Section 6103, 27383 * * ** NOTICE OF COMPLETION Notice pursuant to Civil Code Section 3093, must be filed within 10 days after completion. Notice is hereby given that: 1. The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described: 2. The full name of the owner is: City of Seal Beach. 3. The address of the owner is: 211 — 8th Street, Seal Beach, CA 90740. 4. The nature of the interest or estate of the owner is: In Fee. The City of Seal Beach. 5. A work of improvement on the property hereinafter is described as substantially completed on November 7, 2011. The work was Seal Beach Blvd. Street Improvement Project. No. ST1001. 6. The name of the contractor(s), if any, for such improvement was: All American Asphalt. The date of the Contract Award was June 27 2011. 7. The property on which said work of improvement was completed in the City of Seal Beach, County of Orange, State of California, and is described as follows: Seal Beach Boulevard between Bolsa Ave. and PCH. Date: Director of Public Works, City of Seal Beach Signature of owner or corporate officer of owner named in paragraph 2 or agent. VERIFICATION I, the undersigned, say: the Director of Public Works declarant of the foregoing notice of completion; have read said notice of completion and know the contents thereof; the same is true of my own knowledge. I declare under penalty of perjury the foregoing is true and correct. Executed on , 2012, at Seal Beach, California. (Date of Signature) Director of Public Works, City of Seal Beach