AGENDA STAFF REPORT = _
. .
DATE: April 9, 2012
TO: Honorable Mayor and City Council
THRU: Jill R. Ingram, City Manager
FROM: Sean P. Crumby, Assistant City Manager/Public Works
SUBJECT: NOTICE OF COMPLETION FOR COLLEGE PARK
EAST SEWER REHABILITATION PROJECT NO.
SS0901
SUMMARY OF REQUEST:
It is requested that the City Council:
1. Adopt Resolution No. 6241 accepting the completed project by Charles
King Company for $2,950,961.17 to rehabilitate sewer lines in College
park East, CIP No. SS0901.
2. Direct the City Clerk to file a "Notice of Completion" with the Orange
County Clerk-Recorder within ten (10) days from the date of acceptance
and to release retention in the amount of$295,096.12 in 35 days.
BACKGROUND AND ANALYSIS:
On August 8, 2005, the City adopted the 2005 Sewer System Master Plan
Update, which identified over $15 million in required Capital Improvement
Projects.
At the June 27, 2011 City Council Meeting, Council awarded a construction
contract for the College Park East Sewer Rehabilitation project No. SS0901 to
the lowest bidder, Charles King Company, Inc. for $2,424,356.00. This project
was to increase the capacity on Elder Avenue from Heather Street to Ironwood
Avenue, on Aster Street from Birchwood Avenue to Basswood Avenue, and on
Basswood Avenue from Aster Street to Lampson Avenue. The project would
also repair various sewer pipes and manholes as identified in the 2005 Sewer
System Master Plan Update. These repairs consist of replacing Vitrified Clay
Pipe (VCP), sewer lateral reconnections, manhole modifications and repairs,
lining of existing 8-inch and 6-inch sewer mains, bypass pumping, traffic control,
and extensive dewatering. After the sewer pipe work is completed, the project
would also resurface effected streets with new asphalt pavement.
Agenda Item H
Several change orders were encountered on the project; most were requested by
the City during construction. Most change orders came from finding unmarked
utilities while installing the sewer lines or from modifying the sewer lining and
manhole lining sections of the contract. One large change order is detailed in the
Financial Impact section of this staff report. This change order is for the repaving
of Elder Avenue. The original plans called for a modified grind and cap of Elder.
However, during construction, the conditions of the subgrade of Elder Avenue
were much worse than the original samples indicated, and a full reconstruction
had to be performed. The change order reflects the cost to reconstruct Elder
Avenue minus the cost to grind and cap Elder as originally bid.
The work is now complete to the satisfaction of the City Engineer. The
contractor, Charles King Company Inc. did a remarkable job performing the work
while seamlessly working with the local residents in order to minimize the
impacts during the construction.
ENVIRONMENTAL IMPACT:
On March 26, 2009, the Initial Study/Mitigated Negative Declaration was
approved. This project complies with all requirements of the California
Environmental Quality Act (CEQA).
LEGAL ANALYSIS:
No legal analysis is required for this item.
FINANCIAL IMPACT:
This project is funded through a loan from the State Revolving Fund Financing
program and will not impact the General Fund. The City has the ability to borrow
up to $10,000,000. To date, to agreements have been secured against the
$10,000,000. They are: Finance Agreement No. 10-838-550 "College Park East"
for $2,650,000 and Finance Agreement No. 10-842-550 "Southern City" for
$1,100,000.
These loans are "soft" and give the City the ability to modify them should the cost
of these projects vary significantly. The loan financing will be paid off by the
Sewer Capital Fund. The Sewer Capital Fund will be drawn down over a period
of years and as needed to support the various sewer projects.
Estimated Expenses Amount
Original Contract Amount $ 2,424,356.00
Approved Change Orders and Deletions $ 227,955.46
Elder Avenue additional paving cost $ 298,649.71
Estimated Design/Inspection/Construction Support $ 110,000.00
Estimated Final Project Cost $ 3,061,000.00
Page 2
•
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt Resolution No. 6241 accepting the completed project by Charles
King Company for $2,950,961.17 to rehabilitate sewer lines in College
park East, CIP No. SS0901.
2. Direct the City Clerk to file a "Notice of Completion" with the Orange
County Clerk-Recorder within ten (10) days from the date of acceptance
and to release retention in the amount of$295,096.12 in 35 days.
SUBMITTED BY: NOTED AND APPROVED:
03# c-
can P. Crumby R. Ingram, Ci nager
Director of Public Works
Prepared by: David Spitz, Associate Engineer
Attachments:
A. Resolution No. 6241
B. Notice of Completion
Page 3
RESOLUTION NUMBER 6241
A RESOLUTION OF THE SEAL BEACH CITY COUNCIL
DECLARING WORK TO BE COMPLETED PER CONTRACT
DOCUMENTS FOR THE COLLEGE PARK EAST SEWER
REHABILITATION PROJECT NO. SS0901
WHEREAS, on June 27, 2011 the City of Seal Beach entered into a contract
with Charles King Company, Inc.; and
WHEREAS, the City Engineer has determined that the work has been
substantially completed in accordance with the contract documents.
NOW, THEREFORE, THE SEAL BEACH CITY COUNCIL DOES HEREBY
RESOLVE:
Section 1. That the work required to be performed by Charles King Company,
Inc. has been completed.
Section 2. That the total cost of amount to be paid to Charles King Company,
Inc. is$2,950,961.17 for the work performed.
Section 4. That the work is hereby accepted and approved.
Section 5. It is further ordered that a"Notice of Completion" be filed on behalf
of the City in the Office of the Orange County Recorder within 10
days of the date of this resolution.
PASSED, APPROVED and ADOPTED by the Seal Beach City Council at a
regular meeting held on the 9th day of April , 2012 by the following vote:
AYES: Council Members
NOES: Council Members
ABSENT: Council Members
ABSTAIN: Council Members
Mayor
ATTEST:
City Clerk
STATE OF CALIFORNIA }
COUNTY OF ORANGE } SS
CITY OF SEAL BEACH }
I, Linda Devine, City Clerk of the City of Seal Beach, do hereby certify that the
foregoing resolution is the original copy of Resolution Number 6241 on file
in the office of the City Clerk, passed, approved, and adopted by the Seal Beach
City Council at a regular meeting held on the 9th day of April , 2012.
City Clerk
RECORDING REQUESTED BY
AND WHEN RECORDED MAIL TO
CITY OF SEAL BEACH
Attn: City Clerk
211 - 8th Street
Seal Beach, CA 90740
Space of above this line for Recorder's use.
*** No Recording Fee Pursuant to Government Code Section 6103, 27383 ****
NOTICE OF COMPLETION
Notice pursuant to Civil Code Section 3093, must be filed within 10 days after completion.
Notice is hereby given that:
1. The undersigned is owner or corporate officer of the owner of the interest or estate stated
below in the property hereinafter described:
2. The full name of the owner is: City of Seal Beach.
3. The address of the owner is: 211 —8th Street, Seal Beach, CA 90740.
4. The nature of the interest or estate of the owner is: In Fee. The City of Seal Beach.
5. A work of improvement on the property hereinafter is described as substantially completed on
March 23, 2012. The work was College Park East Sewer Rehabilitation Project No SS0901.
6. The name of the contractor(s), if any, for such improvement was: Charles King Company,
Inc. The date of the Contract Award was June 27, 2011.
7. The property on which said work of improvement was completed in the City of Seal Beach,
County of Orange, State of California, and is described as follows: Various Locations, College
Park East Neighborhood, City of Seal Beach.
Date:
Director of Public Works, City of Seal Beach
Signature of owner or corporate officer of owner
named in paragraph 2 or agent.
VERIFICATION
I, the undersigned, say: the Director of Public Works declarant of the foregoing notice of
completion; have read said notice of completion and know the contents thereof; the same is true
of my own knowledge.
I declare under penalty of perjury the foregoing is true and correct.
Executed on , 2012, at Seal Beach, California.
(Date of Signature) •
Director of Public Works, City of Seal Beach