Loading...
HomeMy WebLinkAboutCC AG PKT 2012-11-13 #I 5 A4 AGENDA STAFF REPORT DATE: November 13, 2012 TO: Honorable Mayor and City Council THRU: Jill R. Ingram, City Manager FROM: Sean P. Crumby P.E., Assistant City Manager/Public Works SUBJECT: SEAL BEACH BOULEVARD AND GOLDEN RAIN INTERSECTION IMPROVEMENTS PROJECT NO. ST1107 SUMMARY OF REQUEST: Staff recommends that the City Council adopt Resolution No. 6927 for the Seal Beach Boulevard and Golden Rain Intersection Improvements Project No ST1 107: (1) approving the plans and specifications; (2) awarding a contract to Flatiron Electric Group, Inc. in the amount of $265,041.00; (3) approving Amendment No. 1 to Agreement to KOA Corporation for Construction Support Services in the amount of $12,500; (4) approving expenditure Of LIP to $20,000 for construction support (inspection) to the firm of Casulas Construction Services; and (5) authorizing the City Manager to approve contract changes in the amount of $27,000. In addition, staff recommends that the City Council consider a donation request from the Golden Rain Foundation of the Cobra Signal Heads from the existing traffic signals (see attachment D). BACKGROUND AND ANALYSIS: In 2010, the City Council authorized a study to assess the existing traffic operations at the intersection of Seal Beach Boulevard and Golden Rain Road. Seal Beach Boulevard is a six lane major arterial with a posted speed limit of 50 mph. Golden Rain Road is a private arterial road that serves as the main entrance to Leisure World, a 55 years and older gated community with a population of over 9,000. The intersection is an atypical "T" intersection, as the ingress and egress are separated by almost 200 feet. The study concluded that a complete redesign of the intersection was unnecessary; however, modifications could be made to the intersection for increased visibility and ease of use. The modifications recommended include: new traffic signal poles with mast arms that meet current standards, with multiple new 12" LED signal heads in locations that are optimal for visibility by drivers, including possible new pole locations. Additionally, modified pavement striping and markings were recommended to enhance -the intersection. This includes Agenda Item I striping for more optimal lane utilization, advanced directional signage, bike lane utilization striping, and possible striped medians. At the October 10, 2011 City Council Meeting, Council authorized the City to enter into an agreement with KOA Corporation to provide construction drawings and specifications for the Seal Beach Boulevard and Golden Rain Intersection Improvements Project No ST1 107. The Plans and Specifications have been completed and the City has advertised for bids. On March 7, 2012 a public meeting was held in Leisure World (Clubhouse #1) to discuss construction impacts for this project. On October 23, 2012, the City Clerk's office received two bids with the following results: RANK E CONTRACTOR BASE BID I Flatiron Electric Group, Inc. $265,041.00 ............. .............. 2 Palp, Inc. DBA Excel Paving Company $318,020.00 .......... ...........- ..........................................--------------- Based upon the references, qualifications, work experience and cost, staff recommends selecting Flatiron Electric Group, Inc. as the lowest responsive bidder at $265,041.00. As is customary, staff recommends that the Council authorize the City Manager to approve contract changes for up to approximately $27,000 (10% of the award) for unforeseen change work orders. The City Attorney's office has approved the construction agreement to be used for this project. The contractor has signed the agreement and it is included in this staff report. Exhibits to that agreement, including bonds and insurance documents will be provided to the City after award of contract. The City will also need additional construction support services from KOA Corporation during the construction of this project. KOA Corporation designed the Project, and, if the Amendment is approved, will assist the City and the City's Inspector with review and approval of submittals; RFI's (Request for Information) and shop drawings, provide necessary traffic counts and additional striping designs, attend field meetings as necessary, and provide final As-Built Record Drawings. In addition, staff seeks authority to expend up to $20,000 for construction support (inspection). The firm of Casulas Construction Services provides to the City public works inspection services at an hourly rate of $65.00 pursuant to a professional services agreement. "Construction support services" (often referred to as inspection) are necessary for making sure that the Contractor builds the project in accordance with the plans and specifications while following all applicable rules and regulations. The inspector is on the job site every day during the construction of the project. Page 2 The final recommendation addresses a request from the Golden Rain Foundation (GRF). The GRF has requested that the City upon demolition of the existing traffic signals donate the signal heads. These heads are the devices on the poles that house the red, green, and yellow lighting device. The old devices have been in place for approximately 10 years and have little value. In other construction projects the City places the responsibility for disposal on the contractor. In this the case, the contractor can remove the signal heads, and provide them at the job site (Seal Beach Boulevard and Golden Rain Road) for the GRF. The City will not transport, nor guarantee the condition of the signal heads for the GRF. Attached to this staff report is a written letter from the GRF requesting -these signal heads. If approved, the City Attorney will prepare the necessary release for the donation. ENVIRONMENTAL IMPACT: This project complies with all requirements of the California Environmental Quality Act(CEQA) and is categorically exempt under section 15302 class 2 (c). LEGAL ANALYSIS: The City Attorney has reviewed and approved the City's standard Construction Contract and the Design Professional Services Agreement Amendment. FINANCIAL IMPACT: Funds were approved in the FY 2011-2012 budget in the amount of $500,000 for design, construction and inspection of the Seal Beach Boulevard and Golden Rain Road Intersection Improvements Project No. ST1 107. The recommended actions include expenditures as follows: Item Amount Design (KOA Corporation) $ 46,900 Construction (award) $265,041 Contingency (10%) $ 27,000 Construction Support(KOA Corporation) $ 12,500 Inspection (Casulas Construction Services $ 20,000 Total $371,441 In the FY 2012-2013 budget, $400,000 in funding was carried over. RECOMMENDATION: Staff recommends that the City Council adopt Resolution No. 6927 for the Seal Beach Boulevard and Golden Rain Intersection Improvements Project No ST1 107: (1) approving the plans and specifications; (2) awarding a contract to Flatiron Electric Group, Inc. in the amount of $265,041.00; (3) approving Amendment No. 1 to Agreement to KOA Corporation for Construction Support Services in the amount of $12,500; (4) approving expenditure of up to $20,000 Page 3 for construction support (inspection) to the firm of Casulas Construction Services: and (5) authorizing the City Manager to approve contract changes in the amount of $27,000. In addition, staff recommends that the City Council consider a donation request from the Golden Rain Foundation of the Cobra Signal Heads from the existing traffic signals. SUBMITTED BY: NOTED AND APPROVED: i;i�l a '1� Sean P. Crumby, P.E. U gram, City M"ger Assistant City Manager/Public Works Prepared by: David Spitz, Associate Engineer Attachments: A. Resolution No. 6927 B. Agreement—Flatiron Electric Group, Inc. C. KOA Corporation-Amendment No. T D. GRF Signal Request Page 4 ATTACHMENT "A" Resolution No. 6927 RESOLUTION NUMBER 6927 A RESOLUTION OF THE SEAL BEACH CITY COUNCIL AWARDING THE CONSTRUCTION CONTRACT FOR SEAL BEACH BOULEVARD AND GOLDEN RAIN ROAD INTERSECTION IMPROVEMENTS PROJECT NO. ST1107 AND APPROVING AMENDMENT NO. 1 TO THE AGREEMENT BETWEEN THE CITY AND KOA CORPORATION FOR CONSTRUCTION SUPPORT SERVICES WHEREAS, the proposed Seal Beach Boulevard and Golden Rain Road Intersection Improvements Project No ST1107 will provide traffic signal modifications and intersection improvements at that intersection; and WHEREAS, staff recommends selecting Flatiron Electric Group, Inc. as the lowest responsive bidder. NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF SEAL BEACH DOES HEREBY RESOLVE: SECTION 1. The City Council hereby approves the plans and specifications for the Seal Beach Boulevard and Golden Rain Road Intersection Improvements Project No ST1107(the 'Project'). SECTION 2. The City Council hereby awards a contract to Flatiron Electric Group, Inc.for the Project in the amount of$265,041. SECTION 3. The City Council hereby approves that certain Amendment No. 1, dated November 13, 2012, to the agreement between the City of Seal Beach and KOA Corporation ("Agreement'), for an additional $12,500 for project management services for the Project. The Council hereby directs the City Clerk to attach Amendment No. 1 and Exhibit B to the Agreement. SECTION 4. The City Council hereby approves the expenditure of up to$20,000 for construction support (inspection)to the firm of Casulas Construction Services in connection with the Project. SECTION 5. The City Council hereby authorizes and directs the City Manager to execute the contract and the amendment on behalf of the City. SECTION 6. The Council hereby authorizes the City Manager to approve payments for additional work requests in connection with the Project in the cumulative amount of$27,000. (Intentionally Left Blank) Resolution Number 893T PASSED. APPROVED and ADOPTED by the Sao| Beach City Council at e regular meeting held on the 13th L day of November 2O12by the following vote: AYES: Council Members: NOES: Council Members: ABSENT: Council Members: ABSTAIN: Council Members: Mayor ATTEST: City Clerk STATE OFCALIFORNIA } COUNTY[]FORANGE } SS CITY OF SEAL BEACH } |. Undo Devine, City Clerk of the City of Seal Beaoh, do hereby certify that the foregoing resolution is the original copy of Resolution Number 6927 on file in the office of the City Clerk, passed, approved, and adopted bythe Seal Beach City Council mka regular meeting held on the_13th_ day uf_YNovember . 2O12. City Clerk ATTACHMENT "13„ Flatiron Electric Group, Inc. Agreement PUBLIC WORKS AGREEMENT FOR SEAL BEACH BOULEVARD & GOLDEN RAIN ROAD INTERSECTION IMPROVEMENTS CIP NO. ST 1107 between SEAL City of Seal Beach 211 - 8th Street Seal Beach, CA 90740 Flatiron Electric Group, Inc. 7911-A Pine Avenue Chino, CA 91708 (714) 228-9631 (909) 597-9151 - FAX TIES AGREEMENT is made as of November 13, 2012, by and between the City of Seat Beach, a California charter city C'City"), and Flatiron Electric Group, Inc., a General Contractor C'Contractor"). RECITALS A. WHEREAS, the City Council has approved the plans and specifications for the Traffic Signal Modification and Site Entrance Improvements on Seal Beach Boulevard and Golden Rain Road("Project") with respect to design criteria; and B WHEREAS, Contractor has submitted a bid to City for the Project dated October 23, 2012 in the amount of$265,041 ("Accepted Proposal" hereinafter). The Accepted Proposal is attached hereto as Exhibit G and contains, among other things, provisions defining the Project scope. NOW, THEREFORE, in consideration of performance by the parties of the mutual promises, covenants,and conditions herein contained,the parties hereto agree as follows: AGREEMENT 1. Contractor's Serv'ices.* 1,1 Scope and Level of Services. For and in consideration of the mutual promises set forth herein, and subject to the terms and conditions set forth in this Agreement, Contractor shall perform and complete in good and workmanlike manner all work ("Work") required by this Agreement and the documents listed in Subsection 1.2 for the Project., 1.2 Contract Documents, The "Contract Documents" that comprise the agreement between the City and the Contractor are the: Notice Inviting Bids, Instructions to Bidders, Accepted Proposal, Non-Collusion Affidavit, Bid Schedule(s), List of Subcontractors, .Contractor's Industrial Safety Record, Contractor's Qualification Statement,Bid Security Forms for Check or Bond, Specifications, General and Special Provisions and documents referenced therein, all addenda as prepared prior to the date of bid opening setting forth any modifications or interpretations of any'of said documents,this Agreement, Exhibits attached to this Agreement, including but not limited to the Performance Bopd (Exhibit A), Payment Bond (Exhibit B), Workers' Compensation Insurance Certificate (Exhibit C), Insurance Endorsements (Exhibit D), Acknowledgment of Penal and Civil Penalties Concerning Contractor Licensing Laws, (Exhibit E), Labor Law Requirements (Exhibit F), Accepted Proposal (Exhibit G) and any and all supplemental agreements executed amending or extending the Work contemplated and that may be required to complete the Work in a substantial and acceptable manner. These Contract Documents are hereby incorporated into.this Agreement. 1.3 The Work shall be performed in accordance with the Plans, Specifications and other Contract Documents. Contractor shall furnish at its own expense all labor, materials, equipm6nt and services necessary therefor, except such labor, materials, equipment and services as are specified in the Contract Documents to be furnished by City. 1.4 In the event of any material discrepancy between the express provisions of this Agreement and the.proVisions of the other Contract Documents, the provisions of this Agreement shall prevail. 2. Effective Date. This Agreement is effective as of November 13, 2012 (the "Effective Date"), and shall remain in full force and effect until Contractor has rendered the services required by this Agreement. 3. Pa meet, For performing, and completing the Work in accordance with the Contract Documents, City shall pay Contractor, in full compensation therefor, the amount of $265,041, subject to any additions and &ene ions pursuant to the terms of the Contract Documents. Said sum shall con*stitute payment in full for all work performed hereunder, including, without limitation, all labor, materials, equipment, tools and services used or incorporated in the Work, supervision, administration, overhead, expenses and any and all other things required, furnished or incurred for completion of the Work as specified in the Contract Documents. City shall make payments to Contractor on account of the contract sum at the time, in the manner, and upon the conditions specified in the Contract Documents. The City Manger may authorize extra work to fund unforeseen conditions up to the amount approved at the time of award by the City Council. Payment for additional work in excess of this amount requires prior City Council authorization. .4. Contractor's Personnel. 4.1 All Work shall be performed by Contractor or under Contractor's direct supervision, and all personnel shall possess the qualifications, permits, and licenses required by state and local law and by the Notice Inviting Bids/Instructions to Bidders to perform such Services, including, without limitation, a City of Seal Beach business license as required by the Seal Beach Municipal Code. 4.2 Contractor shall be responsible for payment of all employees' wages and benefits,-and shall comply with all requirements pertaining to employer's liability, workers' compensation,unemployment insurance, and Social Security. Contractor shall fully comply with the workers' compensation law regarding Contractor and Contractor's employees. 4.3 Contractor shall indemnify and hold harmless City and its elected officials, officers, employees, servants, designated volunteers, and agents serving as independent contractors in the role of city officials, from any and all liabilities, damages, claims, costs and expenses of any nature to the extent arising from Contractor's alleged violations of personnel practices. 4,4 Contractor is, and shall at all times remain as to . City, a wholly independent contractor. Contractor shall have no power to incur any debt, obligation, or liability on behalf of City or otherwise act as an agent of City. Neither City nor any of its agents shall have control over the conduct of Contractor or any of Contractor's employees, except as set forth in this Agreement. Contractor shall not, at any time, or in any manner, represent that it or any of its officers, agents, or employees are in any manner employees of City.. Contractor shall pay all required taxes on amounts paid to Contractor under this Agreement, and indemnify and hold City harmless from any and all taxes, assessments, penalties, and interest asserted against City by reason of the work performed pursuant to this Agreement. 1 4.5 City shall have the right to offset against the amount of any fees due to Contractor under this Agreement any amount due to City from Contractor as a' result of Contractor's failure to promptly pay to City any reimbursement or.indemnification arising under this Section 4. 5. Indemnification, 5.1 Contractor's Duly. Contractor shall defend, indemnify, and hold the City, its elected officials, officers, employees, volunteers, agents, and those City agents serving as independent contractors in the role of City officials (collectively "Indemnitees") free and harmless from.ate against any and all claims (including,.-without limitation, claims for bodily injury, death or damage to property), demands, obligations, damages, actions, causes of action,. suits, losses, bid protests, stop notices,judgments, fines,penalties, liabilities, costs and expenses (including, without limitation, attorney's fees, disbursements and court costs) of every kind and nature whatsoever (individually, a"Claim," collectively,"Claims"), in any manner arising out of or incident to the performance of the Agreement,including without limitation,the payment of all consequential damages and attorneys' fees and other related costs and expenses. 'Further, Contractor shall appoint competent defense counsel, at Contractor's own cost, expense and risk, to defend any and all such suits, actions or other legal proceedings of every kind arising out of or incident to the performance of the Agreement that may be, brought, or instituted against Jhdemnitees. Contractor shall pay and satisfy any judgment, award or decree that may -be rendered against City or the other Indemnitees in any such suit, action, or other legal proceeding arising out of or incident to the performance of the Agreement. Contractor shall reimburse the City and the other Indemnitees, for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. Contractor's obligation to indemnify shall not be restricted to insurance proceeds, if any, received by Contractor or Indemnitees. This indemnity shall apply to all Claims and liability regardless of whether any insurance policies are applicable. 5.2 Bid Protests. In addition to its obligations pursuant to Section 5.1, Contractor shall reimburse the City for all- attorneys' fees and costs incurred by City in connection with, arising out of or incident to any bid protest, 5.3 City's Sole Negligence, . Nothing in Section 5.1 shall be construed to require Contractor to indemnify Indemnitees for that portion of any Claim to the extent arising from the sole negligence or willful.misconduct of the Indemnitees. 5.4 Nonwaiver of Rig J�ts. Indemnitees do not, and shall not, waive any rights _ that they may possess against Contractor because of the acceptance by City, or the deposit with City, of any insurance policy or certificate required pursuant to this Agreement. 5.5 Waiver of Right of Subrogation. Contractor, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation against the Indemnitees, while acting within the scope of their duties, from all claims, losses, and liabilities arising out of or incident to activities or operations performed by or on behalf of the Indemnitor. 5.6 Survival. The provisions of this Section 5 shall survive the termination of the Agreement and are in addition to any other rights or remedies that Indemnitees may have under the law. - Payment is not required as a condition precedent'10'an Indernnitee's right to recover under this indemnity provision, and an entry of judgment against a Contractor shall be conclusive in favor of the Indemnitee's right to recover under this indemnity provision. 6. Insurance. 6.1 Liability Insurance. Contractor shall procure and maintain in full force and effect for the duration of this Agreement insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the services hereunder by Contractor, and its agents, representatives, employees and subcontractors. The policy limits set forth below do not act as a limitation upon the amount of indemnification to be provided by Contractor. Contractor shall complete and execute the following documents attached as Exhibits hereto and incorporated herein by this reference: 6.1.1 Exhibit D-1: Additional Insured Endorsement - Commercial General Liability. 6.12 Exhibit D-2: Additional Insured Endorsement - Automobile 1;ftibility, 6.1.3 Exhibit D-3: Additional Insured Endorsement. 6.2 Minimum Scope of Insurance. Unless otherwise approved by City, coverage shall be at least as broad as: 6.2.1 Insurance Services Office Commercial General Liability coverage (occurrence form CG 0001). 6.2.2 Insurance Services Office form number CA 0001 (Ed. 1/87) covering Automobile Liability,code I (any auto). 6.2.3 Insurance Services Office form number CG 20 10 11 85 (Ed. 11185)covering Additional Insured—Owners,Lessees or Contactors (Form B). 6.2.4 Workers' Compensation insurance as required by the State of California and Employer's Liability Insurance. 6.2.5 Professional Liability insurance. Unless the City waives in the requirement for professional liability insurance, Contractor shall provide to City the standard form issued by the carrier, 6.3 Minimum Limits of Insurance. Contractor shall maintain limits no less than: 6.3.1 General Liability: $2,000,000 per' occurrence and in the aggregate for bodily injury, personal injury and property damage. Commercial General Liability Insurance or other form with a general aggregate limit shall apply separately to this Agreement or the vneral limit shall be twice the reqiiired occurrence limit. 6.12 Automobile Liability: $2,000,000 per occurrence for bodily injury and property-damage. 6.3.3 Employer's Liability: $1,000,000 per occurrence and in the aggregate for bodily injury or disease and Workers' Compensation Insurance in the amount required by-law. 6.3.4 Professional Liabili : Waived (Please note that pursuant to Section 6.2.5, the City may waive the requirement that the Contractor carry professional liability insurance.) 6A Deductibles and Self-Insured Retentions. Contractor shall inform City of any deductible's or self-insured retentions except with respect to any professional liability insurance. 6.5 Other Insurance Provisions, The general liability and automobile liability policies are to contain, or be endorsed to contain,the following provisions: 6.5.1 City, its officers, officials, employees, designated volunteers and agents serving as independent contractors in the role of City officials, are to be covered as additional insureds as respects: liability arising out of activities performed by or on behalf of Contractor;.pr'pducts and completed operations of Conti-actor; promises owned, occupied or used by Contractor; or automobiles owned, leased, hired or borrowed by Contractor. The coverage shall contain no limitations on the scope of protection afforded to City, its.officers, officials, employees, designated volunteers or agents-serving as independent contractors in the role of City officials which are not also limitations applicable to the named insured. 6.5.2 For any claims related to this Agreement, Contractor's insurance coverage shall be primary insurance as respects City, its officers, officials, employees, designated volunteers and agents serving as independent contractors in the role of City officials, Any insurance or self-insurance maintained by City, their officers, officials, employees, designated volunteers or agents serving as independent contractors in the role of City officials shall be excess of Contractor's insurance and shall not contribute with it, 6.5.3 Contractor's insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability. 6.5.4 Each insurance policy required by this Section 6 shall be endorsed to state that coverage shall not be canceled or materially modified except after 30 days ' prior written notice by fist class rna il has been given to City. 6.5.5 Each insurance policy, except for any professional liability policy, required by this Section 6 shall expressly waive the insurer's right of subrogation against City and its elected officials, officers, employees, servants, attorneys, designated volunteers, and agents serving as independent contractors in the role of city or agency officials. 6.6 Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M. Best's rating of no less than A:VHl unless waived'in writing by City's Risk Manager. 6.7 Verification of Coverage. All insurance coverages shall be confirmed by execution of endorsements on forms approved by the City. The endorsements are to be signed by a person authorized by that insurer to bind coverage on its behalf. All endorsements are to be received and approved by City before services commence. As an alternative to City forms, Contractor's insurer may provide complete, certified copies of all required insurance policies, including endorsements effecting the coverage required by these specifications. 7. Liquidated Damages.I Should the Contractor fail to complete the project, or any part thereof, in the time agreed upon in the Contract, the Contractor shall reimburse the City for the additional expense and damage for each calendar day that the Contract remains uncompleted after the Contract completion date. It is agreed that the amount of such additional expense and damage incurred by reason of failure to complete the Contract is the per them rate of$750 per calendar day, Such amount is hereby agreed upon as liquidated damages for the loss to the City resulting from the failure of the Contractor to complete the project within the allotted time and to the value bf the operation of the works dependent thereon. It is expressly understood and agreed that this amount is a reasonable amount and is established in lieu of damages that are incapable of calculation at the inception hereof; and this 'amount is not to be considered in the nature of a penalty. The City shall have the rightAo deduct such damages from any amount due, or that may become due to the Contractor, or the amount of such damages shall be due and collectible from the Contractor or the Contractor's Surety. Progress payments. made after the scheduled completion date shall not constitute a waiver of liquidated damages. 8. Suspension. City may, in writing, order Contractor to suspend all or any part of the Contractor's Services for the convenience of City or for work stoppages beyond thd control of City or Contractor. A suspension of the Services does not void this Agreement. 9. 1 Notices. Any notices, bills, invoices, or reports authorized or required by this Agreement shall be in writing and shall be deemed received on (a) the day of delivery if delivered by hand or overnight courier service during Contractor's and City's regular business hours or by facsimile before or during Contractor's regular business hours; or (b) on the third business day following deposit in the United States mail, postage prepaid, to the addresses heretofore set forth in the Agreement, or to such other addresses as the parties may, from time to time, designate in writing pursuant to the provisions of this Section. All notices shall be addressed as follows: If to City: City Clerk City of Seal Beach 211-8th Street Seal Beach, California 90740 Telephone: (562)431-2527 Fax: (562) 493-9857 With a copy to: Public Works Director City of Seal Beach 211-8th Street Seat Beach, California 90740 If to Contractor: Flatiron Electric Group,Inc. 7911-A Pine Avenue Chino, CA 91708 Telephone: (714) 228-9631 Fax: (909) 597-9151 Attn: Richard Tesoriero,Vice President 10. Non-Assip—nabilily, Subcontracting. Contractor shall not assign, transfer, or subcontract any interest in this Agreement or the performance.of any of Contractor's obligations hereunder. Any attempt by Co'niractor,to so assign, transfer, or subcontract any rights, duties, or obligations arising hereunder shall be null,void and of no effect. 11. Compliance with Laws. Contractor shall comply with all applicable federal, state and local laws, ordinances, codes and regulations in force at the time Contractor performs the Services. 12. Non-Waiver of Terms, Rights and Remedies. Waiver by either party of any one or more of the conditions of performance under this Agreement shall not be a waiver of any other condition of performance u'nder this Agreement. In no event shall the making by City of any payment to Contractor constitute or be construed as a waiver by City of any breach of covenant, or any default which may then exist on the part of Contractor, and the making of any such'Myrnent by City shall in no way impair or prejudice any right or remedy available to City with regard to such breach or default, 13. , Attorneys' Fees. In the event that either party to this Agreement shall commence any legal action or proceeding to enforce or interpret the pro-visions of this Agreement, the prevailing party in such action or proceeding shall be entitled to recover its costs of suit, including all attorneys' fees incurred in connection therewith. 14, Construction. The validity, interpretation, and.performance of this Agreement shall be controlled by and construed under the laws of the State of California. In the event of any asserted ambiguity in, or dispute regarding the interpretation of any matter herein, the interpretation of this Agreement shall not be resolved by any rules of interpretation providing for interpretation against the party who causes the uncertainty to exist or against the party who drafted the Agreement or who drafted that portion of the Agreement. 15, Entire Agreement. This Agreement, including any other documents incorporated herein by specific reference, represents the entire and integrated agreement between Contractor -and City. This Agreement supersedes all prior oral or written negotiations, representations, or agreements. This Agreement may not be amended, nor any provision or breach hereof waived, except in a writing signed by the parties,which expressly refers to this Agreement, 16. Severabili1y. The invalidity in whole 'or in part of any provisions of tl-ds Agreement shall not void or affect the validity of the other provisions of this Agreement, IN WITNESS WIIEREOF, the parties, through their respective authorized representatives,have executed this Agreement as of the date first written above. CITY OF SEAL BEACH CONTRACTOR: By: By- Jill R. Ingram, City Manager Name; _. Attest: Title; By: Linda Devine, City Clerk Approved as to Farm; By: J Quinn.M. Barrow, City Attoiney EXHIBIT A FAITHFUL PERFORMANCE BOND EXHIBIT B PAYMENT BOND EXHIBIT C WORKERS' COMPENSATION INSURANCE CERTIFICATE EXHIBIT D-1 ADDITIONAL INSURED ENDORSEMENT (COMMERCIAL GENERAL LIABILITY) EXHIBIT D-2 ADDITIONAL INSURED ENDORSEMENT (AUTOMOBILE LIABILITY) EXHIBIT D-3 ADDITIONAL INSURED ENDORSEMENT EXHIBIT E ACKNOWLEDGMENT OF PENAL AND CIVIL PENALTIES CONCERNING CONTRACTOR LICENSING LAWS EXHIBIT F LABOR LAW REQUIREMENTS EXHIBIT G ACCEPTED PROPOSAL (NOTE: Exhibits will not be included with the contract at the time of award. The Contractor shall have 10 working days to submit all exhibits to the City after the award of contract. Failure to do so will result in voiding of the contract The City will then have the right to cash the bid bond for the project and re- advertise for construction or award to the next lowest responsive bidder.) ATTACHMENT "C" KOA Corporation Amendment No. 1 AMENDMENT NO. 1 TO PROFESSIONAL SERVICES AGREEMENT FOR SEAL BEACH BOULEVARD AND GOLDEN RAIN ROAD INTERSECTION IMPROVEMENTS PROJECT NO ST1107 Between S EAL CD City of Seal Beach . 211 - 8th Street Seal Beach, CA 90740 KOA Corporation 1120 West La Veta Avenue, Suite 660 Orange CA, 92868 P — 714-573-0317 This Amendment No. 1 dated November 13, 2012, amends that certain agreement ("Agreement") between the City of Seal Beach, a California charter city ("City") and KOA Corporation ("Consultant") dated October 10, 2011. RECITALS WHEREAS, City and Consultant entered into the Agreement on October 10, 2011 under which Consultant has provided professional services in connection with the design of the Seal Beach Boulevard and Golden Rain Road Intersection Improvements Project ("Project); and WHEREAS, the parties wish to amend the Agreement to increase Consultant compensation by $12,500 to compensate Consultant for such additional services required in connection with constructing the Project. NOW, THEREFORE and in consideration of the foregoing and of the mutual covenants and promises herein set forth, the parties agree to amend the Agreement as follows: Section 1. Section 1.0 (Scope of Services) of the Agreement is hereby amended to read as follows: 491.0 Scope of Services 1.1. Consultant shall provide those services ("Services") set forth in the attached Exhibit A. 1.2. Consultant shall provide those additional services ("Additional Services") set forth in the attached Exhibit B. 1.3. Consultant shall perform all services under this Agreement, as amended, in accordance with the standard of care generally exercised by like professionals under similar circumstances and in a manner reasonably satisfactory to the City. 1.4. In performing this Agreement, as amended, Consultant must comply with all applicable provisions of federal, state, and local law. 1.5. Consultant will not be compensated for any work performed not specified in Exhibits A-B unless the City authorizes such work in advance and in writing. The City Manager may authorize payment for such work up to a cumulative maximum of $10,000. Payment for additional work in excess of $10,000 requires prior City Council authorization." Section 2. Section 3.0 (Compensation) of the Agreement is hereby amended to read as follows: "3.0 Consultant's Compensation 3.1 City will pay Consultant in accordance with the fee schedule set forth in Exhibit A (for Services) and B (for Additional Services). In no event will the City pay more than: 0 $46,900 for the services identified in Exhibit A • $12,500 for the additional services identified in Exhibit B 3.2 Any additional work authorized by the City pursuant to Section 1.5 will be compensated in accordance with the rate schedule set forth in Exhibit A. Section I All other terms and provisions of the Agreement, as previously amended, shall have full force and effect. Section 4. - The Council hereby authorizes the City Manager to execute on behalf of the City the Amendment dated November 13, 2012. Section 5. The Council hereby directs the City Clerk to attach Amendment No. 1 and Exhibit B to the Agreement. IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 1 to be executed and attested by their proper officers thereunto: CITY OF SEAL BEACH KOA Corporation Jill R. Ingram, City Manager Pre'side--rit or Vice President ATTEST: Linda Devine, City Clerk Vice President or Secretary APPROVED AS TO FORM: Quinn M. Barrow, City Attorney EXHIBIT A s w of 5aaf Beakh 86u d and Go}deii Rain Etoa i 3 - Proposed Project Schedule & Fee PROPOSED PROJECT SCHEDULE A design schedule is proposed allowing for submittal of plans for initial checking within 4-6 weeks following your notice-to-proceed. We anticipate that the City will require a minimum of two weeks to review plans for each submittal. Responses to City comments would be completed within 7-10 business days following receipt. PROPOSED PEE The proposed fee for the traffic engineering and civil improvement design is. $46,900. Task I I - Post Design services would be billed on a time-and-material basis with a not-to-exceed fee of$2,940.Also KOA proposes the following progress payment schedule: > 50%upon submittal of preliminary plans and specifications ➢ 201 upon submittal of final plans and specifications A 20% upon approval of final plans and specifications Y 10% upon approval by the Cary of Seal Beach t Estimated Fee Break Down by TasklFersonnellHours Principal-in. Charge's 1 Project Senior Civil Office Civil CAD QA&QC Manager's En6neees Engineer's Technician's Total Tasks/Activities Hours Hours Hours Hours Hours Hers TasicCosts I-NO ect Management 4 8 2 0 0 14 $2020 2.0utreachl0therMeetsngs(4 meetings) l0 6 0 0 0 16 $2,480 3-Field Review 0 2 8 16 8 34 $3511 4-Traffic Signal Modification Plan 4 8 0 0 60 72 $6A00 5-Signing&Striping Plan 4 8 0 0 36 48 $4,720 5-ADA Compliance and Median Nose 2 2 19 80 6 104 S13,ot10 7-Traffic Control Plans 2 8 0 0 28 38 $3,780 8-Speci fications&Estimates 2 2 a 0 10 14 $tA40 9-ride Sheet 0 2 0 0 6 8 $780 t0-Submittals and Revisions 4 6 0 4 12 22 $2480 11-Post Design Assistance A 1 1 $ 2 12 Qm TOTAL HOURS 36 60 30 100 168 394 Hourlytsts $190 $180 $160 $110 $70 Labor OVY $6,840 $t0,800 $4,800 $11,000 $11,760 $45�2(30 KOA 94vm%s ;$1M TOTAL COSTS $6,840 $10,900 $4,500 $11,011 $11,760 546,400 Exclusions Y Our approach assumes a consensus to the need for this project. We have not allocated any resources to achieving a consensus regarding the need for improvements. { Potholing is excluded from our design fees. KOA CORPORATION s RANNINc s MGINlearNa 27 ��AI���A�F �^� EXHIBIT" u4| \mao Orangewood Avenue,3vxrA FF ��x � ������ ����^^��� o��CA 9�8 pLxwm/ws u sws|wssmws t:7|4.57]IB|7 f,714.S73,9534 www.koacorporationzom October 3U. 2O|2 Mr. David Spitz,Associate Engineer City of Seal Beach 211 Eight Street Seal Beach. CA 90740 Subject: ExTRA WORK PROPOSAL for Construction Assistance for Seal Beach Boulevard and Golden Rain Road in the City of Seal Beach Dear Mr.Spitz: KOA Corporation /KO/A is pleased to provide engineering services to you for the work in the City ofSeal Beach. The City has requested additional services that were not in the original Scope of Services. We are most interested in performing the necessary services and submitting this proposal accordingly, This letter presents our cost estimate for the project and requests your written authorization. KO/4will perform the following tasks: |. Review signal equipment shop 6ravvin§s, respond to RF[ visit the site to provide assistance for pole locations and detector locations and attend meetings 05,400 2. Preparation of As-Built / Record Drawings no provide an accurate sec of plans for file purposes. Record [}ruvvn8s would be new My|ar originals with changes identified with clouds and delta numbers describing the revision. $2,800 3. Direct Expense $500 4. Traffic Count Program (71 roadway segments plus one intersection) $3.200 5. Additional Striping Modification $600 Afee increase of $12,500 would be sufficient to cover these requests and includes upbmtwo meetings and two site visits during bidding and construction. Thus the fee will increase the total budget from $46.900 to $59.480. This will be billed on aT&M basis. Please contact rne if you have any questions orifyou require additional information regarding the subject project. If you concur with the terms of this proposal and authorize KOA no commence vvork, you may sign the appropriate line below and return it to our office.The proposal is valid for 90 days. Sincerely, Approved by: City mf Seal Beach Min Zhou, P.E. Principal Signed [Juue 6:12012'LExtra WorkLIBI310Xwk2,doc 11� LOS ANGELES ONTARIO ORANGE SAN DIEGO SOUTH BAY ATTACHMENT "D" Request from: Golden Rain Foundation GOLDEN RAIN FOUNDATION P.O. BOX 2069 • SEAL BEACH, CA 90740 (562) 43 1-6586 FAX (562) 593 •2009 September 28,2012 Sean Crumby,Assistant City Manager CITY OF SEAL BEACH 211 Bch Street Seal Beach, CA 90740 Dear Mr.Crumby, In late 2012 or early 2013,you will be changing out the traffic light standards at the main gate of our community. Would you please provide us with the Cobra Heads(in"as is"condition)for our possible use? If you have any questions,please do not hesitate to contact me at 562-431-6586 x312. Sincerely, Dan Schaeffer Executive Director