Loading...
HomeMy WebLinkAboutCC AG PKT 2014-04-14 #C .yflf SEAL Q"'`+. F . AGENDA STAFF REPORT DATE: April 14, 2014 TO: Honorable Mayor and City Council THRU: Jill R. Ingram, City Manager FROM: Sean P. Crumby P.E., Director of Public Works SUBJECT: NOTICE OF COMPLETION FOR THE PIER PLAZA STORAGE VAULT EMERGENCY REPAIRS PROJECT NO. BP1401 SUMMARY OF REQUEST: That the City Council adopt Resolution No. 6448: 1. Declaring damages to the Pier Plaza Storage Vault to be a public nuisance, deeming certain work to be of urgent necessity, and authorizing the City Manager to execute repair contracts as necessary without advertising for bids: 2. Accepting the Pier Plaza Storage Vault Repairs Project No. BP1401 by Golden State Constructors, Inc. in the amount of$55,000; 3. Approving Budget Amendment No. 14-10-01 in the amount of $20,000 for additional construction costs; and 4. Directing the City Clerk to File a "Notice of Completion" with the Orange County Clerk-Recorder within ten (10) days from the date of acceptance, and to release retention in the amount of $2,750 in 35 days. BACKGROUND AND ANALYSIS: The City of Seal Beach owns, within its Public Right-of-Way, a storage facility. This facility is located adjacent to Main Street and to Ocean Avenue on the southeastern side of the pier. The storage room fronts to the 10th Street Parking lot and is paved on the roof which allows for public viewing and vehicular and bike parking. During a site visit during the summer of 2012, staff became aware of possible structural deficiencies in regards to this storage room. The area directly above the storage room was cordoned off and a structural engineering firm, Dale Christian Structural Engineers, was contracted to perform a Limited Structural Investigation (LSI) to determine if the room was damaged and needed repairs or if the City could reopen the viewing area above the room. Agenda Item C The LSI identified structural deficiencies in the storage room, including the roof. Due to these deficiencies, the engineering firm recommended that the parking/viewing area above the storage room remain cordoned off to the general public until the roof and other parts of the room were reconstructed. The City then contracted with Dale Christian Structural Engineers to design repairs to the storage room in order to make the room and viewing area structurally safe. On January 27, 2014, the City Council awarded a contract to Golden State Constructors, Inc. for the Pier Plaza Storage Vault Repairs Project No. BP1401 in the amount of$38,400. The project originally consisted of constructing a concrete roof replacement, certain wall repairs, and a new roll up door to the existing exterior storage room. This initial stages of construction included demolition of the roof and sawcutting out certain sections of failed wall. During construction, it was determined, that the damage to the walls was worse than originally observed and anticipated. Most of the exterior walls that were to remain and the retaining walls were severely fractured and damaged to the point of needing immediate replacement. Staff received some cost estimates from the Contractor to perform different forms of repairs to the storage room. One consisted of repairing the interior walls, and leaving the area open, with no future storage room or viewing area. A second option involved adding an interior pillar; however, the structural engineer was not agreeable with this option. The third, involved adding two new interior walls, flush with the existing fractured walls. This would allow the new roof to be tied into newly poured walls with new rebar. The third option was determined to be the best option. The dangerous condition of the storage room was a threat to the public health, safety and welfare and constituted a public nuisance per section 7.35.010 of the Seal Beach Municipal Code which reads: "A Public Nuisance is ... anything which is injurious to health, indecent or offensive to the senses, or an obstruction to the free use of property, so as to interfere with the comfortable enjoyment of life or property by a neighborhood or by a considerable number of persons... The City Council shall have the power to declare by resolution that any particular act or condition constitutes a nuisance." Hence, staff recommended repairs immediately. The proposed repairs needed to be implemented so that the retaining walls, the viewing area, and park being held in place by them, would not be threatened. Any delays could have adversely affected City property and the public's ability to use that City property. The project is now complete to the satisfaction of the City Engineer. This project was inspected and it meets all standards and requirements within the project Page 2 specifications. It is required to formally accept the project and file a notice of completion with the Orange County Clerk. ENVIRONMENTAL IMPACT: City staff previously determined that this project was exempt from the California Environmental Quality Act (CEQA) and is categorically exempt under section 15301(d) of the CEQA Guidelines. LEGAL ANALYSIS: The City Attorney has reviewed the proposed resolution and approved as to form. FINANCIAL IMPACT: Funds were approved in the 2013-2014 Fiscal Year Budget for the Pier Plaza Storage Vault Repairs Project in the amount of $50,000. Those funds were not sufficient to fund the construction of this project. During award, the City budgeted an additional $10,000. The recommended actions include expenditures as follows: Budget Amendment No. 14-10-01 in the amount of $20,000 is recommended to provide sufficient funds for construction, emergency work and to cover the necessary associated construction costs for this project. Below is a summary and breakdown of expenses for the project: Description Amount Construction $ 38,400.00 Emergency Change Order $ 16,600.00 Design $ 9,400.00 Construction Inspection $ 6,000.00 Materials Testing $ 8,000.00 Total $ 78,400.00 The total cost of amount paid to Golden State Constructors, Inc. for construction/change orders is $55,000. RECOMMENDATION: That the City Council adopt Resolution No. 6448: 1. Declaring damages to the Pier Plaza Storage Vault to be a public nuisance, deeming certain work to be of urgent necessity, and authorizing the City Manager to execute repair contracts as necessary without advertising for bids: Page 3 2. Accepting the Pier Plaza Storage Vault Repairs Project No. BP1401 by Golden State Constructors, Inc. in the amount of$55,000; 3. Approving Budget Amendment No. 14-10-01 in the amount of $20,000 for additional construction costs; and 4. Directing the City Clerk to file a "Notice of Completion" with the Orange County Clerk-Recorder within ten (10) days from the date of acceptance, and to release retention in the amount of$2,750 in 35 days. SUBMITTED BY: NOTED AND APPROVED: Sean P. Crumby, E. II Ingram, City Man ger Director of Public Works Prepared by: David Spitz, Associate Engineer Attachments: A. Resolution No. 6448 B. Notice of Completion C. Change Order Cost Estimate Page 4 RESOLUTION NUMBER 6448 A RESOLUTION OF THE SEAL BEACH CITY COUNCIL DECLARING A NUISANCE, DEEMING CERTAIN WORK TO BE OF URGENT NECESSITY PURSUANT TO THE CITY CHARTER RATIFYING THE CITY MANAGER'S DECISION TO APPROVE CERTAIN REPAIR WORK WITHOUT ADVERTISING FOR BIDS FOR A NEW CONTRACT, AND DECLARING WORK TO BE COMPLETED PER CONTRACT DOCUMENTS FOR PIER PLAZA STORAGE VAULT REPAIRS PROJECT NO. BP1401 THE SEAL BEACH CITY COUNCIL DOES HEREBY RESOLVE: Section 1. In 2012, the City became aware of possible structural deficiencies in the Pier Plaza Storage Vault (Vault) located adjacent to Main Street and to Ocean Avenue on the southeastern side of the pier. The area directly above the vault was cordoned off and a structural engineering firm, Dale Christian Structural Engineers,was contracted to perform a Limited Structural Investigation (LSI) to determine if the room was damaged and needed repairs or if the City could reopen the viewing area above the room. The LSI identified structural deficiencies in the storage room, including the roof. The parking/viewing area above the storage room was therefore cordoned off to the general public. Section 2. On January 27, 2014, the City Council awarded a contract to Golden State Constructors, Inc. (Contractor) for the Pier Plaza Storage Vault Repairs Project No. BP1401 (Project) in the amount of $38,400 to repair the storage room and make the room and the viewing area directly above, structurally safe. Section 3. On March 4, 2014, during the scheduled demolition of the roof and parts of the walls to the Vault, parts of the existing walls that were expected to remain as part of the Project crumbled and were destroyed. It was also discovered that the remaining retaining walls were more severely deteriorated than the prior inspection could have determined. These remaining retaining walls were holding up parts of Eisenhower Park and certain beach viewing areas. Based on the results of an inspection, City staff determined that certain urgent repairs are needed to prevent a full collapse. Section 4. Section 7.35.010 of the Seal Beach Municipal Code defines a public nuisance to include: "...anything which is injurious to health, indecent or offensive to the senses, or an obstruction to the free use of property, so as to interfere with the comfortable enjoyment of life or property by a neighborhood or by a considerable number of persons.... The city council shall have the power to declare by resolution that any particular act or condition constitutes a nuisance. Section 5. Based on the conditions of the Vault, the City Manager determined that immediate action was necessary to abate the nuisance as quickly as possible and authorized the Contractor to perform certain work beyond the scope of the Project, including the addition of two new interior walls, flush with the existing fractured walls, so that the new roof could be tied into newly poured walls with new rebar. The additional work has been completed by the Contractor and the City Engineer has determined that the Project and additional repairs have been substantially completed in accordance with the contract documents. Section 6. Based upon the foregoing and upon the entirety of the record, including but not limited to the staff report and other evidence submitted at the council meeting,the City Council hereby finds and declares as follows: A. The dangerous condition of the Vault was a threat and injurious to the public health, safety and welfare and constituted a public nuisance that Resolution Number 6448 required immediate abatement. In the absence of repair, there was an immediate danger that retaining walls were holding up parts of Eisenhower Park and certain beach viewing areas would collapse. The repair needed to be implemented so that the coast and its precious resources would no longer be threatened. The action was the least environmentally damaging alternative. Any delays would have adversely affected the users and visitors to the beach and Eisenhower Park. B. Repairing the Vault constitutes: an emergency pursuant to City Charter Section 107; a matter of urgent necessity as that term is used in City Charter Section 1010; and a nuisance pursuant to Municipal Code Chapter 7.35. Section 7. Based upon the foregoing, and in accordance with City Charter Section 1010, the Council deems that work, supplies and materials needed to repair the Pier Plaza Storage Vault are of urgent necessity for the preservation of life, health or property and hereby ratifies the City Manager's decision to approve the additional repair work without advertising for bids for a new contract. Section 8. The work required to be performed by Contractors has been completed and accepted. A "Notice of Completion"shall be filed on behalf of the City in the Office of the Orange County Recorder within 10 days of the date of this resolution. Section 9. The Council hereby approves Budget Amendment No. 14-10-02 for the cost of repairing the Vault to modify the Fiscal Year 2013/2014 budget as follows: REVISED/ ADOPTED PROPOSED BUDGET(dif) DESCRIPTION ACCOUNT BUDGET BUDGET AMENDMENT Contract Professional 045-333-44000 $8,014,319 $8,034,319 $20,000 Transfer In 045-000-31500 $8,014,319 $8,304,319 $20,000 Transfer Out 001-080-47000 $6,921,298 $6,641,298 $20,000 PASSED, APPROVED AND ADOPTED by the Seal Beach City Council at a regular meeting held on the 14th day of April , 2014 by the following vote: AYES: Council Members NOES: Council Members ABSENT: Council Members ABSTAIN: Council Members Mayor ATTEST: City Clerk STATE OF CALIFORNIA } COUNTY OF ORANGE } SS CITY OF SEAL BEACH } I, Linda Devine, City Clerk of the City of Seal Beach, do hereby certify that the foregoing resolution is the original copy of Resolution Number 6448 on file in the office of the City Clerk, passed, approved, and adopted by the City Council at a regular meeting held on the 14th day of April 2014. City Clerk RECORDING REQUESTED BY AND WHEN RECORDED MAIL TO CITY OF SEAL BEACH Attn: City Clerk 211 - 8th Street Seal Beach, CA 90740 Space of above this line for Recorder's use. `** No Recording Fee Pursuant to Government Code Section 6103, 27383 **'' NOTICE OF COMPLETION Notice pursuant to Civil Code Section 3093, must be filed within 10 days after completion. Notice is hereby given that: 1. The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described: 2. The full name of the owner is: City of Seal Beach. 3. The address of the owner is: 211 —8th Street, Seal Beach, CA 90740. 4. The nature of the interest or estate of the owner is: In Fee. The City of Seal Beach. 5. A work of improvement on the property hereinafter is described as substantially completed on April 4, 2014. The work was Pier Plaza Storage Vault Repairs Project. No. BP1401. 6. The name of the contractor(s), if any, for such improvement was: Golden State Constructors, Inc. The date of the Contract Award was January 27, 2014. 7. The property on which said work of improvement was completed in the City of Seal Beach, County of Orange, State of California, and is described as follows: Pier Plaza, City of Seal Beach. Date: Director of Public Works, City of Seal Beach Signature of owner or corporate officer of owner named in paragraph 2 or agent. VERIFICATION I, the undersigned, say: the Director of Public Works declarant of the foregoing notice of completion; have read said notice of completion and know the contents thereof; the same is true of my own knowledge. I declare under penalty of perjury the foregoing is true and correct. Executed on 2014, at Seal Beach, California. (Date of Signature) Director of Public Works, City of Seal Beach David Spitz From: Ronnie Cochran <ron @goldensci.com> Sent: Tuesday, March 04, 2014 5:21 PM To: David Spitz Subject: RE: stand down David, Pretty informal but below is the costs you requested, option 1 is the best and I am giving you a fair price because I think in the long run this is the only way to do the project, start from scratch: 1. Complete rework of all walls and new door $16,600 - additional work than was bid A. Saw cut and tear down the remaining stub walls B. Form new interior walls and pour with new deck(for retaining purposes) C. Install new roll up door 2. Remove existing stub walls, delete roofing and exterior walls Credit to city ($-10,100) A. Saw cut and tear down the remaining stub walls B. Form new interior walls and pour with new deck(for retaining purposes). C. Costs associated with what we already have done to date 3. Cost to shore one interior wall $8800 A. Form interior wall along East side of room and pour monolithic with roof. B. Install new roll up door All costs above account for the additional saw cutting and extra wall that we have already incurred. Let me know ASAP how we are going to proceed. Thanks, Ronnie Cochran GSCI 714-625-8758(p) 714-625-8295(f) -------- Original Message -------- Subject: stand down From: David Spitz <DSpitz @sealbeachca.gov> Date: Tue, March 04, 2014 3:55 pm To: "Ronnie Cochran (ron @goidensci.com)" <ron @goldensci.com> We may have to stand down for a bit actually Ronnie. Not only do I need your quotes, but I need to run them up the chain to get approval and I need to have the Structural Engineer give me a stamped design that you can build to. Not sure how long this will take, but your quotes will start the process off. David Spitz, P.E., QSD Associate Engineer City of Seal Beach -211 Eighth Street, Seal Beach, CA 90740 (562) 431-2527 Ext. 1331 i