HomeMy WebLinkAboutCC AG PKT 2014-12-08 #L t Aj.., AGENDA STAFF REPORT DATE: December 8, 2014 TO: Honorable Mayor and City Council THRU: Jill R. Ingram, City Manager FROM: Sean P. Crumby P.E., Director of Public Works SUBJECT APPROVING THE SUBMITTAL OF AN APPLICATION FOR THE WESTMINSTER AVE / 17th ST CORRIDOR TRAFFIC SIGNAL SYNCHRONIZATION PROJECT SUMMARY OF REQUEST: That the City Council adopt Resolution No. 6525 approving the submittal of an application for grant funds under the Westminster Ave/17 h St Corridor Traffic Signal Synchronization Project. BACKGROUND AND ANALYSIS: The Orange County Transportation Authority's (OCTA's) Regional Traffic Signal Synchronization Program (RTSSP) provides grant funds to local agencies used for traffic signal coordination across jurisdictional boundaries. Projects eligible for RTSSP must be identified on the priority corridor network, signal synchronization network, or Master Plan of Arterial Highway (MPAH). The City of Santa Ana, working in cooperation with the cities of Seal Beach, Westminster, Garden Grove, Tustin, and Orange County, has submitted an application for signal synchronization on Westminster Avenue/17th Street from Apollo Dr. in the City of Seal Beach to Newport Boulevard in the County of Orange. Westminster Avenue is identified both on the MPAH and in accordance with the Traffic Signal Synchronization Master Plan. The Westminster Ave/17th St Corridor Traffic Signal Synchronization Project (Project) will design and implement traffic signal coordination across jurisdictional boundaries to improve vehicular flow along the length of the corridor. Intersections will receive improvements at 63 intersections along the corridor. Within Seal Beach, improvements will take place at the following signalized intersections: • Westminster Avenue and Apollo Drive • Westminster Avenue and Road B • Westminster Avenue and Seal Beach Boulevard Agenda Item L • Westminster Avenue Kitts Highway The City will also be simultaneously installing new video detection, digital closed- circuit television cameras for real-time traffic monitoring and upgrading existing controllers. ENVIRONMENTAL IMPACT: There is no Environmental Impact related to this item. LEGAL ANALYSIS: The City Attorney has reviewed the proposed resolution and approved it as to form. FINANCIAL IMPACT: The RTSSP requires a 20% minimum local match. The City's participating project total cost is $288,513 and the City's matching contribution is $57,703. Funds have not yet been budgeted for this project. If the grant is awarded, funding options will be recommended and presented during the FY 2015-16 budget. RECOMMENDATION: That the City Council adopt Resolution No. 6525 approving the submittal of an application for grant funds under the Westminster Ave/17" St Corridor Traffic Signal Synchronization Project. SUBMITTED BY: NOTED AND APPROVED: w Sean P. Crumby, P.E. III Ingram,s City M rya e ' Director of Public Work Prepared by: Cesar Rangel, Assistant Engineer Attachments: A. Resolution No. 6525 B. RTSSP -Grant Application Page 2 RESOLUTION NUMBER 6525 A RESOLUTION OF THE SEAL BEACH CITY COUNCIL APPROVING THE SUBMITTAL OF AN APPLICATION FOR FUNDING UNDER THE COMPETITIVE MEASURE M2 REGIONAL TRANSPORTATION SIGNAL SYNCHRONIZATION PROGRAM FOR THE WESTMINSTER AVE/17TH ST CORRIDOR TRAFFIC SIGNAL SYNCHRONIZATION PROJECT WHEREAS, the Measure M2 Regional Traffic Signal Synchronization Program targets over 2,000 signalized intersections across Orange County to maintain traffic signal synchronization, improve traffic flow, and reduce congestion across jurisdictions; and WHEREAS, the Orange County Transportation Authority declared the City of Seal Beach to meet the eligibility requirements to receive revenues as part of Measure M2; and WHEREAS, the City of Seal Beach has a Local Signal Synchronization Plan that is consistent with the Regional Traffic Signal Synchronization Master Plan as a key component of synchronizing traffic signals across local agencies' boundaries; and WHEREAS, the City of Santa Ana, working in cooperation with the City of Seal Beach and other local jurisdictions, has prepared a funding application (Application) for the Westminster Ave./17th St. Corridor Traffic Signal Synchronization Project(Project); and WHEREAS, the City of Seal Beach desires to implement the Project and is willing to provide its share of the required matching funds for the Project; and WHEREAS, the City of Seal Beach will not use Measure M funds to supplant Developer Fees or other commitments; and NOW, THEREFORE, THE SEAL BEACH CITY COUNCIL DOES HEREBY RESOLVE: Section 1. The City Council hereby approves the submittal of the Application to the Orange County Transportation Authority for funds in the amounts specified in the Application. Section 2. The City agrees to provide its share of the required matching funds for the Project if the Application is approved. PASSED, APPROVED AND ADOPTED by the Seal Beach City Council at a regular meeting held on the 8th day of December. 2014 by the following vote: AYES: Council Members NOES: Council Members ABSENT: Council Members ABSTAIN; Council Members Mayor ATTEST: City Clerk STATE OF CALIFORNIA } COUNTY OF ORANGE } SS CITY OF SEAL BEACH } I, Linda Devine, City Clerk of the City of Seal Beach, do hereby certify that the foregoing resolution is the original copy of resolution Number 6525 on file in the office of the City Clerk, passed, approved„ and adopted by the City Council at a regular meeting held on the 8th day of December, 2014. City Clerk MAYOR CITY MANAGER Miguel A. Pulido David Cavazos MAYOR PRO TEM 0, 4. CITY ATTORNEY Sal Tinajero Sonia R.Carvalho COUNCILMEMBERSlV a� CLERK OF THE COUNCIL Angelica Amezcua i .a Maria D.Huizar P.David Benavides Michele Martinez Roman Reyna Vincent F.Sarmiento CITY OF SANTA ANA 20 Civic Center Plaza a P.O Box 1988 M-43 Santa Ana,California 92702 www.santa-ana.org October 24, 2014 Mr. Anup Kulkarni Orange County Transportation Authority 550 South Main Street P.O. Box 14184 Orange, CA 92863-1584 SUBJECT: MEASURE M2 CTFP CALL FOR PROJECTS — REGIONAL TRAFFIC SIGNAL SYNCHRONIZATION (RTSSP) PROGRAM Dear Mr. Kulkarni: In response to OCTA call for projects under Measure M2 Regional Traffic Signal Synchronization Program, the City of Santa Ana with cooperation of the Cities of Seal Beach, Westminster, Garden Grove, Tustin and County of Orange is pleased to submit the following project: • Westminster Ave/17th St Corridor Traffic Signal Synchronization If you have any questions or need additional information, please contact Vinh Nguyen, Sr. Civil Engineer at (714) 647-5612. Sincerely, Edwin "William" Gam"ez, P.E. City Engineer SANTA ANA CITY COUNCIL Miguel A.Pralido Sal Tinajero i Vincent F.Sarrnienio i Michele Brtartinez I Angelica Amezcua i P David 6enavides i Roman F2rtryna Mayor e Idr9Rca Mayor or r . � - adS ldc rarfa-a r, na-Lr--P— nta ana g A.Arn rF es j eri vid ��arEaana.o a � a -an..ar -c r t y CITY OF SANTA ANA FY 2015 Call for Projects Regional Traffic Signal Synchronization Program Proj ect P Westminster Ave/ 17th St Corridor Traffic Signal Qy'�'ici ronizutio'�'i Proj edit Supplemental Application Documentation Submitted by: City of Santa Ana With the cooperation of the following Agencies; City of Seal Beach City of Westminster City of Garden Grove City of Tustin County of Orange Contact: Vinh Nguyen 714-647-5612 Loamvnguyengsanta-ana.org Project P Regional Traffic Signal Synchronization Program Application Checklist Project P Application Checklist Included RTSSP Online Application—submitted through OCFundTracker Online 1.Vehicle Miles Traveled 2.Benefit Cost Ratio 3.Project Characteristics 4.Transportation Significance 5.Maintenance of Effort 6.Project Scale 7.Number of Jurisdictions 8.Current Project Readiness 9.Funding Over-Match Section 1:Key Technical Information a. Project limits of the corridor to synchronize Pg.2 b. Designation of the corridor to synchronize:priority corridor,signal synchronization network Pg.2 corridor,or master plan of arterial highways corridor c. Project start date and end date,including any commitment to operate signal synchronization beyond Pg.2 the three year grant period d. Signalized intersections that are part of the project Pg.3 e. Traffic Forum members Pg.4 ---- _............... _—......... .._._. Section 2:Lead agency Pg.4 Section 3: Resolutions of Support From the Project's Traffic Forum members Appendix A I Section 4:Preliminary Plans for the Proposed Project Primary Implementation a. Project Administration b. Developing and implementing optimized signal synchronization timing Pp.5-7 c. Producing a Before and After Study for the proposed project d. Engineering design of signal system improvements e. Proposed signal improvements Ongoing Maintenance and Operation a. Monitoring and improving optimized signal timing Pg.8 b. Communications and detection support c. Project final report Section 5:Total Proposed Project Cost by Task Pp.9-14 Section 6: Project Schedule by Task for the 3 Year Grant Period Pp. 15 Section 7: Matching Funds Pg. 16-18 Section 8: Environmental clearances and other permits Pg. 18 Section 9:Calculations used to Develop Selection Criteria Inputs Pp. 19-20 Section 10:Any additional information deemed relevant by the applicant Pg.20 Appendices - 1 Section 1: Key Technical Information a. The network of Westminster Ave/ 17th St is being proposed for traffic signal synchronization. According to Figure 1, the project limits are from Apollo Dr in the City of Seal Beach to Newport Blvd in the County of Orange, which will have inter-agency coordination among six jurisdictions. b. Designation of the corridor to synchronize: ® Priority Corridor ® Signal Synchronization Network Corridor ❑Master Plan of Arterial Highways Corridor C. Project start date: May 1, 2016 Project end date: May 1, 2019 All agencies commit to operate signal synchronization beyond the three year grant period for: ®0 years ❑1 year ❑2 years ❑ 3 years ❑ Other mm o j r 0 a w.. .f aY� � CL r a t n SAWA PM WAN GARVENAWWE ORA OF .Imuw ✓rM.iu ffi:� Wwrrr�r^' � "�"'G^'`f woa^" � Y � /v�, r'1"F.d LEGEND o Seal Beach ® Santa Ana m o Westminster o Caltran D12 Westminster/17 Corridor Garden Grove o Tustin • Orange County Figure 1: Signalized intersection and Proposed Project limits 2 d. Signalized intersections that are part of the project: see Table 1 Table 1: Project Traffic Signals for the Westminster Avenue/ 17`h Street Si nal S nchronization Project Intersection Name Jurisdiction ._....................... �... .......... 1. Apollo Dr Westminster Ave 2. Road B Westminster Ave 3. Seal Beach Blvd Westminster Ave Seal Beach 4. Kitt Hwy @ Westminster Ave 5., Bolsa Chica Blvd g Westminster Ave 6,. Universi Westminster Ave 7. Milan St A Westminster Ave 8. Rancho Rd/Hammon PI(c, Westminster Ave 9. S rin dale St @ Westminster Ave 107 Willow Ln @ Westminster Ave Westminster 11. Edward St @ Westminster Ave .w 12. Westmart Ln Westminster Ave 13. Commerce Ln Westminster Ave 14. Goldenwest St ,Westminster Ave 15. Olive St A Westminster Ave 16. Hoover St Westminster Ave Caltrans/ 17. Beach Blvd @ Westminster Ave Westminster ..............._.... ....._ .................... 18. Monroe St/All American W (a,Westminster Ave 19. Newland St(a7 Westminster Ave Westminster 20. Magnolia St Westminster Ave 21. Deodara Dr/Swan St @ Westminster Ave www__www 22. Bushard St @ Westminster Ave 23, Kerry St Westminster Ave 24. Brookhurst St A Westminster Ave Garden Grove 25, Dawson St/Hope St @ Westminster Ave 26. Bowen St Westminster Ave _.�....... ._........................ ............... 27. Taft St Westminster Ave 28. Euclid St @ Westminster Ave 29. Newho e St Westminster Ave ................. 30. Harbor_plyA_@ Westminster Ave Santa Ana 31. Clinton St Westminster Ave 32. Roxey Dr @ Westminster Ave Garden Grove 33. Fairview St 17"' St 34. King St @ 17 S 35. English St @ 17''St 36. Alona St @@17 St . ._._. 37. College Ave @ 17`h St 38. Bristol Marketplace/Santa Ana Colle e , 17` St Santa Ana 39. Bristol St 17 St 40. Fire Station @ 17 1h St 41. Flower St 17 St 42, Ross St 17 St 43. Broadway a, 17 St 44. Main St 2 17`h St 3 45. Spurgeon St @ 17` St 46. Penn Iky @ 17` St 47. Santiago St/1-5 NB Off-ramp @ 17`h St Santa Ana/ Caltrans 48. Lincoln Ave(d), 17'h St 49. Grand Ave 17` St 50. Linwood Ave @ 17` St Santa Ana 51. She!R Ln/Cabrillo Park Dr(a), 17"St 52. Centre on 17 @ 17` St 51 Tustin Ave a, 17` St 54. Deodar St/SR-55 SB On-ramp @D. 17`h St Caltrans/ Orange Cou2,� 55, SR-55 NB Off-ramp @ 17"'St - Caltrans/Tustin 56. Caroll WY/Yorba St(& 17'h St .5.7...............Y.orba St/Enderle Center Dr_@ 17' St Tustin .58. Yorba St(South)/VandenbuM Ln 59. Laurinda Wy/Pros pect Ave @ 17"'St 60. Holt Ave(d), 17"' St Ih Orange County E�pLanaqS.Ay�..@. 17 St 62. Hewes Ave @ 17 St........ ............... 63. Newport Ave @ 176 St e. Traffic Forum members: Sea] Beach Westminster Garden Grove Santa Ana Tustin Orange County Section 2: Lead Agency F-1 City of City of Santa Ana will be the lead agency Z OCTA agency is requested to be the lead F-I County of Orange will be the lead agency 4 Section 3: Resolutions of Support Resolutions of support from Traffic Forum members are provided on Appendix A. Section 4: Preliminary Plans for the Proposed Project 1. Primary Implementation a. Project Administration b. The multi jurisdiction project of Westminster Avenue/ 17th Street will be led by OCTA. Project Administration services will include but not limited to administration, engineering, design, coordination, presentation and other related responsibilities to ensure the timely implementation of the project. c. Developing and implementing optimized signal synchronization timing In accordance with the Traffic Signal Synchronization Master Plan, the proposed synchronization of Westminster Avenue/ 17th Street will involve the Traffic Forum members to design and implement signal timing synchronization across jurisdictional boundaries to mitigate traffic and improve volume throughput along the corridor. Coordination parameters for peak traffic periods will be dependent upon existing field conditions, traffic patterns and maintaining cross-coordination. Even though Caltrans in not a participant of the project, timing plans for Caltrans intersections will be prepared and provided to Caltrans for implementation. d. Producing a Before and After Study for the project The Before and After Study for Westminster Avenue/ 17th Street will be conducted as defined by Regional Traffic Signal Synchronization Program guidelines. The studies will collect empirical data before and after the Primary Implementation. e. Engineering Design of Signal Improvements for the Project OCTA will use qualified traffic engineering consultants to complete the engineering design of intersection/field system upgrade, detection and communications upgrade for the project. For all improvements where engineering design is needed, the agency's staff will provide existing/as-built information and assist the project consultant to prepare the plans. Additionally, the traffic engineering consultant will provide design support for any required central system upgrades. 5 m L Proposed Signal Improvements Seal Beach The City is proposing to install fiber optic cable in existing conduit between Apollo Dr and Kitts Hwy. The fiber optic cable will provide a communication backbone for proposed Ethernet switches and CCTV cameras at several intersections. The City is also proposing to upgrade existing controllers and install new video detection system at various locations. Westminster The City is proposing the installation of Ethernet switches at various locations which will enable communication to proposed digital closed-circuit television cameras for real-time monitoring. In addition, the City is proposing cabinet upgrade at Westmart Ln along with video detection upgrades at several locations. The City is also proposing upgrades at the Traffic Management Center(TMC). The TMC improvements include upgrades to the Video Wall Display and integration of a Congestion Map and Travel Time System. Garden Grove The City is proposing the installation of new video detection system and Ethernet communication switches at various locations. In addition, the City is proposing the installation of emergency vehicle preemption and pedestrian upgrades at several locations. The City is also proposing traffic signal cabinet upgrades including controller and malfunction management unit at Taft St and Roxey Dr. A GPS clock is proposed at Roxey Dr. Santa Ana All of the traffic signals along Westminster Avenue/ 17th Street within the City are proposed to have Ethernet communications, which will enable various locations to have Bluetooth travel time measuring systems and digital closed-circuit television cameras for real-time monitoring, evaluation and fine tuning of the new synchronization plans. Approximately 4,200 feet of new conduit and 20,000 feet of new fiber optic cable will be installed. The City is also proposing to upgrade or replace all existing controllers with new Advance Traffic Controllers. In addition, 6 nine existing traffic signal cabinets will be replaced with new Type 332 cabinet. Three locations are proposed to have System Detection upgrades. The City is also proposing upgrades to the Video Management System and additional CCTV licensing. Tustin The City is proposing to upgrade all existing controllers with new ASC3 Controllers. In addition, the City is proposing to install fiber optic cable in new and existing conduit along with Fiber Optic Distribution units and Ethernet Communication switches at all intersections. Orange County The County is proposing to install new conduit with fiber optic cable between Prospect Ave and Newport Ave. Fiber Optic Ethernet switches will be installed at all intersections for communication. The County is also proposing controller upgrades at three locations and will replace existing traffic signal cabinet & foundation at Prospect Ave and Esplanade Ave. In addition, The City is also proposing installation of Emergency Vehicle Preemption at two intersections. Furthermore, the City proposes upgrades to the Traffic Management Center including Ethernet equipment, software licensing, integration and support. 7 2. Ongoing Maintenance and Operation Ongoing maintenance and operation period will start after signal timing is implemented and last for a period of two years. It will consist both of(1)monitoring and improving optimized signal timing and(2)communications and detection support. Ongoing Maintenance will not be provided for Caltrans intersections. Descriptions of both are provided below: a. Monitoring and improving optimized signal timing After the Primary Implementation of the new coordination parameters, the corridor will monitored and fine-tuned monthly or as needed for the duration of two years. Improvements to the signal synchronization will be made according to the test drives and changing field conditions. b. Communications and detection support The communication and detection systems will be monitored and repaired as necessary to maintain efficient corridor synchronization throughout the project schedule. c. Final report After the three year grant period, a final report for the project will be developed and will include before and after studies, updates of the results from the ongoing maintenance and operations phase and will establish completion of all CTFP Guideline requirements. 8 F"'OSection 5: Total Proposed Project Cost by Task Primary Implementation The Primary Implementation will include the following elements. A enc Total b Cash Table 2.Estimated P g Cost of Proposed Signal Im P rovements for Westminster Ave/17'h St Ma In Kmd a. Project Administration $120,000 $7,800 $16,200 b. Developing and Implementing Optimized Si al Synchronization Timing $252,000 $36,000 $14,400 c. Producing a Before and After Study for the proposed project $63,000 $12,600 $0 Total 1-1P!1jert Admin,I)evelo in Int l went"I°iMtiin „,Final Report,and Engineering Desi gn 1 $435,il00 1 $56A00 :$30,600 e. Proposed Sig at System Im rove rents Westminster/ Description of Unit Material, Match Agency 17th @ work at This Price* Unit Design Tax,& Total Cash In-Kind Location Labor Controller Upgrade, Install Fiber,CCTV Seal Beach Apollo Dr Camera System, $56,710 1 $3,000 $56,710 $59,710 $11,942 $0 Ethernet Communication, Video Detection . ...... ....................._._._..... ... ....M.............................. Controller Upgrade, Install Fiber,CCTV Seal Beach Road B Camera System, $56,710 1 $3,000 $56,710 $59,710 $11,942 $0 Ethernet Communication, Video Detection Seal Beach CCTV Camera Seal Beach Blvd System,Video $25,000 1 $3,000 $25,000 $28,000 $5,600 $0 Detection Controller Upgrade, Install Fiber,CCTV Seal Beach Kitt Hwy Camera System, $52,710 1 $3,000 $52,710 $55,710 $11 $0 Ethernet Communication, Video Detection _ CCTV Camera Bolsa Chica System,Ethernet Westminster Blvd Communication, $16,700 1 $1,670 $16,700 $18,370 $3,674 $0 Video Detection w Westminster University �....-....... ...... _ __ ._ .......... .....__........... CCTV Camera Westminster Milan St System,Ethernet $16,700 1 $1,670 $16,700 $18,370 $3,674 $0 Communication, Video Detection CCTV Camera Westminster Rancho System,Ethernet $16,700 1 $1,670 $16,700 $18,370 $3,674 $0 Rd/Hammon PI Communication Video Detection CCTV Camera Westminster Springdale St System,Ethernet $16,700 1 $1,670 $16,700 $18,370 $3,674 $0 Communication, Video Detection Westminster Willow Ln CCTV Camera Westminster Edward St System,Ethernet $16,700 1 $1,670 1 $16,700 $18,370 $3,674 $0 Communication, Video Detection 9 Cabinet Upgrade, CCTV Camera Westminster Westmart Ln System,Ethernet $46,700 1 $4,670 $46,700 $51,370 $10,274 $0 Communication, I.. Westminster Commerce Ln Video Detection CCTV Camera Westminster Goldenwest St System,Ethernet $16,700 1 $1,670 $16,700 $18,370 $3,674 $0 Communication, Video Detection Westminster Olive St _..............................�.�......... ......- Westminster Hoover St Westminster/ Beach Blvd Caltrans wwwwwwwww_ Westminster Monroe St/All American W Westminster Newland St CCTV Camer� a............................. Westminster Magnolia St System,Ethernet Communication, $16,700 1 $1,670 $16,700 $18,370 $3,674 $0 Video Detection Video Display Westminster TMC Upgrade,Traveleler $96,600 1 $9,660 $96,600 $106,260 $21,252 $0 Information System Deod ra Ethernet Dr/Swan Garden Grove /Swan St Communication, $27,500 l $2,750 $27,500 $30,250 $6,050 $0 Video Detection Ethernet Garden Grove Bushard St Communication, $27,500 1 $2,750 $27,500 $30,250 $6,050 $0 Video Detection ............ Ethernet Garden Grove Kerry St Communication, $30,200 1 $3,020 $30,200 $33,220 $6,644 $0 Video Detection, Ped UWade Ethernet Communication, Garden Grove Brookhurst St $38,100 1 $3,810 $38,100 $41,910 $8,382 $0 Video Detection, EVP,Ped UpgLade Dawson Garden Grove St/Ho e St Video Detection $25,000 1 $2,500 $25,000 $27,500 $5,500 $0 Garden Grove Bowen St Video Detection $25,000 1 $2,500 $25,000 $27,500 $5,500 $0 .�ww Cabinet Upgrade, Ethernet Garden Grove Taft St Communication, $59,900 1 $5,990 $59,900 $65,890 $13,178 $0 Video Detection, EVP,Ped Upgrade Ethernet Communication, Garden Grove Euclid St Video Detection, $41,300 1 $4,130 $41,300 $45,430 $9,086 $0 EVP.Ped Upgrade Fiber Optic,CCTV Camera System, ., Santa Ana Newhope St Ethernet Comm $23,920 1 $2,392 $23,920 $26,312 $5,262 $0 Bluetooth Travel Time,System Detection Controller Upgrade, Santa Ana Harbor Blvd Ethernet $12,120 1 $1,212 $12,120 $13,332 $2,666 $0 Communication, System Detection 10 IXINNWANOWiAIJIIX�pIIM I F[JC:S�antaAna Clinton St 'Cabinet& Controller Upgrade, e Roxey Dr Video Detection, $66,600 1 $6,660 $66,600 $73,260 $14,652 $0 EVP,Ped Upgrade, GPS Unit W_ �w Controller Upgrade, Install Conduit& CCTV Santa Ana Fairview St Fiber, $48,120 1 $4,812 $48,120 $52,932 $10,586 $0 Camera System, Ethernet Communication Controller Upgrade, Santa Ana King St Install Conduit& $37,620 1 $3,762 $37,620 $41,382 $8,276 $0 Fiber,Ethernet Communication Install Conduit& Santa Ana English St Fiber,Ethernet $36,120 1 $3,612 $36,120 $39,732 $7,946 $0 Communication Cabinet& Controller Upgrade, Santa Ana Alona St Install Conduit& $75,120 1 $7,512 $75,120 $82,632 $16,526 $0 Fiber,Ethernet Communication i Cabinet& Controller Upgrade, Install Conduit& Santa Ana College Ave Fiber,CCTV $85,120 1 $8,512 1 $85,120 $93,632 $18,726 $0 Camera System, Ethernet Communication Bristol Controller Upgrade, Marketplace/Sa Install Conduit& Santa Ana nta Ana Fiber,Ethernet $38,120 1 $3,812 $38,120 $41,932 $8,386 $0 College Communication Controller Upgrade, Install Conduit& CCTV Santa Ana Bristol St Fiber, $45,500 1 $4,550 $45,500 $50,050 $10,010 $0 Camera System, Ethernet Communication Cabinet& Controller Upgrade, Santa Ana Fire Station Install Fiber in Existing Conduit, $46,020 1 $4,602 $46,020 $50,622 $10,124 $0 Ethernet Communication Controller Upgrade, Santa Ana Flower St CCTV Camera $14,120 1 $1,412 $14,120 $15,532 1 $3,106 $0 System,Ethernet Communication Cabinet& Controller Upgrade, Santa Ana Ross St Install Fiber in $46,020 1 $4,602 $46,020 $50,622 $10,124 $0 Existing Conduit, Ethernet Communication Controller Upgrade, CCTV Camera System,Ethernet Santa Ana Broadway Communication $12,000 1 $1,200 $12,000 $13,200 $2,640 $0 «wawa_ 11 Cabinet& Controller Upgrade, Install Fiber in Existing Conduit, Santa Ana Main St Ethernet $53,900 1 $5,390 $53,900 $59,290 $11,858 $0 Communication, Bluetooth Travel Time,System Detection Cabinet& Controller Upgrade, Santa Ana Spurgeon St Install Fiber in $49,020 1 $4,902 $49,020 $53,922 $10,784 $0 Existing Conduit, Ethernet Communication Cabinet& Controller Upgrade, Santa Ana Penn Wy Install Fiber in $32,020 1 $3,202 $32,020 $35,222 $7,044 $0 Existing Conduit, Ethernet Communication Cabinet& Controller Upgrade, Santa Ana/ Santiago St/1-5 Install Fiber in Caltrans NB Off-ramp Existing Conduit, $20,020 l $2,002 $20,020 $22,022 $4,404 $0 Ethernet Communication Controller Upgrade, Install Fiber in Santa Ana Lincoln Ave Existing Conduit, $18,020 1 $1,802 $18,020 $19,822 $3,964 $0 CCTV Camera System,Ethernet Communication ........�.... ...- Controller Upgrade, i Install Fiber in Santa Ana Grand Ave Existing Conduit, $9,900 1 $990 $9,900 $10,890 $2,178 $0 Ethernet Communication Controller Upgrade, Install Fiber in Santa Ana Linwood Ave Existing Conduit, $12,020 1 $1,202 $12,020 $13,222 $2,644 $0 Ethernet Communication Cabinet& Controller Upgrade, Sherry Install Fiber in Santa Ana Ln/Cabrillo Existing Conduit, $59,020 1 $5,902 $59,020 $64,922 $12,984 $0 Park Dr CCTV Camera System,Ethernet Communication Controller Upgrade, Install Fiber in Santa Ana Centre on 17 Existing Conduit, $12,020 1 $1,202 $12,020 $13,222 $2,644 $0 Ethernet Communication Controller Upgrade, Santa Ana Tustin Ave Install Conduit& $35,370 1 $3,537 $35,370 $38,907 $7,781 $0 Fiber,Ethernet Communication TMC Upgrade, Santa Ana TMC Video System $50,000 1 $5,000 $50,000 $55,000 $11,000 $0 Upgrade Caltrans/ Deodar St/SR- Oran e County 55 SB On-ramp ._ 12 Caltrans/ SR-55 NB Off- Tustin ram Controller Upgrade, Caroll Install Fiber in Tustin Wy/Yorba St Existing Conduit, $14,250 1 $1,425 $14,250 $15,675 $3,135 $0 Ethernet Communication Controller Upgrade, Yorba Install Fiber in Tustin St/Enderle Existing Conduit, $89,000 1 $8,900 $89,000 1 $97,900 $19,580 $0 Center Dr Ethernet Communication Controller Upgrade, Yorba St Install Fiber in Tustin (South)/Vande Existing Conduit, $14,750 1 $1,475 $14,750 $16,225 $3,245 $0 nburg Ln I Ethernet Communication Cabinet& Laurinda Controller Upgrade, Orange County Wy/Prospect Install Conduit& $63,500 1 $6,350 $63,500 $69,850 $13,970 $0 Ave Fiber,Ethernet Communication, EVP Install Conduit& Orange County Holt Ave Fiber,Ethernet $84,700 1 $8,470 $84,700 $93,170 $18,634 $0 Communication Cabinet& Controller Upgrade, Orange County Esplanade Ave Install Conduit& $83,100 1 $8,310 $83,100 $91,410 $18,242 $0 Fiber,Ethernet Communication, EVP Controller Upgrade,Install Orange County Hewes Ave Conduit& Fiber, $72,700 1 $7,270 $72,700 $79,970 $15,994 $0 Ethernet Communication Install Conduit& Orange County Newport Ave Fiber,Ethernet $55,900 1 $5,590 $55,900 $61,490 $12,298 $0 Communication TMC Upgrade, Orange County TMC Software,Ethernet $45,708 1 $5,000 $45,708 $50,708 $10,142 $0 Communication Subtotal:Estimated cost of"Proposed Signal System Improvements"(total $212,043 $2,187,268 $2,399,311 $479,823 $0 combined) g.Contingency(un to 10%of the estimated costs of"Proposed Signal System $218,727 $43,745 $0 Im rovements") h.Construction management(W to 15%of the estimated costs of"Proposed $328090 $22,579 $43,039 Signal System Improvements"for support and inspection costs) Total 2-Signal System Improvements,Construction Support/Inspection, $2,946,128 $546,147 $43,039 and Contin encv Costs Totals 1+2 $3,381,128 $676,226 *: Details of improvement and cost are listed in the Appendix B 13 Ongoing Maintenance and Operation a. Monitoring and improving optimized signal timing Estimated Cost: $100,800 b. Communications and detection support Estimated Cost: $43,200 Table 3: Estimated Cost of Proposed Ongoing Maintenance and Operation Description of Work Description Unit Price Cost Monitoring and Drive monthly and improve timing parameters along improving $70 per signal 60(*)signals for 24 months after signal timing is $100,800 g g g optimized signal implemented per month timing Communications Monitor,maintain and repair communication and $30 per signal and detection detection along 60(*)signals for 24 months after signal $43,200 support timing is implemented per month Project team will develop a final report for the project. Project final report This report will be completed after the three year grant Negligible Negligible period. .............. ...... ...... Proposed On going Maintenance and Operation $144.000 (*): Ongoing Maintenance and Operation will not be provided for three(3)Caltrans intersections. Total Project Cost Including Primary Implementation and Ongoing Maintenance and Operation for Three Year Grant Period Total Estimated Cost: $3,525,128 Table 2 + Table 3 = $3,381,128 + $144,000) mm n Co e is if any): 14 WJ Section 6: Project Schedule by Task for the 3 Year Grant Period Project start date: May 1,2016 Project end date: May 1, 2019 ",rwi]�4 lernentation Task Starting Date Ending Date a. Project Administration May 1, 2016 May 1,2019 b. Developing and implementing optimized signal synchronization May 1, 2016 May 1, 2017 timing C. Producing a Before and After Study May 1, 2016 June 1, 2017 d. Engineering design of Signal System Improvements May 1, 2016 Dec 30, 2016 e. Proposed Signal Improvements, Construction Support/Inspection and Jan 1, 2017 May 1, 2017 Contingency Costs f. Contingency Jan 1, 2017 May 1, 2017 .. _ ._ �.aa�.�. _ ....._.. .......... . g. Construction Management Jan 1, 2017 I May 1, 2017 _Onwg_oing',Naintenance and Operation Task Starting Date Ending Date a. Monitoring and improving optimized ' v' 'zed signal timing June 1, 2017 May 1, 2019 b. Communications and detection support a __. June 1, 2017 May 1, 2019 c., Producing a Final Report Jan 1, 2019 May 1, 2019 15 Section 7: Matching Funds Table 2(Implementation): M2 Funds Requested $2,704,902 Phase Match Amount $676,226 ............ In-kind match amount $73,639 Cash match amount $602,587 Total Phase Cost 1 $3,381,128 Table 3(Ongoing Activities): M2 Funds Requested $115,200 Phase Match Amount $28,800 .. ......... In-kind match amount $3,456 Cash match amount $25,344 Total Phase Cost $144,000 Project Total: M2 Funds Requested $2,820,102 Total Match Amount(min 20%) $705,026 In-kind match amount(max 20016) $77,095 ............................................ Cash match amount 81,77 031 Total Project Cost $3,525,128 .......................................................... Total Match Ratio(to total project cost) $705,026/$3,525,128=20% AGENCY TOTAL MATCH SUMMARY Agency Cash In-Kind Total Match Seal Beach $47,903 $9,800 $57,703 Westminster $84,448 $15,006 $99,454 Garden Grove $95,184 $13,833................................. $109,017- Santa Ana $241,896 $38,456 $280,352 Tustin $38,500 $0 $38,500 Orange County $120,000 $0 $120,000 TOTAL $627,931 $77,095 $705.026 d Note: No improvements are proposed for Caltrans locations; only timing plans will be prepared and given to Caltrans for implementation. Cost for timing is included in Cities of Westminster,Tustin, &Orange County. 16 MATCH BREAKDOWN(CASH VS IN-KIND SERVICES) A. Cash Match Ai!enev Funding Source Amount of Cash Contribution Seal Beach M2 Fairshare $47,903 Westminster Traffic Im act Fee $84,448 ir Garden Grove M2 Fairshare $95,184 _... ...... ........... Santa Ana M2 Fairshare $241,896 Tustin M2 Fairshare $38,500 Oran ge County Gas Tax $120,000 TOTAL $627,931 B. In-Kind Services i; as-,cr ic,Imcrrovements (Gist items and Cost Agency Improvement Date of Expenditure Construction TOTAL $0.00 ii. Islyta fang Commitment: No. of Fully Burdened Agency Staff Position_ Type of Service to Project Hours* Hr Rate* Total* City Traffic Engineer Project Admin 8.00 $175.00 $1,400 Proj ect Seal Assistant Engineer Design/Implement/Constr 40.00 $145.00 $5,800 Beach En rn Construction Construction Engineering 20.8 $125.00 $2,600 Ins ector Sub Total for Seal Beach $9,800 Project Westmi City Traffic Engineer Admin/Implement/Constr 110.00 $94.12 $10,353 nster .ww.......w En rn Civil Engineering Project Implement/Constr 58.12 $80.06 $4,653 Assistant En rn Subtotal for Westminster $15,006 Associate Engineer Project 40.00 $95.00 $3,800 De n/Im lementation/Review Garden Associate Engineer Project Design/Implementation 40.00 $95.00 $3,800 Grove Sr.Traffic Signal Project Design/Construction 40.00 $75.00 $3,000 Electrician En g. Construction Construction Eng. 28.11 $115.00 $3,233 Inspector Subtotal for Garden Grove $13,833 Sr Civil Engineer Project Admin 24.00 $233.00 $5,592 Assistant Traffic Project -- Santa Operation Enginner Design/Implement/Constr 40.00 $213.00 $8,520 Ana En rn Project Asssitant Engineer Design/Implement/Constr 55.00 $213.00 $11,715 ................. ........................ En M _. 17 .. ........ Construction Construction Engineering 55.00 $187.00 $10,285 Ins ectop r Project Engineering Intern Design/Implement/Constr 57.17 $41.00 $2,344 En rn Subtotal for Santa Ana $38,456 TOTAL IN-KIND MATCH $77,095 *: Estimate, subject to change Section 8: Environmental clearances and other permits "A categorical exemption will be obtained for this project upon project award." 18 Section 9: Calculations used to Develop Selection Criteria Inputs: 1. Vehicle Miles Traveled(VMT): Segment Current Average Daily Traffic Distance (mi) VMT=ADT*D Apollo Dr to Seal Beach Blvd 27,000 0.55 14,850 Seal Beach Blvd to Bolsa Chica Blvd 26,000 2.03 52,780 Bolsa Chica Blvd to Rancho Rd 16,000 0.72 11,520 �. _ _._ ..... Rancho Rd to Springdale St 28,000 _ 0.31 8,680 S rin dale St to Edwards St 37,000 0.5 18,500 Edwards St to Goldenwest St 38,000 0.51 19,380 Goldenwest St to Hoover St 27,000 1 0.5 13,500 Hoover St to Beach Blvd 34,000 0.5 17,000 ...... Beach Blvd to Newland St 30,000 0.5 15,000 Newland St to Magnolia St 27,000 0.49 13,230 Magnolia St to Bushard St 27,000 0.51 13,770 Bushard St to Brookhurst St � 33,000 0.5 16,500 Brookh,.... urst 28,000 1 28,000 .._St to Euclid St µ_ ........... Euclid St to Newho e St 26,000 0.5 13,000 Newho a St to Harbor Blvd 26,000 0.5 13,000 Harbor Blvd to Fairview St 26,000 1 26,000 Fairview St to Bristol St 33,000 1.03 33,990 Bristol St to Flower St 38,000 0.49 Flower St to Broadwa 39,000 0.39 15,210 Broadway to Main St 40,000 0.12 4,800 Main St to Santiago St 32,000 0.43 13,760 Santiago St to Grand Ave 33,000 0.47 15,510 Grand Ave to She Ln 31,000 0.59 18,290 Sherry Ln to Tustin Ave 31,000 0.43 13,330 Tustin Ave to SR-55 SB Ramp 42,_000 0.12 5,040 SR-55 SB to Prospect Ave 32,000 0.56 17,920 Prospect Ave to Holt Ave 27,000 0.38 10,260 Holt Ave to Esplanade Ave 24,000 � ' 0.13 3,120 Esplanade Ave to Hewes Ave 23,000 0.32 7,360 Hewes Ave to Newport Ave 22,000 0.25 5,500 Total Project VMT 477,420 Source of ADT are from OCTA 2013 Traffic Flow map 19 Calculation and Estimated Points Criteria Estimated Points 1. Vehicle Miles Traveled (VMT) (20 Points) VMT=477,420 (See Above Table) 20 2. Cost Benefit Ratio: (15 Points) Calculation for Total Project Cost/VMT=3,525,128/477,420=7.4 11 3. Project Characteristics: (10 Points) Signal Coordination® Communications and detection support;New or upgraded coma-minication s stuns acid detection Intersection/field 10 system modernization and replacement, Emergency Vehicle Preemption, TMC Upgrades 4. Transportation Significance: (10 Points) Priority Corridor 10 5. Maintenance of Effort: (5 Points) 0 years beyond 3 year grant period 0 6. Project Scale: (10 points) a. Number of signals=63 b. Number of signals being synchronization/Total number of 10 corridor signals=63/63= 100% 7. Number of Jurisdictions: (20 Points) 6 jurisdictions 20 8. Current Project Readiness: (5 Points) Project start date: May 1, 2015 5 ....... ..... ................... 9. Funding Match: (5 Points) $705,026/$3,525,128=20% 0 Total Points 86 Section 10: Include any additional information or documentation deemed relevant by the applicant Project Summary ® All guidelines were met for this project ❑ Not all qualifications were met, provide an explanation below of why the guidelines were not met for this project. 20 APPENDIX A Resolutions of Support 21 RESOLUTION NO. 2014- A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SANTA ANA APPROVING THE SUBMITTAL OF IMPROVEMENT PROJECTS TO THE ORANGE COUNTY TRANSPORTATION AUTHORITY FOR FUNDING UNDER THE COMPREHENSIVE TRANSPORTATION PROGRAM BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SANTA ANA AS FOLLOWS: Section 1: The City Council of the City of Santa Ana hereby finds, determines and declares as follows: A. The rifii of Cants Ana Amcirac to imnlement the trancnorfatinn imnrnvamante listed below. B. The City of Santa Ana has been declared by the Orange County Transportation Authority to meet the eligibility requirements to receive Measure M "turnback" funds. C. The City's Circulation Element is consistent with the County of Orange Master Plan of Arterial Highways. D. The City of Santa Ana will provide matching funds for each project as required by the Orange County Comprehensive Transportation Funding Programs Guidelines. E. The Orange County Transportation Authority intends to allocate funds for transportation improvement projects within the incorporated cities and the County. F. The City of Santa Ana will not use Measure M funds to supplant Developer Fees or other commitments. G. The City of Santa Ana will use Arterial Highway Rehabilitation Funding as a supplement to the existing pavement management program. Reso#2014- Page 1 of 3 Section 2: The City Council of the City of Santa Ana hereby requests the Orange County Transportation Authority allocate funds in the amounts specified in the City's application to the City of Santa Ana from the Comprehensive Transportation Programs. Said funds shall be matched by funds from Santa Ana as required and shall be used as supplemental funding to aid the City in the improvement of the following street(s): PROJECT PROGRAM FY Westminster Ave/17th St. Traffic Signal Synchronization TSSP 15/16 Main St. Traffic Signal Synchronization TSSP 15/16 Bear St. Traffic Signal Synchronization TSSP 15/16 Fairview Ave. Widening from Civic Center to 17th St. RCP 15/16 Grand Ave. and 1st St. Intersection Widening RCP 15/16 Bristol St Widening: Civic Center to Washington RCP 16/17 Bristol St. Widening: Warner to St. Andrew RCP 16/17 Section 3: The City Council appoints the City Manager, or the Executive Director of the Public Works Agency or his designee, as agent for the City of Santa Ana to conduct all negotiations, execute and submit all documents, including but not limited to applications, agreements, amendments, payment requests and so on, which may be necessary for allocation of the requested funds to Santa Ana. Section 4: This Resolution shall take effect immediately upon its adoption by the City Council, and the Clerk of the Council shall attest to and certify the vote adopting this Resolution. ADOPTED this day of 2014. Miguel A. Pulido Mayor APPROVED AS TO FORM: Sonia R. Carvalho, City Attorney B : < first last > Reso#2014- Page 2 of 3 Assistant City Attorney AYES: Councilmembers NOES: Councilmembers ABSTAIN: Councilmembers NOT PRESENT: Councilmembers CERTIFICATE OF ORIGINALITY I, Maria D. Huizar, Clerk of the Council, do hereby certify the attached Resolution No. 2013 - to be the original resolution adopted by the City Council of the City of Santa Ana on , 2013. Date: Clerk of the Council City of Santa Ana Reso#2014 Page 3 of 3 September 18,2014 Mr.Vinh Nguyen, P.E. Sr. Civil Engineer City of Santa Ana PWA—Transportation&Traffic Engineering 20 Civic Center Plaza, M-43 Santa Ana,CA 92702 Subject: 17th/Westminster Avenue Corridor Traffic Signal Synchronization Project Dear Mr. Nguyen: This letter is in support of the traffic signal coordination efforts along 17th/Westminster Avenue application for funding under the Orange County Transportation Authority's Regional Traffic Signal Synchronization Program.The signal synchronization on 17th/Westminster Avenue from Apollo Drive to Newport Beach Boulevard will reduce stops,delays and improve travel times along this heavily traveled corridor. The City of Seal Beach is in support of the City of Santa Ana's effort in pursuing Renewed Measure M funds for this project. If grant funds are awarded by OCTA,the City of Seal Beach intends to support this effort by seeking City Council adoption and approval of OCTA's cooperative agreement in support of implementing this project. Should you have questions regarding this matter, please call Cesar Rangel, Assistant Engineer at (562) 431-2527 ext. 1328 or by e-mail at crangel a sealbeach.ca.gov. Sincerely, 4A Michael Ho, P.E. Deputy Director of Public Works/City Engineer City of Seal Beach m City of Westminster 8200 Westminster Boulevard,Westminster,CA 92683114.898.3311 www.westminster-ca.gov ,. TRI TA Mayor MARGIE L.RICE October 16,2014 Mayor Pro Tern DIANA LEE CAREY Vinh Nguyen, P.E. Council Member City of Santa Ana PWA-Transportation&Traffic Engineering uGIO RAS Co Membe r 20 Civic Center Plaza, M-43 Council Member Santa Ana, CA 92702 ANDY HACH Subject: Westminster Blvd/17th St Corridor Traffic Signal Synchronization Project Council Member EDDIE MINIM City Manager Dear Mr. Nguyen: i This letter is in support of your application for funding for traffic signal coordination efforts along Westminster Boulevard/171h Street under the Orange County Transportation Authority's Regional Traffic Signal Synchronization Program. The signal synchronization on Westminster Boulevard/171h Street from Apollo Drive in Seal Beach to Newport Avenue in the County of Orange will improve travel times along with reducing stops and delays along this heavily traveled corridor. The City of Westminster is in support of the City of Santa Ana's effort in pursuing Renewed Measure M funds for this project. If grant funds are awarded by OCTA, the City of Westminster is committed to providing the required matching funds and will seek City Council adoption of OCTA's cooperative agreement in support of implementing this project. If you have any questions,please contact me at(714) 548-3462. Sincerely, PUBLIC WORKS DEPARTMENT Traffic engineering Divisi m e _ ..._._..... Adolfo Oeta, P E ,T.E. City Traffic Engineer' CC: File 'P (,f GARDEN GROVE CITY OF GARDEN GROVE Bruce A. Broadwater Dina Nguyen Steven IR iouwues October 6, 2014 Chir°'iS9:DII-AIETV, Phain Mr. Vinh Nguyen, P.E. Krrl ,n Beard Sr. Civil Engineer City of Santa Ana PWA - Transportation &Traffic Engineering 20 Civic Center Plaza, M-43 Santa Ana, CA 92702 RE: WESTMINSTER AVE. CORRIDOR TRAFFIC SIGNAL SYNCHRONIZATION PROJECT P APPLICATION Dear Mr. Nguyen: The purpose of this letter is to indicate our support for the Westminster Avenue/17th Street Corridor Traffic Signal Synchronization Project as submitted by the City of Santa Ana in the Regional Traffic Signal Synchronization Program (Project P). The City of Garden Grove will be contributing 20% of matching funds. This project, to improve the traffic signal system on Westminster Avenue/17th Street, will include fourteen signalized intersections within the City of Garden Grove, which will benefit local and regional traffic. If you have any questions or require additional information, please contact Mr. Tony Aquino at (714) 741-5193. Sincerely, ,J ony W�vt bin E. raffi gin r 11222 Acacia Parkway P.O.Box 3070 Garden Grove, CA 92842 www.ci.garden-grove.ca.us Department of Public Works Douglas S. Stack, P.E. Director October 9, 2014 Mr. Edwin "William" Galvez, City Engineer Public Works Agency City of Santa Ana Public Works Agency, M-21 P.O. Box 1988 Santa Ana, CA 92702 Subject: Letter of Intent for Regional Traffic Signal Synchronization Program Application — Seventeenth Street/Westminster Avenue Dear Mr. Godinez: The Orange County Transportation Authority (OCTA) has issued the 2014 Call for Projects under Project P for the Regional Traffic Signal Synchronization Program to coordinate traff'i'c signals across jurisdictional boundaries in the county. The City of Tustin, in collaboration with the City of Santa Ana and other participating agencies, identified the Seventeenth Street/Westminster Avenue corridor for a Project P application. Within the City of Tustin the project would include existing traffic signals and interconnect on Seventeenth Street between Prospect Avenue and the SR 55 Freeway. The City of Tustin is in support of the City of Santa Ana's lead in submitting an application for Renewed Measure M funds for this project. Tustin is committed to provide the required matching funds and will be seeking City Council adoption of a resolution on November 18, 2014 in support of implementing and funding this project. We will forward the adopted resolution to the OCTA as soon as it is available. Sincerely, 41'i Ken Nishikawa Deputy Director of Public Works/Engineering C: Krys Saldivar,Public Works Manager Vinh Nguyen, City of Santa Ana Anup Kulkarni, OCTA Ron Keith,OCTA S:\Transportation Engineering\OCTA\Letter of Intent for Seventeenth Street Sync. Proj.P doc 300 Centennial Way, Tustin, CA 92780 • P: (714) 573-3150 0 F: (714) 734-8991 • WWW.tustinca.org RESOLUTION OF THE BOARD OF SUPERVISORS OF ORANGE COUNTY, CALIFORNIA October 23, 2012 WHEREAS, the County of Orange desires to imp lement!participate in traffic signal synchronization projects that are eligible for the Renewed Measure M Regional Traffic Signal Synchronization Program, one of the Comprehensive Transportation Funding Programs administered by Orange County Transportation Authority; and WHEREAS, the County of Orange supports the funding applications for such traffic signal synchronization projects; and WHEREAS, the Renewed Measure M Regional Traffic Signal Synchronization Program targets over 2000 signalized intersections across Orange County to maintain traffic signal synchronization, improve traffic flow, and reduce congestion across jurisdictions; and WHEREAS, the County of Orange has been declared by the Orange County Transportation Authoritv to meet the eligibility requirements to receive revenues as part of Renewed Measure M; and WHEREAS, the County of Orange has a currently adopted Local Signal Synchronization Plan consistent with the Regional Traffic Signal Synchronization Master Plan as a key component of local agencies' efforts to synchronize traffic signals across local agencies' boundaries; and WHEREAS, the County of Orange will provide matching funds or in-kind services for each project as required by the Comprehensive Transportation Funding Programs Guidelines; and WHEREAS, the County of Orange will not use Measure M funds to supplant Developer Fees or other commitments; and WHEREAS, OC Public Works will request approval from the County's Board of Supervisors to submit a funding application for each eligible project for the Renewed Measure M Regional Traffic Signal Synchronization Program; and WHEREAS, the Director of OC Public Works or designee requests authority for the duration of the Regional Traffic Signal Synchronization Program to file applications for the Renewed Measure Resolution No. 12-156, Item No. 18 M2 Regional Traffic Signal Synchronization Program Page IofI M Regional Traffic Signal Synchronization Program, to sign such applications, and to invoice the Orange County Transportation Authority for payment of allocated funds as appropriate. NOW, THEREFORE, BE IT RESOLVED that this Board does hereby: 1. Request the Orange County Transportation Authority to allocate funds in the amounts specified in each County's application for the Regional Traffic Signal Synchronization Program. Said funds shall be matched by funds from the County of Orange as required and shall be used as supplemental funding to aid the County in each signal synchronization project eligible for the Renewed Measure M Regional Traffic Signal Synchronization Program. 2. Authorize the Director of OC Public Works or designee for the duration of the Regional Traffic Signal Synchronization Program to file applications for the Renewed Measure M Regional Traffic Signal Synchronization Program, to sign such applications, and to invoice the Orange County Transportation Authority for payment of allocated funds as appropriate. Resolution No. 12-156, Item No. 18 M2 Regional Traffic Signal Synchronization Program Page 2 of 2 The foregoing was passed and adopted by the following vote of the Orange County Board of Supervisors, on October 23, 2012, to wit: AYES: Supervisors: JANET NGUYEN,SHAWN NELSON, BILL CAMPBELL PATRICIA BATES,JOHN M. W. MOORLACH NOES: Supervisor(s): EXCUSED: Supervisor(s): ABSTAINED: Supervisor(s): CHAIRMAN STATE OF CALIFORNIA ) COUNTY OF ORANGE ) I,SUSAN NOVAK,Clerk of the Board of Orange County,California,hereby certify that a copy of this document has been delivered to the Chairman of the Board and that the above and foregoing Resolution was duly and regularly adopted by the Orange County Board of Supervisors gor IN WITNESS WHEREOF, I have hereto set my hand and seal. , SU S AN`"N0 V A K Clerk of the Board County of Orange,State of California Resolution No: 12-156 Agenda Date: 10/23,12012 Item No: 18 t certify that the foregoing is a true and correct copy of the Resolution adopted by the Board of Supervisors, Orange County.State of California Susan Novak,Clerk of the and tat Supprvisors By� r � �.r � Deputy APPENDIX B Improvements Detail Costs 22 K..9 ------------- Z�m ,4f 4 ww VF-—— lw uW V,'M',X 5t R R 10 U, f R f 4n wE '2 A E" E 5 L9 Ma I � moms 1 wry NRv.. . --- .- — W ...�..u i Malawi all R I r f� I — — 1.. 1 1 T _.w. II I g� I E yr r� m w a.n Gi 9 E� I o y m m r � r m m n I o � I 9 a g RR I AT N m rill 13 all 7 U a T,' n lki q§gel 'v I= 011 ... t J f I .. zu . .5 RPM. w ' ¢ F rm s ag M w �„h h °x a F: i r _ y c GPs vents nw � ,. 8 7 pm L 9 Ov— µ ,7 i �p we. r ,S L a` i z 6 k u A,.0 7A a U 7r _ s M �7 ax��ar��s rr o� a ar ' s ;'' A R a NN ZEN M nM q 77 ," ° ^+� n dmmm gm gig' � 4 R �I s� 8 T d �� �#„ ra w w w w a z .�.�4 M r Ma I a .R .P Ji $ q _ t rw Ai x 0 ...... a �. .. ,. � — R cx .n rA . . 44 K s � IL........... 9i Sk. =I:. 1 � Rim slim Iris OR IR T,1 . .............. . ......-A-L-- ----- , L a I � W I .. NMI, s 1 9 -------- ---- Ell--- R ir 1-01 1 wa . r , 1 x n All, am M O 9. .. F� s�l E ---- � Jill 11 1 A I I ,o ' ` .. N Hum v, n q _..... .. --- ,.._...s.._ 0 u � � l I ILIA s w MITI Corridor: Westminster Ave-17th St No Agency Intersection ADT Distance(mile) VMT 1 Seal Beach Westminster Ave Appolo Dr 0 0 2 Seal Beach Westminster Ave Road B 26998 0.22 3 Seal Beach Westminster Ave Seal Beach Blvd 26998 0.33 4 Seal Beach Westminster Ave Kitt Hwy 25672 0.17 5 Westminster Westminster Ave Bolsa Chica Blvd 25672 1.86 6 Westminster Westminster Ave University 16000 0.37 7 Westminster Westminster Ave Milan St 16000 0.16 8 Westminster Westminster Ave Rancho Rd Hammon PI 16000 0.19 9 Westminster Westminster Ave Springdale St 28000 0.31 10 Westminster Westminster Ave Willow Ln 37000 0.33 11 Westminster Westminster Ave Edward St 37000 0.17 12 Westminster Westminster Ave Westmart Ln 38000 0.18 13 Westminster Westminster Ave CommerceLn 38000 0.19 14 Westminster Westminster Ave Goldenwest St 38000 0.14 15 Westminster Westminster Ave Olive St 27000 0.37 16 Westminster Westminster Ave Hoover 5t 27000 0.13 17 Westminster(Caltrans) Westminster Ave Beach Blvd 34000 0.5 18 Westminster Westminster Ave Monroe St/All American Wy 30000 0.25 19 Westminster Westminster Ave Newland St 28,997 0.25 20 Westminster Westminster Ave Magnolia St 28,835 0.49 21 Garden Grove Westm i nster Ave Deodara Dr/Swan St 28,835 0.39 22 Garden Grove Westminster Ave Bushard St 30,674 0.12 23 Garden Grove Westminster Ave Kerry St 30,674 0.28 24 Garden Grove Westminster Ave BrookhurstSt 29,079 0.22 25 Garden Grove Westminster Ave Dawson St/Hope St 29,079 0.25 26 Garden Grove WestminsterAve Bowen St 29,079 0.18 27 r" rden Grove U/ T -ter Ave r? ST„ 79,079 0.32 28 Garden Grove Westminster Ave Euclid St 24,784 0.25 29 Santa Ana Westminster Ave Newhope St 29,079 0.5 30 Santa Ana Westminster Ave Harbor Blvd 27,834 0.5 31 Santa Ana Westminster Ave Clinton St 28,132 0.5 32 Garden Grove Westminster Ave Roxey Dr 29,299 0.13 33 Santa Ana Westminster Ave/17th St Fairview 29,299 0.37 34 Santa Ana 17th St King St 34,548 0.29 35 Santa Ana 17th St English St 34,548 0.07 36 Santa Ana 17th St Alona St 34,353 0.17 37 Santa Ana 17th St College Ave 34,353 0.12 38 Santa Ana 17th St Bristol Market/Santa Ana College 34,353 0.18 39 Santa Ana 17th St Bristol St 34,353 0.2 40 Santa Ana 17th St Fire Station 38,,111 0.4 41 Santa Ana 17th St Flower St 38,111 0.09 42 Santa Ana 17th St Ross St 39,047 0.23 43 Santa Ana 17th St Broadway 41,020 0.16 44 Santa Ana 17th St Main St 40,054 0.12 45 Santa Ana 17th St Spurgeon St 41,351 0.14 46 Santa Ana 17th 5t Penn Wy 41,351 0.11 47 Santa Ana(Caltrans) 17th St Santiago St/1-5 NB Off-ramp 41,351 0.18 48 Santa Ana 17th St Lincoln Ave 33,025 0.23 49 Santa Ana 17th St Grand Ave 32,057 0.24 50 Santa Ana 17th St Linwood Ave 32,012 0.18 51 Santa Ana 17th St Sherry Ln/Cabrillo Park Dr 32,012 0.41 52 Santa Ana 17th St Centre on 17th 30,525 0.27 53 Santa Ana 17th St Tustin Ave 30,525 0.16 54 Orange County(Caltrans) 17th St Deodar St/SR-55 5B On-ramp 45,545 0.12 55 Tustin(Caltrans) 17th St SR-55 NB Off-ramp 45,545 0.14 56 Tustin 17th St Caroll Wy/Yorba St 32,,000 0.03 57 Tustin 17th St Yorba St/Enderle Center Dr 32,000 0.12 58 Tustin Yorba St Vandenburg Ln 59 Orange County 17th St Laurinda Wy/Prospect Ave 32,000 0.27 60 Orange County 17th St Holt Ave 27,000 0.38 61 Orange County 17th St Esplanade Ave 24,000 0.13 62 Orange County 17th St Hewes Ave 23,000 0.32 63 Orange County 17th St Newport Ave 22,,000 0.25 Total 16.33 0 Corridor: Westminster/17th Agency: City of Seal Beach Category Description Unit Quantity Unit Cost Amount Sub-total Intersection Total Intersectiow APOLLO DR. Upgrade to McCain 2070L traffic controller L LS 1 $ 3,500.00 $3,500 Intersection/Field Install new CCTV camera w/Cohu Helios 3920 HD LS 1 $10,000.00 $10,000 $13,500 System Upgrade Install new 36 SMFO cable from Apollo Dr.to Road B LF 1500 $ 10.00 $15,000 $56,710 in existing 3-inch PVC conduit Communication Terminiate new 36 SMFO cable EA 1 $ 700.00 $700 $18,210 Upgrade Install new Ethernet switch EA 1 $ 2,500.00 $2,500 Install new CAT5E ethernet patch cable(3 feet) EA 1 $ 10.00 $10 Detection Upgrade Install new Iteris video detection system LS 1 S25,000.00 $25,000 $25,000 Intersection: ROAD B U2grade to McCain 2070L traffic controller LS 1 $ 3,500.00 $3,500 Intersection/Field Install new CCTV camera w/Cohu Helios 3920 HD LS 1 $10,000.00 $10,000 $13,500 System Upgrade Install new 36 SMFO cable from Road B to Seal Beach LF 1500 $ 10.00 $15,000 $56,710 Blvd.in existing 3-inch PVC conduit Communication Terminiate new 36 SMFO cable EA 1 $ 700.00 $700 $18,210 Upgrade Install new Ethernet switch EA 1 $ 2,500.00 $2,500 Install new CAT5E ethernet patch cable(3 feet) EA 1 $ 10.00 $10 Install new Iteris video detection system LS 1 $25,000.00 $25,000 Detection Upgrade $25,000 Intersection:"SEAL BEACH BLVD. Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $10,000.00 $10,000 Intersection/Field HD $10,000 System Upgrade $0 $0 $25,000 Upgrade existing video detection w/Iteris Vantage Ls 1 $15,000.00 $15,000 Vector Detection Upgrade $0 $15,000 $0 Intersection: KITTS HWY Upgrade to McCain 2070L traffic controller LS 1 $ 3,500.00 $3,500 Intersection/Field Install new CCTV camera w/Cohu Helios 3920 HD LS 1 $10,000.00 $10,000 System Upgrade $13,500 Install new 36 SMFO cable from Kitts Hwy to Seal LF 1100 $ 10.00 $11,000 Beach Blvd.in existing 3-inch PVC conduit Communication Terminate new 36 SMFO cable EA 1 $ 700.00 $700 $14,210 $52,710 Upgrade Install new Ethernet switch EA 1 $ 2,500.00 $2,500 Install new CAT5E ethernet patch cable(3 feet) EA 1 $ 10.00 $10 Install new Iteris video detection system LS 1 $25,000.00 $25,000 Detection Upgrade $25,000 Total $191,130 Corridor: Westminster/17th Agency: City of Westminster Category Description Unit Intersection g N P Quantity Unit Cost Amount Sub-total Total Intersection: Westminster and Bolsa Chica Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $10,000 $10,000 $10,000 System Upgrade $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote Communication communications modules(Includes EM cables, $16,700 Upgrade ethernet patch cable,multi-Video cable,ethernet EA 1 $3,200 $3,200 $6,700 crossover cable,null modem serial cable,USB mouse, software,&manual) $0 Intersection:Westminster and Milan Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $10,000 $1Q000 System Upgrade $0 $10,000 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote $16,700 Communication communications modules(Includes EM cables, ethernet patch cable,multi-Video cable,ethernet $6,700 Upgrade crossover cable,null modem serial cable,USB mouse, EA 1 $3,200 $3,200 software,&manual) $0 Intersection: Westminster and Rancho Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $ $10,000 $10,000 System Upgrade $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote Communication communications modules(Includes EM cables, $16,700 Upgrade ethernet patch cable,multi-Video cable,ethernet EA 1 $3,200 $3,200 $6,700 crossover cable,null modem serial cable,USB mouse, software,&manual) $0 Intersection:Westminster and Springdale Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $10,000 $10,000 $10,000 System Upgrade $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote $16,700 Communication communications modules(Includes EM cables, ethernet patch cable,multi-Video cable,ethernet $6,700 Upgrade crossover cable,null modem serial cable,USB mouse, EA 1 $3,200 $3,200 software,&manual) $0 Intersection: Westminster and Edwards Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $10,000 $10,000 $10,000 System Upgrade $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 w/Hardened Power Supply) Corridor:Westminster/17th Agency:City of Westminster Category Description Unit Intersection g ry p Quantity Unit Cost' Amount Sub-total Total Iteris Vantage EdgeConnect quad-view remote Communication communications modules(Includes EM cables, $16,700 Upgrade ethernet patch cable,multi-Video cable,ethernet EA 1 $3,200 $3,200 $6,700 crossover cable,null modem serial cable,USB mouse, software,&manual) $0 � Intersection:Westminster and Westmart Replace cabinet w/Type 333L cabinet and Type II LS 1 $30,000 $30,000 Service Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 $40,000 System Upgrade HD-HDTV H.264 dome camera(Model:HD25-3000) LS 1 $10,000 $10,000 $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 $46,700 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote Communication communications modules(Includes EM cables, ethernet patch cable,multi-Video cable,ethernet $6,700 Upgrade crossover cable,null modem serial cable,USB mouse, EA 1 $3,200 $3,200 software,&manual) $0 Intersection: Westminster and Goldenwest Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 LS 1 $10,000 $10,000 $10,000 System Upgrade $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote Communication communications modules(Includes EM cables, $16,700 ethernet patch cable,multi-Video cable,ethernet $6,700 Upgrade crossover cable,null modem serial cable,USB mouse, EA 1 $3,200 $3,200 software,&manual) $0 Intersection:Westminster and Magnolia Intersection/Field Replace existing CCTV camera wl Cohu Helios 3920 LS 1 $10,000 $10,000 $10,000 System Upgrade $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB EA 1 $3,500 $3,500 w/Hardened Power Supply) Iteris Vantage EdgeConnect quad-view remote Communication communications modules(Includes EM cables, $16,700 Upgrade ethernet patch cable,multi-Video cable,ethernet EA 1 $3,200 $3,200 $6,700 crossover cable,null modem serial cable,USB mouse, software,&manual) $0 Intersection: TMC Monitor Wall Upgrade LS 1 $59,100 $59,100 Congestion Map and Travel Time System Integration LS 1 $37,500 $37,500 $96,600 TMC Upgrade $0 $96,600 $0 $0 Total $260,200 Corridor:Westminster-17th Agency,City of Garden Grove Category Description Unit Intersection g ry p Quantity Unit Cost ' Amount Sub-total Total Intersection: Deodara/Swan Communication Ethernet Switch EA 1 2500 $2,500 $2,500 Upgrade $0 $27,500 Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 $0 Intersection: Bushard Communication Ethernet Switch EA 1 2500 $2,500 $2,500 Upgrade $0 $27,500 Detection Upgrade Video Dection LS 1 25000 $2$000 $25,000 Intersection: Kerry Intersection/Field iPed Upgrade LS 1 2700 $2,700 $2,700 System Upgrade $0 Communication Ethernet Switch EA 1 2500 $2,500 $30,200 Upgrade $0 $2,500 Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 $0 Intersection: Brookhurst Intersection/Field EVP LS 1 7000 $7,000 System Upgrade Fed Upgrade LS 1 3600 $3,600 $10,600 $0 38 100 Communication Ethernet Switch EA 1 2500 $2,500 $ ' $2,500 Upgrade $0 Detection Upgrade Video Dection LS 1 25000 $2$,0000 $25,000 Intersection.Dawson/Hope Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 $25,000 $0 Intersection: Bowen Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 $25,000 Intersection:Taft Cabinet EA 1 a $21,000 Intersection/Field MMU EA 1 $1,000 System Upgrade Fed Upgrade LS 1 $3,400 $32,400 EVP LS 1 $7,000 $59,900 $0 Communication Ethernet Switch EA 1 $2,500 $2,500 Upgrade $0 Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 Intersection: Euclid Intersection/Field Ped Upgrade LS 1 6800 $6,800 EVP EA 1 7000 $7,000 $13,800 System Upgrade $0 $41,300 2500 $2,500 Communication Ethernet Switch EA 1 $2,500 Upgrade $0 Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 $0 Intersection: Roxey Cabinet EA 1 21000 $21,000 Fed Upgrade LS 1 5100 $5,100 Intersection/Field EVP LS 1 7000 $7,000 $41,600 System Upgrade MMU EA 1 1000 $1,000 $66,600 Traffic Signal Controller EA 1 7000 $7,000 GPS Clock EA 1 500 1 . $500 Detection Upgrade Video Dection LS 1 25000 $25,000 $25,000 $0 Total "$341,100 Corridor:Westminster Ave/17th St Agency: City of Santa Ana Category ry S stem Improvements Unit Quantity Unit Cost Amount Sub-total Intersection Total Intersection: Westminster Ave&Newhope St Blufax Travel Time System EA 1 $4,500 $4,500 Replace existing CCTV camera w/Cchu Helios 3920 HD- Intersection/Field EA 1 $10,000 $10,000 System upgrade HDTV H.264 dome camera(Model:HD25-3000) $14,500 Install Corning CCS-01U FDU(including connectors and trays)and Terminate 24-SMFO EA 1 $2,000 $2,000 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/ EA 1 $3,500 $3,500 Communication Hardened Power Supply) Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $6,420 $23,920 Upgrade Fiber Optic Patch Cable SC-SC,2 Meter) EA 2 S50 $100 CAT5E Ethernet Patch Cable(3 Feet) EA 2 $10 $20 2U 16"Component Shelf for 19"EIA Equipment Rack EA 1 $300 $300 Install 1 System Detection Type E Loop and 1-DLC for EB EA 1 $1,500 $1,500 Detection Upgrade Install 1 System Detection Type E Loop and 1-DLC for WB EA 1 $1,500 $1,500 $3,000 $0 Intersection: Westminster Ave&Harbor Blvd Upgrade controller card to Econolite 2070 ATC controller EA 1 Intersection/Field $1,500 $1,500 System upgrade SO $1,500 $O Install outdoor rated CAT5E cable from TS cabinet to LS 1 $1,000 $1,000 CCTV/HUB cabinet Communication Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/ EA 1 $3,500 $3,500 Upgrade Hardened Power Supply) $4,620 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 $12,120 CAT5E Ethernet Patch Cable(3 Feet) EA 2 $10 $20 $O Install 1 System Detection Type E Loop and 1-DLC for EB EA 1 $1,500 $1,500 Install 1 System Detection Type E Loop and 1-DLC for WB EA 1 $1,500 $1,500 Detection Upgrade Install 1-DLC for SBSystem Detection EA 1 $1,500 $1,500 $6,000 Install 1 System Detection Type E Loop and 1-DLC for NB EA 1 $1,500 $1,500 $0 Intersection: Westminster Ave&Clinton St $0 $0 $0 Intersection: Westminster Ave&Fairview St Intersection/Field Replace existing CCTV camera w/Cohu Helios 3920 HD- EA 1 $10,000 $10,000 System upgrade Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 $11,500 $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/ EA 1 $3,500 $3,500 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 $45,120 Communication CAT5E Ethernet Patch Cable(3 Feet) EA 2 $10 $20 $36,620 Upgrade Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 Install 24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 Install Corning CCS-03U FDU(including connectors and trays)and Terminate(2)24-SMFO EA 1 $3,000 $3,000 Intersection: 17th St&King St Intersection/Field Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 Guctom nnornrla I 1 $0 $1,500 Corridor: Westminster Ave/17th St Agency:City of Santa Ana Intersection Cate o N System Improvements Unit Quantity Unit Cost Amount Sub-total Total $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 $37,620 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 $36,120 Upgrade Install24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice EA 1 $2,000 $2,000 Fiber Optic Cable Intersection: 17th St&English St Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 Communication $36,120 Install 24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 $36,120 Upgrade Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice EA 1 $2,000 52,000 Fiber Optic Cable Intersection, 17th St&Alona St Replace cabinet w/Type 332 cabinet,Type I I Service and LS 1 $30,000 $30,000 Foundation Intersection/Field $38,500 System upgrade Southern California Edison New Service Fee EA 1 $4,000 $4,000 Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 11 $100 $75,120 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Power Distribution Unit(APC-AP7900) EA 1 $500 $500 Communication Upgrade Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 $36,620 Install 24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cable EA 1 $2,000 $2,000 Intersection: 17th St&College Ave Replace cabinet w/Type 332 cabinet,Type II Service and Foundation LS 1 $30,000 $30,000 Intersection/Field Southern California Edison New Service Fee EA 1 $4,000 $4,000 System upgrade Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 $48,500 Install Cohu Helios 3920 HD-HDTV H.264 dome camera (Model:HD25-3000) EA 1 $10,000 $10,000 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) $85,120 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 Uoerade Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 1 $36,620 Corridor: Westminster Ave/17th St Agency: City of Santa Ana Category System Improvements Unit Quantity Unit Cost Amount Sub-total Intersection Total Install 24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice EA 1 $2,000 $2,000 Fiber Optic Cable Intersection: 17th St&Santa Ana College/Bristol Marketplace Intersection/Field Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 System upgrade $0 $1,500 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 $38,120 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 Upgrade Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 $36,620 Install 24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cable EA 1 $2,000 $2,000 Intersection: 17th St&Bristol St Replace existing CCTV camera w/Cohu Helios 3920 HD- Intersection/Field HDTV H.264 dome camera(Model:HD25-3000) EA 1 $10,000 $10,000 System upgrade Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 $11,500 $0 Install 4"PVC Conduit(includes necessary pullbox) LF 600 $45 $27,000 $45,500 Install 24-Single Mode Fiber Optic Cable LF 1000 $3 $3,000 Communication Install Corning CCS-04U&CSH-05U-F FDU(including Upgrade connectors and trays)and Terminate(4)24-SMFO EA 1 $4,000 $4,000 $34,000 Intersection: 17th St&Fire Station No. Replace cabinet w/Type 332 cabinet,Type II Service and LS 1 $30,000 $30,000 Foundation Intersection/Field 'Southern California Edison New Service Fee EA 1 $4,000 $4,000 System upgrade Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 $38,500 $O $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2000 $2000 Hardened Power Supply) , , $46,020 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $7,520 Upgrade Install 12-SMFO in existing conduit LF 300 $3 $900 Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cable EA 1 $2,000 $2,000 Intersection: 17th St&Flower St Replace existing CCTV camera w/Cohu Helios 3920 HD EA 1 $10,000 $10,000 Intersection/Field HDTV H.264 dome camera Model:HD25-3000 $11,500 System upgrade Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 $0 Corridor: Westminster Ave/17th St Agency: City of Santa Ana Category ry S stem Improvements Unit Quantity Unit Cost Amount Sub-total Intersection Total Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 $14,120 Hardened Power Supply) Communication Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 $2,620 Upgrade CATSE Ethernet Patch Cable(3 Feet) EA l 2 $10 $20 Power Distribution Unit(APC-AP7900) EA 11 1 $500 $500 $0 Intersection: 17th St&Ross St Replace cabinet w/Type 332 cabinet,Type II Service and LS Foundation 1 $30,000 $30,000 Intersection/Field Southern California Edison New Service Fee EA 1 $4,000 $4,000 $38,500 System upgrade Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 $0 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) $46,020 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $7,520 Upgrade Install 12-SMFO in existing conduit LF 300 $3 $900 Install Corning CCS-01U(including connectors and trays) and Terminate 24-SMFO EA 1 $2,000 $2,000 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cabie EA 1 $2,000 $2,000 Intersection: 17th St&Broadway Replace existing CCTV camera w/Cohu Helios 3920 HD HDTV H.264 dome camera(Model:HD25-3000) EA 1 $10,000 $10,000 Intersection/Field Power Distribution Unit(APC AP7900) EA 1 $500 $500 $12,000 $12,000 System upgrade Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 1 $1,500 $0 $0 ,Intersection: 17th St&Main St Replace cabinet w/Type 332 cabinet,Type It Service and LS 1 $30,000 $30,000 Foundation Intersection/Field Southern California Edison New Service Fee EA 1 $4,000 $4,000 System upgrade Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 $43,000 Blufax Travel Time System EA 1 $4,500 $4,500 $0 Install outdoor rated CATSE cable from TS cabinet to CCTV/Splice cabinet LS 1 $1,000 $1,000 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ $53,900 Communication Hardened Power Supply) EA 1 i $2,000 $2,000 $7,900 Upgrade Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Terminate 24-SMFO(including connectors and trays)in EA 1 $1,000 $1,000 existing FDU $0 Install 1 System Detection Type E Loop and 1-DLC for EB EA 1 $1,500 $1,500 Detection Upgrade Install 1 System Detection Type E Loop and 1-DLC for WB EA 1 $1,500 $1,500 $3,000 $0 Intersection: 17th St&Spurgeon St Replace cabinet w/Type 332 cabinet,Type II Service and LS 1 $30,000 $30,000 Foundation Intersection/Field Southern California Edison New Service Fee EA 1 $4,000 $4,000 Coo[nn Corridor: Westminster Ave/17th St Agency: City of Santa Ana Category ry S stem Improvements Unit Quantity Unit Cost Amount Sub total Intersection Total System upgrade Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 $0 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ Hardened Power Supply) EA 1 $2,000 $2,000 $49,020 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CAT5E Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $10,520 Upgrade Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cable EA 1 $2,000 $2,000 Furnish and Install Corning CCS-01U(including connectors and trays)and Terminate 24-SMFO EA 1 $2,000 $2,000 Intersection: 17th St&Penn Wy Replace cabinet w/Type 332 cabinet LS 1 $10,000 $10,000 Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 Intersection/Field Install Cohu Helios 3920 HD-HDTV H.264 dome camera System upgrade (Model:HD25-3000) EA 1 $10,000 $10,000 $21,500 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) $32,020 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CAT5E Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 11 1 $500 $500 $10,520 Upgrade Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Install Splice Enclosure(including splice trays)and splice EA 1 $2,000 $2,000 Fiber Optic Cable Furnish and Install Corning CCS-01U(including connectors and trays)and Terminate 24-SMFO EA 1 $2,000 $2,000 Intersection: 17th St&Santiago St/1-5 NB On/Off Ramp Replace cabinet w/Type 332 cabinet LS 1 $10,000 $10,000 Intersection/Field rade controller card to Econolite 2070 ATC controller EA 1 System upgrade I Upgrade $1,500 $1,500 $11,500 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) $20,020 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 Communication CAT5E Ethernet Patch Cable(3 Feet) EA 2 $10 $20 $8 520 Upgrade Power Distribution Unit(APC-AP7900) EA 1 $500 $500 Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Furnish and Install Corning CCS-01U FDU(including connectors and trays)and Terminate 24-SMFO EA 1 $2,000 $2,000 Intersection: 17th St&Lincoln Ave Replace existing CCTV camera w/Cohu Helios 3920 HD- HDTV H.264 dome camera(Model:HD25-3000 EA 1 $10,000 $10,000 Intersection/Field ) $11,500 System upgrade Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ $18,020 Hardened Power Supply) EA 1 $2,000 $2,000 Communication Fiber Optic Patch Cable(SC SC,2 Meter) EA 2 $50 $100 Upgrade CATSE Ethernet Patch Cable(3 Feet) EA 2 $SO $20 $6,520 Power Distribution Unit(APC-AP7900) EA 1 $500 $500 Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Corridor:Westminster Ave/17th St Agency:City of Santa Ana Category ry S stem Improvements Unit Quantity Unit Cost Amount Sub-total Intersection Total Intersection: 17th St&Grand Ave Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 Intersection/Field System upgrade $0 $1,500 $0 Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $9,900 Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Communication Install Corning CCS-04U&CSH-05U-F FDU(including $8,400 Upgrade connectors and trays)and Terminate(4)24-SMFO EA 1 $4,000 $4,000 Intersection: 17th St&Linwood Ave Intersection/Field Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 System upgrade $0 $1,500 $0 i Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 $12,020 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $10,520 Upgrade Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cable EA 1 $2,000 $2,000 Furnish and Install Corning CCS-01U(including connectors and trays)and Terminate 24-SMFO EA 1 $2,000 $2,000 Intersection: 117th St&Cabrillo Park Dr/Sherry Ln Replace cabinet w/Type 332 cabinet,Type II Service and LS 1 $30,000 $30,000 Foundation Southern California Edison New Service Fee EA 1 $4,000 $4,000 Intersection/Field System upgrade Upgrade to Econolite 2070 ATC controller EA 1 $4,500 $4,500 $48,500 Install Cohu Helios 3920 HD-HDTV H.264 dome camera (Model:HD25-3000) EA 1 $10,000 $10,000 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) $59,020 Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 Upgrade Install 24-SMFO in existing conduit LF 1300 $3 $3,900 $10,520 Install Splice Enclosure(including splice trays)and splice Fiber Optic Cable EA 1 $2,000 $2,000 Furnish and Install Corning CCS-01U(including connectors and trays)and Terminate 24 SMFO EA 1 $2,000 $2,000 Intersection: 17th St&Centre on 17th Intersection/Field Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 System upgrade $1,500 $0 Fiber Optic Ethernet Switch(Etherwan EX71620-AOB w/ EA 1 $2,000 $2,000 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 $12,020 'CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Communication Power Distribution Unit(APC-AP7900) EA 1 $500 $500 $10,520 Upgrade Install 24-SMFO in existing conduit LF 1300 $3 $3,900 Install Splice Enclosure(including splice trays)and splice EA 1 $2,000 $2,000 Fiber Optic Cable Corridor: Westminster Ave/17th St Agency::City of Santa Ana Category System Improvements Unit Intersection g ry y p Quantity Unit Cost Amount Sub-total Total Furnish and Install Corning CCS-01U(including connectors and trays)and Terminate 24-SMFO EA 1 $2,000 $2,000 Intersection- 17th St&Tustin Ave Upgrade controller card to Econolite 2070 ATC controller EA 1 $1,500 $1,500 System upgrrade Intersection Field Blufax Travel Time System EA 1 $4,500 $4,500 $6,000 $0 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/ EA 1 $3,500 $3,500 Hardened Power Supply) Fiber Optic Patch Cable(SC-SC,2 Meter) EA 2 $50 $100 CATSE Ethernet Patch Cable(3 Feet) EA 2 $10 $20 Install 24-SMFO in existing conduit LF 1300 $3 $3,900 $35,370 Install Corning CCS-03U FDU(including connectors and Communication trays)and Terminate 24-SMFO EA 1 $2,500 $2,500 Upgrade g $29,370 Install 12-SMFO in existing conduit from 17th/Tustin to LF 3700 $3 $11,100 Tustin/Fruit Install Corning FDU(including connectors and trays)and Terminate 24-SMFO at Centre on 17th,Wellington,and EA 3 $2,000 $6,000 Fruit Install 4"PVC Conduit LF 1 50 $45 $2,250 Intersection: Traffic Management Center Video Management System Upgrade and Licensing LS 1 $50,000 $50,000 $50,000 TMC $0 $50,000 TOTAL $871,230 Corridor:Westminster/17th Agency:City of Tustin Category Description Unit Intersection g ry p Quantity Unit Cost Amount Sub-total Total Intersection:Yorba St/Carroll Wy Intersection/Field New ASC/3 Controller EA 1 3500 $3,500 System Upgrade $0 $3,500 $0 FO Distribution Unit,FO Switch and Ethernet Switch LS 1 4500 $4,500 $14,250 Communication No.6E Pullbox and Splice Closure EA 1 2500 $2,500 Upgrade Install FO cable in exist counduit LF 750 5 $3,750 $10,750 $0 $0 Intersection:Yorba St/Enderle Ctr Intersection/Field New ASC/3 Controller EA 1 3500 $3,500 System Upgrade $0 $3,500 $0 FO Distribution Unit,FO Switch and Ethernet Switch LS 1 4500 $4,500 $89,000 Communication No.6E Pullbox and Splice Closure EA 2 2500 $5,000 Upgrade Install FO cable in new counduit LF 1900 40 $76,000 $85,500 $0 $0 Intersection:Yorba St at Vandenburg Ln Intersection/Field New ASC/3 Controller EA 1 3500 $3,500 $0 $3,500 System Upgrade $0 FO Distribution Unit,FO Switch and Ethernet Switch LS 1 4500 $4,500 $14,750 Communication No.6E Pullbox and Splice Closure EA 1 2500 $2,500 Upgrade Install FO cable in existing counduit LF 850 5 $4,250 $11,250 $0 $0 Total $118,00, Corridor:Westminster/17th ABency:.Orange County 77Category Description Unit Quantity Unit Cost Amount Sub-total Intersection Total Intersectiow Prospect/LaurintNa Install new Controller and Cabinet w/Foundation upgrade LS 1 35,000 535,000 Install Type ll Service Cabinet LS 1 5,000 $5,000 Intersection/Field Install EVPs EA 6 3.,000 $18,000 $63,500 $63,500 System Upgrade Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/Hardened Power Supply)and EA 1 $5,500 $5,500 cables $o Intersection.Halt Ave Install 2,200'of 2"interconnect conduit from Holt to Prospect EA 2„200 33 ES72,600 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/Hardened Power Supply)and EA 1 $5,500 Communication ,cables $84,700 $84700 Upgrade (install 2,220'of new 24SMFO EA 2,200 $3 Intersection:Esplanade Install new Controller and Cabinet w/Foundation upgrade LS 1 35,000 S35,000 Intersection/Field Install EVPS EA 4 3,000 $12,000 System Upgrade $0 $47,000 $0 Install 850'of 2"interconnect conduit from Esplanade to Holt EA 850 33 $28,050 1 $83,100 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/Hardened Power Supply)and EA 1 $5,500 $5,500 Communication cables Upgrade Install 850'of new 72-SMFO EA 850 $3 $2,550 $36,100 So $o Intersection:Hewes Ave Intersection/Field Install new Controller LS 1 6,000 S6,000 System Upgrade 50 $6,000 $0 Install 1700"of 2"interconnect conduit from Hewes to Esplanade EA 1,700 S33 $56,100 $72,700 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/Hardened Power Supply)and EA 1 $5,500 $5,500 Communication cables - $66,700 Upgrade Install 1,700'of new 72 SMFO EA 1,700 $3 $5.,100 $0 $0 Intersection:Newport Ave .(install 1400'of 2"interconnect conduit from Newport Ave to Hewes Ave EA 1.,400 $33 $46,.200 Fiber Optic Ethernet Switch(Etherwan EX73242-ABB w/Hardened Power Supply)and EA 1 $5,500 $5,500 Communication cables -- $55,900 $55,900 Upgrade Install 1,400'of new 72-SMFO EA 1,400 $3 $4,200 $0 $0 Intersection:TMC TMC Equipments,Furnishings LS 1 28,,708 $28,708 Licensing,Software,System Integration and Support LS 1 10,000 510,000 $45,708 TMC Ethernet Hub at TMC EA 1 7,000 $7,000 $45,708 $0 $0 Total $405,608 Orangetrak- Edit Project Page I of 2 Q!4��%IAQ� �Qq TJ9 rWM KL)IL &L UAISCAG IF,W PREWQQS VERSION OF NJIS PROJE"T )CWUM8N APPLICATION NUMBER: CTFP TOTAL ALLOCATIONS: $2,820,102.00 TOTAL PROJECT COST $$,525,128.00 PROJECT ID: CP--3324 CTFP TOTAL PAYMENTS' $0.00 MATCH RATE 0.00 VERSION: 1 STATUS: Planned BOARD APPROVAL DATE LAST MODIFIED BY: Cesar Rodriguez(110122/2014) APPROVED BY: N/A HISTORY PROJECT INFORMATION WROVEMEETTYPF 1111 OEMENNIN 7aAr ,L ..............- 'NQ TSSP-Traffic Signal Syncronization Program V :, it ante A y of V .1 1, Re IF,f PF4 QT MIAN G�,R PHI I I T A m r y 5 tVi!n�hNguyen 7146475612 tng1uyen@santa-ana,or PROJECT rrTLE.— ...... ................ [W��enue/17th Street Corridor Traffic Signal Synchronizatfon PROJECT OF-SCRIPT12N, il ESL IN51 Westmin ter Ave/17th St Traffic Signal Synchronization project will coordinate the traffic signals along this corridor between six agencies. Designated as part of a Priority Corridnr by the Traffir! Signal Synchronization Master Plan, the project .................................................. SYSTEM 114'O41 J R E N 60CAL.9'rREFrNAm F QM Loot 1�/ P.�111 �AP Street astminster Ave/17th Street Apollo Drive LNewpart Boulavat] ..............=...................................................... GENERAL QUESTIONS CTFP QUESTIONS Is this application on your current approved measure M2 CIP? =YrS11- Has your agency previously received CTFP funding for this Application? If Yes,When? /A?I Project I D?I NIA Is this on agency's LOCAL SYNCHRONIZATION PLAN? FYES7-7 TSSP PROGRAM RULES: If Project is TSSP Program,it should be 20%MINIMUM Match PROGRAMMING INFORMATION($0) [HISTORICAL REVENUESt (GRAPH REVENUES? Please enter all funding required for the total project for all years.Note:This 2015 Call for Projects will allocate I M2 funds for FY15116,FY16/17,FY17118 only. **Minimum match for local funds is 20%— Actual Local Agency Match Rate is 20% FISCAL YEAR FUND TYPE(PROGRAMMED REVENUE SOURCE) PRIMARY ROW MAINTENANCE A TOTAL IMPLEMENTATION (DISABLED) MONITORING 1 22i-2t C—= $0 00 $0,00 $2,704,902 0 r Other E[-fBfg—,R��,a I ......... 1— $0 col=��E—K—L ........ [Fc,T`T Traffic ic-SF,-gn—al Lc.Progra TSS maintenance&Monitodng',,1 600 X 14�42 Other $0 00 = 060 E 40000 E==$ _Oj 777T E, F-:. $0.00 00 =-V: (Traffic Signal Sync Program(TSSP)-Maintenance&Monitoring Ev E=$0-00 E �g $57,600.00 $57,600 X V tv F------]=7---] 0 —-—------- ----i F-7--51 0 ...........-................ .................- ...................... -- ---------- E ==$0 https:Hocfundtracker.octa.net/ed it_proj ect.asp?proj ect-id=CP--3 3 24&version=I&stpl_fla... 10/22/2014 Traffic Signal Sync Program(TSSP)-Primary Implementation [= Other L:==so =giA Traffic Signal Sync Program(TSSP)-Maintenance&Monitoring Update SuGtotafs GRAND TOTAL SCHEDULE INFORMATION CONTRACT SCHEDULED START SCHEDULED COMPLETION STATUS AWARD/NOTICE ACTUAL FINAL REPORT TO PROCEED COMPLETION SUBMITTAL DATE MQUId YEAR MONTH YEAR MQNT H L� F:TA1 MAY 2016 ELAN PMRIIMJ%RY ........... .......................... 0�17 1v JPlanned MAINTENANCE& MQWMR.1NArJLFN VT2017 I [�E 1�01 9 IV an PROJECT ADJUSTMENTS LINK BOARD APPROVAL PHASE ACTION COMMENT DATE EDF EDf ELDE LAMNEWBDU NF gAnQU-LAST UPDATEO-,1WI512014 Call for project ............. ........................ SPELL CHECK.— LENTER SCORING DATA MARK ON MAP ' Save for Later Save and Submit to 06'f," I PRINT] CONTACT QQ.TA, 1401, EMAIL Qr,,, I 'R&C ERoM.PAECORIE86mv -QM https://ocfundtracker.octa.net/edit_project.asp?project__id=CP--3324&version=I&stpl—fla... 10/22/2014 urangetraK-Projecttcanxtng rage 1 of t MAtlN M N), CHANGE PASSWORD p LOG OUT p O TA p CAA Ram' PROJECT RANKING !AGENCY: Santa Ana, City of TITLE: Westminster Avenue/ 17th Street Corridor Traffic Signal Synchronization TSSP-Traffic Signal Svnchoronization Program POINTIS) Facility Usage _ Vehicle Miles Traveled (VMT) 477420 Y0 Cost/Benefit Ratio 3525128(Total Project Cost)/477420 (ADT)=7 11 Jurisdictions Percent of Priority Corridor Jurisdictions Involved 86 12 Total Number of Involved Jurisdictions 6 20 Jurisdictions Score(higher of two scores above) 20 Project Scale Percent of Corridor Signals Being Retimed 100 5 Number of Signals Being Retimed 63 5 Proiect Scale(Total) 10 Project Details Int./field system modernization and replacement Minor signal operational improvements Project Characteristics New or upgraded communication systems New or upgraded detection TMC/TOC and motorist information Real-time traffic actuated ops. and � demo, pr o j . � ..,. 10 Transportation f 9 cance 10 Maintenance oEffort None v 0 Project Effectiveness Current Project Readiness Withm�2 Months v 5 Funding Match p � � 0 SAVE RANKING CLOSE WIN __ .. DOW , PRINT TOTAL POINTS: 86 COrvB"rACT, CTA., 0.70s EMAIL OC FUN DTRACKERHELP OECOINTERACTIVE.COM https:Hoefundtracker.octa.net/ranking_edit.asp?project_id=CP--3324&version=l 10/22/2014