HomeMy WebLinkAboutSupplemental Information RE Item G Revised 5-Year CIP DocumentMEMO Department of Public Works June 13, 2016 To: Robin Roberts, City Clerk From: Michael Ho, Dep. Dir. PW /City Engineer SUBJECT 5 YEAR CIP AND AGENDA ITEM G STAFF REPORT 5 Year CIP Revisions were made after the agenda was posted to the 5 -Year CIP document. Attached are replacement pages to the document. Agenda Item G Staff Report Attachment C Attachment C, PEA has duplicate copies of the same PEA No. UK100002. Attached is the correct PEA No. UK100001. CIP PROCESS The Capital Improvement Program is comprised of construction projects and equipment purchases (excluding vehicles) which cost $10,000 or more. The CIP also includes activities that can be planned for or occur on an irregular or one time basis. Minor capital outlays of less than $10,000 and reoccurring maintenance activities will be included with the operation and maintenance budget. The Capital Improvement Program is a plan that identifies the capital projects to be funded during a five year planning horizon. The CIP is updated annually, and the first year of the plan serves as the current year capital budget. The CIP is a planning document to help City Council systematically schedule and finance capital projects to ensure cost - effectiveness as well as conformance with established policies. The CIP is organized into the same functional groups used for the operating programs. The CIP reflects a balance between capital replacement projects that repair, replace, or enhance existing facilities, equipment or infrastructure, and capital facility projects that significantly expand or add to the City's existing fixed assets. The CIP will emphasize project planning with projects typically progressing through the following phases: Identification of Project. Improvements within the Capital Improvement Plan are generated or identified as follows: Advanced planning: Most of the improvements are identified within a Planning document or Master Plan. Many master plans are required by funding agencies. All master plans are adopted by the City Council. Currently the City has master plans adopted as follows: • 2005 Sewer Master Plan (Currently being updated) • 2008 Master Plan of Drainage • 2010 Water Rate Study • 2011 Water Master Plan • 2011 Street Tree Master Plan 2011 Facility Master Plan • 2012 Fleet Management Plan 2013 Concrete Rehabilitation Master Plan • 2013 Park and Community Services Master Plan • 2014 Pavement Management Plan • 2015 Pier Condition Assessment • 2016 Urban Water Management Plan 2. Reaction to need or opportunity: Projects may originate through a need or opportunity. An example of a project that was delivered as a result of a need and opportunity is the El Nino Storm Prep that occurred this year. Desire from the community: Projects may originate through a desire from the community. One example in the proposed CIP is PCH and Anderson Landscaping Improvements project. ^a� ry� .'A w J �w °a wy 2 IF^ Z Z crL 7 G LL U)r U) m E U E Aa? All Yls' �Ai� F Y pti� PP ^4 s � qfy t firi � r cFf, F g� E W J Q d = F } Z Q �? U) W CL _ U i m m m m m .. v v v v m v m y v N d 0000000 0 o 0 0 0° e °o °o °o °o °oo °OO °oo ° ° °oo ° °oo °o o° °o °o °o aloo Q 000 N 19 19 w Yi w w W M Vi Vi w w w w w w w w w w e9 d) M w W w' M W N w di w N w I i o 0 o o ° N m N O O O O O O yaj N w w w w I i o o m II °o a 0 o e �pm N P a N wl I I w w w °o °o° °o ° 00 0 000000 o° ! CI ip d N �t 19 N N 19 w w aA w w w 19M w w w I I r 0 m a t I� N a m a «c .0 Q tt 3 E a am u °- E m Z A N m CL j 0 °' `m m ° O p W C LL E «u `v N o L m E .c 3 c r c o o `m m v U °°' v m «v v -° U 2 m W n a Nm Vitt cyUd u LLI�Um um LLmU m c= m 'o m UO ON N.�N� A� Um C NiW� °v LLNQ r a 0 m ¢` n ¢` ^NNp� U N N f N° via U N P N N P y O qim O O O N 'o a A a a r��� r r H F i= F F u '� f- t- F- LL•H a `a EL o .�: _, .. LL inmmmmN3h a m m m m ;imm33333333333 rm r mm c� (9lmmm vlm r�mmm �2 (56 6, b 0 C)-a LLI o o.000 -j D Lfi C3 LU r.- Lu a. U) 0 >. Z Z LL m U) IL "*' 0000000000 rn C;t R TR gilg� R go co c? CN (0 r- 0 M00 N M c: Z, Z3 AL 0 -W — -LL m Ex m mV a E k w v LL z Q cx L U- tn m 'am Co ID m In 0) 1 1 43 m It; M -C 00 z cn to i� �2 W J W w a LU} U U >- W of �a U) m a U N > >> O O° N N N N N N N N N N N N N N N N N N N N N N N N N N W N N N W W a0 m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o O O o 0 0 0 0 0 vi, 0 O 0 O 0 O 0 O 0 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 lO 0 O 0 O 0 O 0 O 0 O 0 Co... O O O O O 0 O 0 N tp O i Co Lp o 0 O V m O m r n n N N N N O O O E r m o O 1 N N o W N r r o N o O m O r O O O r d r m O m m n O m n O 1p m Vi f9 Vi Vi FA f9 FA fA f9 fA fA f9 f9 tl3 d3 fA fA k9 f9 (9 f9 i9 (A f9 fA W IA f9 4i f9 f9 W I I ti N a N O O O 0 o 0 O 0 O 0 O 0 O 0 O O O O ♦��i N' O Q N m n0'D O O Or �p O OIpNN O m O O m O N N O m N N t0 t0 N a` o �5., � N FA (9 e9 f9 t9 f9 f9 tH f9 N H O O 0 0 0 0 0 0 0 0 0 0 0 0 O O O O O O O O O O 0 0 0 0 0 0 O O O O a O m N ��� f9 f9 19 f9 f9 f9 f9 t9 fA W N O 0 0 0 0 0 0 O O O O O y O N O 0 0 0 0 0 0 O O O O O O O O - p O O O N O O 1(1 Ip N O N O O O O N O a m a N N t0 1N O_ d y a N Fq tl3 f9 fA M fA 69 fA fA Vi f9 W I 0 o O o 0 0 0 0 0 0 0 p) O 0 0 0 0 0 0 O O O O a 0 0000°0 0 0 0 0 yNj O N O O 1[] O O N O O O O O » we>»wen en w » w w 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o O o 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 m O 0 o o 0 O 0 o 0 0 0 0 0 0 0 0 0 o 0 vi N O) O m o OO Lnmm000moo�n N o- N m e �O o O 0 m o O Om000 r r O N O m r �c Yl p m N O On I � _ J a 0 0 0 N C O m L N Q1 f/J C T N v O N E .° E a > E m m °> n m m E p g 3 E Q x a m E o m E p e o m c N d a n E m am Eo m o m h c m u t y w K c pY c a m m m o m a > U w mm m m m c o a m= m c 1= Z U N a c y d v m a E L api rn cm d i t a n p m p c o C J m cm N 2 U-i N N m m U m m E b m m c a.c-p was" o m mac ani oa C N J N R' v EQA Q > � ¢ T° 3 j N U C N ° v >� v N c M C m N m j E m N N n T p p E m m E m c v >> a E E o.N 5 m N> m N aVNi m E E C C N Q C Q C Q C Q ij O d> W L O N T O __ O O O O O O _ O O O O �•' N d N m d �!] �(] [O (p m [p m [p F n n n n n n �N. O N N� N O n! o ! m a N � N ! O O � N 0 d N a ry d O 0 N ! Q � T O � ao N y o a O N ! 4 � 2 O � a� N a � y O 4 O N C n r c O a N a � n !O O Q N E T m d A 3 °ol °o 0 0 O O N N D LL N a d U d `0 3 m f T d m m d L d c O d O m a O F 3 i D LL d .n d U d L j c E m S m E d d A 6 C C O 3 i 0 H N C d N d m N 3 a LL N O d U `d O 0 °m O n a LL A 6 d U d 3 d c E d 'o E 3 D 3 d J N O 3 I' m 0 H c LL d n N U d d N t3 U d m O a d L d cr 3 d N 3 O m 0 H d N m E d N y c A c O L U N i i O 0 0 0 O 0 0 0 N O O O O O O O O O O O O O O N O N N ? o > > o F LL LL H 10 R n 'n U U m a �y3 u u m W 2 S U a T N N d N L A O 3 n a d 3 N d N N N 3 n 3 Y1 FY 2016/17 - 2020121 PROJECT CATEGORY Water System PROJECT No. WT0904 PROJECT NAME Booster Sta. Rehab. - Beverly Manor TOTAL PROJECT COST $5,200,000 PROJECT MANAGER David Spitz, Associate Engineer WORKED PERFORMED BY Contract LOCATION North Gate Road PROJECT STATUS Construction PRIORITY Nigh ALTERNATE FUNDING SOURCE None DESCRIPTION JUSTIFICATION This project will construct upgrades and improvements to the Beverly The water system requires continual capital maintenance to maintain reliability and to Manor Water Well, Booster Station and Reservoir as identified in the meet water quality standards. 2011 Water System Master Plan. On -going Operating & Maintenance Impact: It will eliminate the existing monthly maintenance cost '1 } /09. iL 4J �C:1T7ED y�i i� . F M4VJL w L ', Sr4TLDM "' .VFAFONS MAP Proposes Proposed Proposed Pmpased Proposed 2016-2017 2017 -2018 2018 -2019 2019 -2020 2020 -2021 Proposed Budget Budget Budget Budget Budget 5-year total Expenditures Design $ 231,000 $ 231,000 Construction $4,969,000 $4,969,000 TOTAL $5,200,000 $5,200,000 PICTURE 59 PROJECT CATEGORY Water System PROJECTNo. WT1501 PROJECT NAME Water Rate Study TOTAL PROJECT COST 880,000 PROJECT MANAGER Michael Ho City Engineer WORKED PERFORMED BY Consultant LOCATION City Wide PROJECT STATUS Planned PRIORITY High ALTERNATE FUNDING SOURCE NIA DESCRIPTION JUSTIFICATION The study will update the rate structure for the City's Potable Water The operation of the City's Water System is funded through a water enterprise fee System. that is charged to the residents bimonthly. The rate structure is typically studied and set approximately every 5 years. This will insure that the fee charged is appropriate for the services that are rendered. Ongoing Operating S Maintenance Impact None MAP Proposed Proposed Proposed Proposed Proposed 20162017 20r7-2018 201 &2019 20193020 2020 -2021 Pmposed Budget BedW Budget Budget Bvdp wear oral PICTURE DE PROJECT CATEGORY Water System PROJECTNO. W11603 PROJECT NAME Balsa Chips Weil Improvement Project TOTAL PROJECT COST $1,000.000 PROJECT MANAGER Cesar Rangel, Associate Engineer WORKED PERFORMED BY Contract LOCATION Balsa Chica Road PROJECTSTATUS Design PRIORITY Medium ALTERNATE FUNDING SOURCE None DESCRIPTION JUSTIFICATION This projectwill rehabilitate the well site pumps, generators, molars and water This project will rehabilitate the Balsa Chico Water Well as identified in the 2003 treatment equipment. Water System Master Plan. l�c'3�J Source On -going Operating & Maintenance Impact: Project wig eliminate the maintenance at Ne electrical pump 8 equipment MAP PICTURE Proposed Proposed Pmposetl Proposed Proposed 20162017 M11 -2018 20162019 20132020 20201 Proposed Expenditures Design $ 100,000 S 100,000 COnstrodion $ 900,000 $ 900.000 TOTAL $ 1.000,000 $1.000,000 63 -2020121 PROJECT CATEGORY Water System PROJECT NAME 7th Street Alley (PCH to N. Electric) PROJECT MANAGER Cesar Partial, Associate Engineer LOCATION Citywide PRIORITY Medium PROJECTNo. Wi1B07 TOTAL PROJECT COST a } rii d ea e� PROJECT STATUS Construction ALTERNATE FUNDING SOURCE ♦ 1,. yWt 1 i�v�..♦•`. api�.,r' r }.'-4Y �.._. t a }A �_ � �1 s .. 1 }[ .:. OSZ . r ^A}±LIk 1�'S 2L: -2020121 PROJECT CATEGORY Water System PROJECT NAME 7th Street Alley (PCH to N. Electric) PROJECT MANAGER Cesar Partial, Associate Engineer LOCATION Citywide PRIORITY Medium PROJECTNo. Wi1B07 TOTAL PROJECT COST $470,000 WORKED PERFORMED BY Contract PROJECT STATUS Construction ALTERNATE FUNDING SOURCE None DESCRIPTION JUSTIFICATION This project rehabilitates water and sewer facilities within the 7th Street This project will update deteriorated water and sewer facilities within the 7th Street Alley between Electric Avenue and Pacific Coast Highway. Alley between Electric Avenue and Pacific Coast Highway. The pavement in the alley will be removed in order to rehabilite the utilities and be replaced with concrete at the conclusion of construction. Ongoing Operating & Maintenance Impact: None TOTAL $ 470,000 $ 470,000 65 Proposed Proposed Proposed Proposed Proposed 2016­2017 2017 -2018 201 8­2019 201 9­2020 2020 -2021 Proposed Funding Budget Budget Budget Budget Budget Budget Budget Budget Badget Budget Syear total Syear total Sewer Fund $ 235,000 $ 235,000 Water Fund $ 235,000 $ 235.000 TOTAL $ 470,000 $ 470,000 65 FY 2016117 - 2020121 PROJECT CATEGORY Water System PROJECT No. VVt1702 PROJECT NAME Westminster Ave. Water Main Replacement TOTAL PROJECT COST $2,600,000 PROJECT MANAGER David Spitz, Associate Engineer WORKED PERFORMED BY Contract LOCATION Westminster Ave. PROJECT STATUS Ongoing PRIORITY High ALTERNATE FUNDING SOURCE None DESCRIPTION JUSTIFICATION This project will replace the existing water main line on Westminster Ave. This project will update the deteriorated waterline located on Westminster Ave. On -going Operating & Maintenance Impact: BYO un.On� Y MAP Pmpdsed Proposed Pmpased Proposed Proposed 20162017 2017- 2018 2018-2019 20142020 2020.2021 Purposed PICTURE 67 PROJECT CATEGORY Water System PROJECT NAME Lampson Ave Water Main Replacement PROJECT MANAGER David Spite, Assormte Engineer LOCATION Lampson Avenue PRIORITY High PROJECT No. WT1704 TOTAL PROJECT COST $1,300,000 WORKED PERFORMED BY Contact PROJECT STATUS Planned ALTERNATE FUNDING SOURCE None DESCRIPTION JUSTIFICATION To remove and replace the existing 12" ACP waterline on Lampson Ave The existing Lampson waledine has historically failed and caused numerous main line from Seal Beach BNtl. to Basswood St. breaks. It has outlasted its useful life. Ongoing Operating & Maintenance Impact: - 2t is P �. �y'�M wEN Go yy SEE "I 3 3, �UNJTEO_ - �m MAP PropmeC Prapose0 Propons! PmpasM P,-Ed 20162017 2017 -2010 20lb2019 20142020 2020.2021 Pm,aid BWgtl Budget 9udge1 Budget Budgm Syear War Expenditures Design $ 130.000 $ 130.000 Construction $ 1.170,000 S 1,170.000 TOTAL $ 1.300.000 $ 1.300.000 PICTURE 69 ORANGE COUNTY TRANSPORTATION AUTHORITY PRELIMINARY ENGINEERING AGREEMENT DISTRICT COUNTY ROUTE POST MILE EA PROJECT ID 9.3 -24.2 12 Orange 1 -405 12- 1200000180 OH 1000 FEDERAL AID NUMBER OWNER'S PLAN NUMBER H PLULN- 6071(043) N/A FEDERAL PARTICIPATION On the project ® YES ❑ NO On the Utilities ❑ YES ® NO PRELIMINARY ENGINEERING AGREEMENT NO. UK100001 DATE The Oranee Countv Transportation Authority (OCTA) in cooperation with the California Department of Transportation ( "Caltrans ") is proposing to improve Interstate 405 between State Route 73 and Interstate 605 (Project). OCTA and Caltrans have entered into a Cooperative Agreement relating to the Proiect under which Caltrans will Drovide Proiect oversight and upon completion of the Proiect, Caltrans will continue to own and maintain the I -405 Citv of Seal Beach Hereinafter referred to as "OWNER ", owns and maintains • 12 inch ACP Crossing the I -405, SB -W4063 • 12 inch WSP within Bolsa Chica Channel east side, SB -W4036 within the limits of the OCTA Project which requires preliminary relocation plans to accommodate OCTA's Project. It is hereby mutually agreed between OCTA and OWNER as follows: I. WORK TO BE PERFORMED 04 -05 -2016 In accordance with the Notice to Owner No. SB -W4063 and SB -W4036 dated June I, 2016, Owner shall prepare preliminary engineering utility relocation studies for the utility relocation work on the following Design Build project: Interstate 405 between State Route 73 and Interstate 605 (Proiect). Any revision to the Owner's preliminary engineering studies, after approval by OCTA shall be agreed upon by both parties hereto under a Revised Notice to Owner. Such Revised Notices to Owner, approved by OCTA and agreed to /acknowledged by the OWNER, will constitute an approval revision of the OWNER's preliminary engineering studies described above and are hereby made a part hereof. No redesign or additional engineering, after approval by OCTA, shall commence prior to written execution by the OWNER of the Revised Notice to Owner and may require an amendment to this agreement in addition to the Notice to Owner. PRELIMINARY ENGINEERING AGREEMENT II. LIABILITY FOR WORK Page 2 of 6 PRELIMINARY ENGINEERING AGREEMENT NO. OCTA shall pay all actual preliminary engineering utility relocation studies expenses for utility studies according to the Pilot Program approved by the Department of Transportation on the Design Build project in the letter dated October 27, 2015. III. PERFORMANCE OF WORK Engineering services for preliminary engineering utility relocation activities and studies are to be furnished by the consulting engineering firm on a fee basis previously approved by OCTA. Cost principles for determining the reasonableness and allowability of consultant costs shall be determined in accordance with 48 CFR, Chapter 1, Part 31; 23 CFR, Chapter I, Part 645; and OMB Circular A -87, as applicable. Engineering services for preliminary engineering are to be furnished by the Utility Owner and approved by OCTA. Cost principles for determining the reasonableness and allowability of OWNER's costs shall be determined in accordance with 48 CFR, Chapter I, Part 31; 23 CFR, Chapter I, Part 645; and 18 CFR, Chapter I, Parts 101, 201 and OMB Circular A -87, as applicable. Use of out -of -state personnel (or personnel requiring lodging and meal "per diem" expenses) will not be allowed without prior written authorization by OCTA's representative. Requests for such authorization must be contained in OWNER's estimate of actual and necessary relocation costs. Accounting Form FA -1301 is to be completed and submitted for all non - State personnel travel per diem. OWNER shall include an explanation why local employee or contract labor is not considered adequate for the relocation work proposed. Per Diem expenses shall not exceed the per diem expense amounts allowed under the State's Department of Personnel Administration travel expense guidelines. Work performed directly by Owner's employees falls within the exception of Labor Code Section 1720(a)(1) and does not constitute a public work under Section 1720(a)(2) and is not subject to prevailing wages. OWNER shall verify compliance with this requirement in the administration of its contracts referenced above. IV. PAYMENT FOR WORK The initial, estimated cost of the Owner's preliminary engineering is Thirty-Two Thousand, Five Hundred Dollars ($32,500.00). Final actual costs may be more or less than such estimate, which will not be construed as a limitation of costs for the preliminary engineering. OCTA shall pay its share of the actual and necessary cost of the herein described work within 45 days after receipt of OWNER's itemized bill, signed by a responsible official of OWNER's organization and prepared on OWNER's letterhead, compiled on the basis of the actual and necessary cost and expense incurred and charged or allocated to said work in accordance with the uniform system of accounts prescribed for OWNER by the California PRELIMINARY ENGINEERING AGREEMENT Page 3 of PRELIMINARY ENGINEERING AGREEMENT NO. Public Utilities Commission, Federal Energy Regulatory Commission or Federal Communications Commission, whichever is applicable. It is understood and agreed that OCTA will not pay for any betterment or increase in capacity of OWNER's facilities in the new location and that OWNER shall give credit to OCTA for the accrued depreciation of the replaced facilities and for the salvage value of any material or parts salvaged and retained or sold by OWNER. Not more frequently than once a month, but at least quarterly, OWNER will prepare and submit itemized progress bills for costs incurred, not to exceed OWNER's recorded costs as of the billing date less estimated credits applicable to completed work. Payment of progress bills, not to exceed the amount of this Agreement, may be made under the terms of this Agreement. Payment of progress bills which exceed the amount of this Agreement may be made after receipt and approval by OCTA of documentation supporting the cost increase and after an Amendment to this Agreement has been executed by the parties to it. The OWNER shall submit a final bill to OCTA within 360 days after the completion of the work described in Section I above. If OCTA has not received a final bill within 360 days after notification of completion of OWNER's work described in Section 1 of this Agreement, and OCTA has delivered to OWNER fully executed Director's Deeds, Consents to Common Use or Joint Use Agreements for OWNER's facilities (if required), OCTA will provide written notification to OWNER of its intent to close its file within 30 days. OWNER hereby acknowledges, to the extent allowed by law, that all remaining costs will be deemed to have been abandoned. If OCTA processes a final bill for payment more than 360 days after notification of completion of OWNER's work, payment of the late bill may be subject to allocation and /or approval by OCTA. The final billing shall be in the form of an itemized statement of the total costs charged to the project, less the credits provided for in this Agreement, and less any amounts covered by progress billings. However, OCTA shall not pay final bills which exceed the estimated cost of this Agreement without documentation of the reason for the increase of said cost from the OWNER and approval of documentation by OCTA. Except, if the final bill exceeds the OWNER's estimated costs solely as the result of a revised Notice to Owner as provided for in Section 1, a copy of said revised Notice to Owner shall suffice as documentation. In either case, payment of the amount over the estimated cost of this Agreement may be subject to allocation and /or approval by OCTA. In any event if the final bill exceeds 125% of the estimated cost of this Agreement, an Amended Agreement shall be executed by the parties to this Agreement prior to the payment of the OWNER'S final bill. Any and all increases in costs that are the direct result of deviations from the work described in Section I of this Agreement shall have the prior concurrence of OCTA. Detailed records from which the billing is compiled shall be retained by owner for a period of three years from the date of final payment and will be available for audit by State and /or PRELIMINARY ENGINEERING AGREEMENT Page 4 of 6 PRELIMINARY ENGINEERING AGREEMENT NO. Federal auditors. In performing work under this Agreement, owner agrees to comply with the Uniform System of Accounts for Public Utilities found at 18 CFR Part 101, 201, et ah, and, to the extent they are applicable to owner doing work on the project that is the subject of this agreement, the contract cost principles and procedures as set forth in 48 CFR, Chapter I, Part 31, et seq., 23 CFR, Chapter I, Part 645, and 2 CFR Part 200 et al. If a subsequent State and /or Federal audit determines payments to be unallowable, owner agrees to reimburse agency upon receipt of agency billing. If owner is subject to repayment due to failure by State /Local Public Agency (LPA) to comply with applicable laws, regulations, and ordinances then State /LPA will ensure that owner is compensated for actual cost in performing work under this agreement. V. GENERAL CONDITIONS All costs accrued by OWNER as a result of OCTA's request of March 6, 2015 (SB- W4063) and March 10, 2015 (SB- W4036) to review, study and /or prepare relocation plans and estimates for the project associated with this Agreement may be billed pursuant to the terms and conditions of this Agreement. If OCTA's project which precipitated this Agreement is canceled or modified so as to eliminate the necessity of work by OWNER, OCTA will notify OWNER in writing and OCTA reserves the right to terminate this Agreement by Amendment. The Amendment shall provide mutually acceptable terms and conditions for terminating the Agreement. Such terms will include OCTA's agreement to pay all costs incurred by Owner in its performance of preliminary engineering and study work upon the submissions of invoices. OWNER shall submit a Notice of Completion to OCTA within 30 days of the completion of the work described herein. It is understood that said highway is a Federal aid highway and accordingly, 23 CFR, Chapter I, Part 645 is hereby incorporated into this Agreement. In addition, the provisions of 23 CFR 635.410, Buy America, are also incorporated into this agreement. The Buy America requirements are further specified in Moving Ahead for progress in the 21" Century (MAP -21), section 1518; 23 CFR 635.410 requires that all manufacturing processes have occurred in the United States for steel and iron products (including the application of coatings) installed on a project receiving funding from the FH WA. This Agreement is for preliminary design and as such, OCTA represents and warrants that this Agreement is not subject to 23 CFR 635.410, the Buy America provisions. It is expressly understood by the Parties that Owner is not, in executing this Agreement, abandoning any pre- existing right, title or interest it may have in any land or facilities, all such rights, title and interest being expressly reserved. PRELIMINARY ENGINEERING AGREEMENT Page 5 of 6 PRELIMINARY ENGINEERING AGREEMENT NO. The terms of this Agreement shall be binding and inure to the benefits of the Parties hereto. THE ESTIMATED COSTS TO THE OWNER FOR ITS SHARE OF THE ABOVE DESCRIBED WORK IS $32,500. Signatures on Following Page PRELIMINARY ENGINEERING AGREEMENT Page 6 of PRELIMINARY ENGINEERING AGREEMENT NO. U K i 00001 SIGNATURE PAGE TO PRELIMINARY ENGINEERING AGREEMENT NO. UK100001 IN WITNESS WHEREOF, the above parties have executed this Agreement on the dates below. Owner: CITY OF SEAL BEACH APPROVED By: Title: Date: ORANGE COUNTY TRANSPORTATION AUTHORITY, a public entity APPROVED to Jim Beil Executive Director, Capital Programs Date: APPROVED AS TO FORM: By: By: Title: James M. Donich General Counsel Date: Date: