HomeMy WebLinkAboutItem P AGENDA STAFF REPORT DATE: June 27, 2016 TO: Honorable Mayor and City Council THRU: Jill R. Ingram, City Manager FROM: Jim Basham, Interim Director of Public Works SUBJECT: EMERGENCY WATER LINE REPAIRS ON LAMPSON AVENUE CIP NO WT1608 SUMMARY OF REQUEST: That the City Council receive and file an update on the completion of the emergency water line repairs on Lampson Avenue, CIP No. WT1608. BACKGROUND AND ANALYSIS: On the evening of Friday July 24, 2015, a water main break occurred on Lampson Avenue at Seal Beach Boulevard. City crews responded immediately to assess the situation. The Water Division staff determined that the water main break was much larger than the City's resources could accommodate and contracted with Charles King Company to make the necessary repairs. The actual repairs took an estimated two weeks because of the amount of excavation, multiple utility lines and a high pressurized gas line crossing the water line. On August 10, 2015 the City Council authorized a Budget Amendment in the amount of $100,000 for repair costs to the broken water line. On the same day, the Gas Company dug up the recently paved trench as emergency work due to the possibility of a leak in their high pressure transmission line (HP Gas line). During the excavation, the Gas Company cut through a critical Time Warner line that prompted over 20 Time Warner trucks and crews to mobilize and repair their line well into the night. The Gas Company determined that there may be additional and possibly more critical leaks in their HP Gas line at this location and would need to do further testing to determine if there are leaks, and if so, how to repair them. While conducting the emergency work, the Gas Company data collection including sonar, surveys, x-rays, etc. and the subsequent in-house testing of the collected data observed potential leaks outside the current trench boundary. Agenda Item P They proceeded to widen the trench approximately 3 times the original size in order to perform some additional emergency repairs and perform further testing. The Gas Company determined there were substantial permanent repairs needed on their HP Gas line and ordered all necessary straps and clamps. Due to the specialty nature of this work, the repair items are all individually fabricated to fit the exact field need and take a long time to procure. Specialized welders are needed to perform the work which provides an additional potential delay towards scheduling the repairs. The Gas Co. performed full repairs on their HP Gas line. The trench was plated while the Gas Co. schedules sub-contractors to repair the trench. In January 2016, the Gas Company returned to the site to conduct minor alterations of their repairs after testing was completed. The Gas Company was on-site to slurry and backfill the trench and temporarily pave the surface in order to remove the steel plates while scheduling the final paving. On February 24, 2016 the sub-contractor for the Gas Company performed the final grind and paving of the trench for a smooth drivable surface. The surrounding location of the waterline break has been affected by past waterline breaks and detrimental weather which caused numerous potholes, rutting, and raveling of the asphalt surface. Compounded with the most recent work, staff contracted with Hardy and Harper to grind and repave the rough surface above the City's water line on eastbound Lampson Avenue. This work was completed on May 19, 2016. All repair work has been completed and staff recommends that the City Council receive and file this report. ENVIRONMENTAL IMPACT: This project is categorically exempt from review under California Environmental Quality Act ("CEQA") pursuant to Section 15301, Class 1(c) of the State CEQA Guidelines LEGAL ANALYSIS: The City Attorney has reviewed and approved as to form. FINANCIAL IMPACT: On August 10, 2015 City Council approved Budget Amendment No. 16-02-01 which allocated $100,000 from Water Capital Funds (019). A breakdown of the expenses for the project is as follows: Page 2 Description Vendor Amount Waterline Repair Charles King Company, Inc. $25,023.02 .................. ..................... .................... .. .............................................. .. ............................. ..................... ..... .................. ............ ............................................................................................ Inspection Casulas Consulting Services $2,080.00 Final Paving Hardy & Harper, Inc. $13,750.00 Total $40,853.02 The funds budgeted were sufficient to complete the work. The remaining funds will be returned to the Water Capital Funds. RECOMMENDATION: That the City Council receive and file an update on the completion of the eme • -ncy water line repairs on Lampson Avenue, CIP No. WT1608. SU: ED : NOTED AND APPROVED: •, s 117-. Ingram, CitMager Int:rim Director of Public Works Prepared by: David Spitz, P.E., Associate Engineer Page 3