HomeMy WebLinkAboutSupplemental Information Item K Revision made after Agenda distributionRank Contractor Amount
1
Cedro Construction, Inc.
$ 401,658.50
2
Charles King Company, Inc.
$ 425,021.00
3
Ramona, Inc.
$ 507,075.00
4
Lonerock, Inc.
$ 537,073.00
5
Mike Bubalo Construction Co., Inc.
$ 625,965.00
6
MNR Construction, Inc.
$ 682,850.00
7
Paulus Engineering, Inc.
$ 729,393.00
8
1 Minako America Corporation
$ 768,950.00
9 1
Elser Constructors, Inc.
$ 821,233.00
Based upon the references, qualifications, work experience and cost, staff
recommends selecting Cedro Construction, Inc. as the lowest responsive and
responsible bidder at $401,658.50.
In addition, a public meeting is tentatively scheduled Thursday, August 18, 2016,
6:00 p.m. at City Hall in the Council Chambers to discuss construction impacts
and address any concerns from the residents regarding the Project.
ENVIRONMENTAL IMPACT:
This Project complies with all requirements of the California Environmental
Quality Act (CEQA) and is categorically exempt under section 15301 class 1
subsection (b).
LEGAL ANALYSIS:
The City Attorney has reviewed and approved as to form.
FINANCIAL IMPACT:
In the approved FY 2016/17, a budget for $470,000 of Water Capital Funds and
Sewer Capital Fund is identified for construction of the Project. The construction
contract is $401,658.50 with Cedro Construction, Inc. The table below presents
the estimated breakdown of the Project cost:
Description Amount
Construction $ 401,658.50
Contingency $ 34,000.00
Total $ 435,658.50
Page 2