HomeMy WebLinkAboutItem A !F SEA( eF\
•AGENDA STAFF REPORT
\C4(tiFortNsk/
DATE: November 14, 2016
TO: Honorable Mayor and City Council
THRU: Jill R. Ingram, City Manager
FROM: Jim Basham, Interim Director of Public Works
SUBJECT: ENERGY EFFICIENCY CLIMATEC PROGRAM
UPDATE
SUMMARY
To provide direction to staff on completion of the Energy Efficiency Study project
with Climatec.
BACKGROUND
At the July 25, 2016 City Council meeting, staff provided an update to the 2014
Energy Efficiency Project (Project). Staff presented background information on
the Project which included construction items that were completed and those that
were not completed. Based on an updated Project financial analysis, staff
recommended that there was insufficient financial justification for purchasing
Edison-owned street lights in the City as had previously been proposed and thus,
staff started to research an alternative energy savings program. After
discussions with the City Council, staff received direction to not move forward
with the purchase of Edison owned street lights.
At the October 24, 2016 City Council meeting, staff provided two Project options.
Option 1 was to restructure the Loan to lower the balance to match the energy
savings and not continue forward with any other additional energy savings
projects. The Loan is a Financing Agreement between the City of Seal Beach
and Municipal Finance Corporation with an 11-year term at a rate of 3.40% for a
total of $1 ,893,455.86, which includes a principal of $1,546,930.82 (Project Cost)
and an interest of $346,524.95. Option 2 was for Climatec to present other
energy savings projects to offset the Loan to comply with Resolution No. 6456
and Government Code Section 4217. The City Council Resolution No. 6456
adopted the following findings:
A. The installment of the Energy Conservation Equipment will improve the
energy efficiency at City facilities. It is in the best interest of the City to
enter into the Installment Agreement and the Lease.
Agenda Item A
B. The anticipated cost to the City for electrical energy and conservation
services for the Energy Conservation Equipment is less than the
anticipated marginal cost to the City of energy that would have been
consumed by the City in the absence of the acquisition and installation of
the Energy Conservation Equipment.
C. The difference, if any, between the fair rental value for the property subject
to the Lease and the agreed rent is anticipated to be offset by below-
market energy purchases or other benefits provided under the Installment
Agreement.
D. The repayment of the Financing and the cost of design, construction, and
operation of the Energy Conservation Equipment, as required by the
Installment Agreement and the Lease are projected to be available from
funding that otherwise would have been used for purchase of electrical,
thermal, or other energy required by the City in the absence of the Energy
Conservation Equipment.
To comply with Resolution No. 6456 findings and Government Code Section
4217:
o The total dollar amount projected to be used to repay the financing can be
no more than the money that otherwise would have been used to
purchase the energy if the proposed equipment was never purchased: and
e All project costs must be paid through the reduction in anticipated utility
costs over the life of the equipment financed through the program.
The 2014 Energy Efficiency Project as approved complied with adopted
Resolution 6456 and Government Code Section 4217 because, at the time, it
included the purchase of Edison owned street lights. If the City purchased Edison
lights, the City was allowed to replace the HVAC units and other scope of work
items in the Project because the overall Project costs are less than the energy
savings. However, as the City Council is aware, Edison's proposed costs and
terms for the acquisition were unacceptable to the City and the uncertain ongoing
maintenance cost ultimately made acquisition of the street lights infeasible.
Because a balance remains out of the original loan program, staff has been
working with Climatec to identify other energy savings projects. One project staff
explored was Citywide water meter replacement with Automatic Meter Reading
(AMR) or Advanced Metering Infrastructure (AMI). AMR uses a handheld device
that automatically reads the meter to get a current reading, which is used to
generate a bill. AMR systems can be walk-by, drive-by, or fixed network. The
communication is one-way. The City currently has approximately 500 water
meters with AMR technology. Conversely, AMI enables two-way communication
over a fixed network between the City facilities with antennas and the metering
endpoints. Meters can be read wirelessly and without any personnel. With an
AMI system, the City can continuously monitor through hourly interval reads.
With this data, it allows a water utility to find evidence of leaks. It may even
prevent a small leak from becoming a much larger leak. Previously, the City
researched the cost to implement AMI citywide and found the cost; to be
extremely expensive. The estimated cost for design, construction and annual
ongoing maintenance was estimated at over $3 million. Although the AMR and
AMI systems might provide energy costs savings, staff does not recommend this
City wide water meter replacement project because it would be extremely costly.
Staff recommends that the City Council restructure the existing Loan to lower the
outstanding balance to match the energy savings and not continue forward with
any other additional energy savings projects. This will allow the City to prepay
the restructured Loan. Per the Detailed Audit Report, the project cost would have
been $1,551,333 which includes the Edison streets lights. Since the City did not
purchase the Edison lights, there was a savings of $595,498 from the
$1,551,333. This now leaves $955,835 as the current project expenditures, with
interest not included. Climatec has calculated the total estimated utility reduction
cost over the useful life of the equipment (15 years), without the purchase of the
Edison lights, would be $816,000.
To comply with Resolution No. 6456 findings and Government Code Section
4217, all project costs ($955,835) need to be paid through the reduction in
anticipated utility costs ($816,000) over the life (15 Years) of the equipment.
Stopping the energy efficiency work at this stage results in a difference of
$139,835. This difference of $139,835 will not comply with Resolution No. 6456
findings and be financed under Government Code Section 4217. The City is
required to remove $139,835 from the Loan and prepay it.
In summary, staff asks the City Council to provide direction to staff to start the
process of restructuring the existing energy efficiency program loan to lower the
balance to match the estimated energy savings from the project improvements
that have been concluded and direct staff to not continue forward with any other
additional energy savings projects for the Climatec Energy Efficiency Program,
including the proposed purchase of City street lights. If this is the direction from
the City Council, staff will bring back an action item and resolution with the
amended loan documents and a proposed budget amendment to finalize
transaction for the City Council's consideration.
SU: I ED B : NOTED AND APPROVED:
ilk a e !: , tit.�
J mlasham V E'. Ingram, City Mader
Inte m Director of Public Works
Attachments
A. Energy Savings Cost Analysis Update
•
BEACH D
O PDATE
c,:pri-c,:.‘ir:f0:1Teq,c'a !-A:074,V.'n3Ir('-'. . \ , . \--1
City of Seal Beach
$6Q000 -
For the period of November 2014 -August 2016:
-X Energy-Consumption Reduction: 325,589 kWh -
$50,000 - -
-' Cost Avoidance: $ 55,902
-
o, $40,000 - -
co
N -
T _
$30,000 -
5 r
v -
>
E $20,000 -
n
V -
$10,000 - - '
Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug-
14 14 15 15 15 15 15 15 15 15 15 15 15 15 16 16 16 16 16 16 16 16
ANNUAL ANNUAL ANNUAL ANNUAL UTILITY
SITE NAME ENERGY WATER UTILITY OPERATIONS REBATES&
SAVINGS SAVINGS SAVINGS SAVINGS INCENTIVES
(KWH) (KGAL) ($) ($) ($)
CITY HALL 21,129 - $2,821 $266 $1,389
CITY YARD 8,133 - $1,507 $338 $389
MARINA COMMUNITY CENTER 12,460 - $2,051 $608 -
NORTH SB COMMUNITY CENTER 11,062 - $1,773 $265 -
POLICE HQ 79,665 - $9,232 $2,957 $771
SEAL BEACH LIFEGUARD/PIER 3,638 - $625 $82 -
TENNIS CENTER 33,213 - $9,077 $1,179 -
CITY WIDE IRRIGATION CONTROL - 1,734 $4,705 $0 -
STREET LIGHT LS-2 RETROFIT 52,673 - $3,837 $0 $16,748
PROJECT TOTALS 221,973 1,734 $35,628 $5,695 $19,298
STREET LIGHT LS-1 RETROFIT 359,208 - $26,260 $0 $139,448
STREET LIGHT LS4 TO*S-2 - - $87,944 $0 -
PROJECT TOTALS W/LS-1 SCOPE 581,180 1,734 $149,831 $5,695 $158,954
*The values presented.in this document are preliminary estimates of energy and cost savings;Climatec BTG reserves the right to adjust the savings according to
IPMVP standards based on the findings of the comprehensive M&V report upon the conclusion of each savings guaranteed year. All savings were evaluated
in accordance to the.International Performance Measurement and Verification Protocol (IPMVP EVO 10000-1:2010) Option A. In order to qualify for
utility incentives,the Street Lights currently billed under LS-1 must be converted to LS-2.
ALL INC�1i'UDED CONTENTS PRODUCEtTBY QLTItvIA7EC ARE AGREED TO BE PROPRIETARY CLI ATEC®
AND GONFIDENTIABTAN,..DNQTITQBE SHHARE IMITH ANY NON DISTRICTjP,ERSoNNEL MERGING BUILDINGS&TECHNOLOGY