Next Steps
► Final Designs
• Electrical (2-3 Months)
• Structural and Utilities (3-4 Months)
• Sewer Pump Station (3-4 Months)
► Review
▪ Insurance Review (1 month)
► Permitting
• Coastal Commission (6- 12 Months)
► Construction
• All tasks including: structural repairs, utility lines,
sewer pump station, and new decking (9-12
Months)
4
11/14/2016
Final Timeline
2016 2017 2018 2019
Task Description sep 0u Nov Ow Jan Fat Mar n May Jun Jul Aug Sep Cu! Nov Dec Jen fen Mar Aye AMY Jon.An!Aw Sep ai No. Dec = Ma! APP Nee
Electrical rs y
Structural MOM* __ __
Sewer Pump Station nag
. Review'
Insurance Company Review
Environmental/Permitting
CEPA 11111.1 ___
Coastal Commission _ T U M I I•S.S U®i ____
Bidding and Award __
Advertising and Out to Bid
111 I
Award and Contract Documents
Construction
Structural Repairs __ RIME I�
Utilities lines — M■
Sewer Pump Station �t Il Met
_ M
I�{
New packing r l♦111
Project Close Out
IllItinp- ii. dINiClllllllll I'.i.,,