Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
Supplemental Information Received After Posting of Agenda - Pier Fire Incident Update (PowerPoint Presentation)
4/24/2017 4/24/2017 Ongoing & Future Tasks Final Designs Electrical (4 -8 Months) Structural and Utilities (4 -8 Months) Sewer Pump Station (4 -6 Months) Review Insurance Review (1 month) Environmental Approval & Permitting • CEQA (4 -8 Months) • Coastal Commission (6-12 Months) � JPA Formation & Funding Pier Construction Loan (2 -3 Months) � Construction All tasks including: structural repairs, utility lines, sewer pump station, and new decking (9-12 Months) 4/24/2017 Timeline from January 2017 4/24/2017 Questions?