AGENDA STAFF REPORT �� ,-
`dilt/FORNiP
DATE: June 26, 2017
TO: Honorable Mayor and City Council
THRU: Jill R. Ingram, City Manager
FROM: Patrick Gallegos, Assistant City Manager
SUBJECT: CITY OF SEAL BEACH STRATEGIC PLAN SIX
MONTH STRATEGIC OBJECTIVES UPDATE
SUMMARY OF REQUEST:
That the City Council receive and file the City of Seal Beach Six-Month Strategic
Objectives update.
BACKGROUND AND ANALYSIS:
On April 4, 2017, the City Council held a Special Meeting to review the progress
made on the six-month objectives and re-evaluate the three-year goals as
needed. The strategic plan provides the principal guidance for the preparation of
the City budget, program objectives and a plan for implementation and
accountability.
The City of Seal Beach strategic plan is a living document which will be reviewed
and revised on a regular basis by the City Council. The attached matrixes
provide an update on the current status of the six-month objectives as of
June 26, 2017. It should also be mentioned that City staff have had to manage a
number of emerging issues (these include matters that are not identified in the
strategic goals matrix nor are part of typical staff responsibilities); since
April 4, 2017. Some of these issues include resolving facility concerns at the
Mary Wilson Library, a surge in shark sightings, and implementation of software
solutions to streamline both the Public Records Act request and Agenda
Management processes, to name a few.
ENVIRONMENTAL IMPACT:
There is no environmental impact related to this item.
Agenda Item A
LEGAL ANALYSIS:
No legal analysis is required for this item.
' FINANCIAL IMPACT:
No fiscal impact is associated with the approval of this item.
RECOMMENDATION:
That the City Council receive and file the City of Seal Beach Six-Month Strategic
Objectives update.
SUBMITTED BY: NOTED AND APPROVED:
I ‘"•
Patrick Gallegos ". Ingram, City / ana)jer
Assistant City Manager
Attachments:
A. City of Seal Beach Six-Month Strategic Objectives
Page 2
"Attachment A"
CITY OF SEAL BEACH
SIX-MONTH STRATEGIC OBJECTIVES
.April 4, 2017 - October 15, 2017
THREE-,YEAR GOAL PROVIDEA QUALITYBEACHAND PIER ENVIRONMENT,,INCLUDING A'RESTAURANT
WHEN WHO WHAT STATUS COMMENTS
DONE ON -REVISED
TARGET —
1. 1 Staffthas-reseived-tho
By May 15,2017 Public Works Resubmit the revised application material to the Coastal Commission tor
Director *mating the structural repairs on the pier.
e &17 and-will
Comms mining-le6eastal
X * 6eme.issieeease
ceviewed#Staff has
submitted all application
material to the Coastal
Commission and is
awaiting their response.
2, m ,� The beach parking lots
May 29,2017 Public Works Restripe 8 Street&10 Street beach lots to improve circulation and X were res4iped on May 16
Director enforcement.
and 17,2017.
By June 15,2017 Public Works Complete the CEQA documentation for the water infrastructure and pier This wiU-bewas presented
Director improvements. X X to the City Council on May
22,2017 for consideration.
4.
By July 15,2017 Public Works Bring before the City Council for consideration an extension of the Berm In progress
Director construction and removal contract. X
By A meeting has-been
y October 15, Public Works Secure the Tidelands lease agreement for the beach. ssheduledwas held with
2017,contingent Director,working State officials fer-or±May
upon State Lands with the ad hoc 31,2017 to discuss the
Commission Council Tidelands x items on the proposed
approval Subcommittee Lease agreement.Staff is
awaiting a response from
_ . .the State reoardina certain _ _ _ _
questions that came up
during the meeting,
A
THREE-YEAR GOAL: ACH/EVE SHORT-AND,L'ONG4TERM'E/SCAL SUSTAINABILITY
WHEN. WHO WHAT ;STATUS 'COMMENTS
DONE ON. REVISED'
TARGET
1. Update to the Council and
At an April 24, Finance-Director Update the City Council and the community on the process used X community completed at
2017 City Council by the City for evaluating oil revenue recovery. special study session. A
study session second consultant
preparing.REQ response,
-due May-15th-
Secona response received,
will.eGaluateand make a
final recommendation.
- '2. -City Attorney has-revised
At the June 12, City Clerk and Bring to the City Council for consideration a citywide X original recommendation
'2017 City Council Finance Director Procurement and Contract Administration Policy. .and Finance has pr'ovided
meeting additional edits and
resubmitted to City
Attorney for review.On City
Council agenda for June ,
2fL
- - - Formatted:Superscript
3. There was a delayed
By July 10,2017 Finance Director Bring a consultant contract to the City Council for consideration X response by.the"additional
to hire an oil professional to evaluate oil revenue recovery consultant'confirmingthat
options. they Would respond to the
RFD.See Above.
4. This-is+tem-wiil4a
At the September Public Works Present to the City Council for direction the proposed new water
11',2017 City Director and City and sewer rates. after-securing finaadial
Council meeting Engineer X X optieae-te-fund tho water
prejeeteln.Progress
5.
By October 15, Finance Director Hire a consultant to develop a 5-Year Financial Plan to address X 14-Prowess Awaiting JPA
2017 the cost of retirement,retiree health and creation of a new"rainy amendment and
day"fund,among other items. wafer/sewer rates.
B
6. Team formed,one grant.
By October 15, Finance Director, Identify and apply for at least two grants. X application complete.
2017 working with the Second grant application in
Grant Funding Team. progress.
, (representative from
each Department
selected by the
Department Head by
April 15,2017)
C
THREE-YEAR GOAL:,IMPROVEAND MAINTAIN THE INFRASTRUCTURE;AND FACILITIES'
WHEN WHO 'WHAT STATUS' COMMENTS
DONE' ON REVISED'
. TMGET -
1.
By June 1,2017 Public Works Present to:the City Council for consideration an agreement to update - In progress
July 10.2017 Ditector construction costs of facilities identified in.the 2011 Facility Condition X X
Assessment and begin development of an implementation.plan.
2. A draft work p1ar is o'rroatly
By July 15, Public Works Complete.formation of the JPA to allow for public financing of under-review leterim
2017 Director and infrastructure improvements. X X milestone-dates-will-be
Finance Director ineerperatedln Progress
3.
By tiny-}§ Public Works Present to the City Council for consideration a JPA for water X under-review-lMedm
2o17September Director infrastructure funding.
_2017 incergeratedln Progress .
4.
By July 15. Public Works Bring to the City Council a funding request for Lifeguard In progress
2017 Director(lead), Headquarters/Police Substation repairs.
Police Chief and X
Marine Safety
Chief
5.
At a September Public Works Present to the City Council for prioritization and direction the In progress
11,• 017 City Director Stormwater Master Plan improvements. X
Council study
session
6.
By October 15, Public Works Present a long-term citywide landscape maintenance contract and a In progress
2017 Director draft RFP to the City Council for consideration. X
7.
By October 15, Police Chief and Implement the Comprehensive Parking Management Plan. X In progress
2017 Finance Director
8. A draft work plan is currently
By July 15, City Engineer Present to the City Council financial options to fund building facilities per X under review.Interim
2017 and Finance • the 2011-Facility Condition Assessment.- - milestone dates will be - -
Director incorporated
D
THREE=.YEAR.GOAL:.ATTRACT, DEVELOP, COMPENSATEAND RETAIN:QUALITY STAFF
-WHEN' `
WHO 'WHAT. STATUS COMMENTS
DONE 'DG, ' REVISED
TAriGEf' -
1.
By Juno IS, Assistant City Manager Present the results of the Classification and Compensation X X In progress
2047Auaust 14 Study,with recommendations,to the City Council for action.
2017
2. Staff has begun negotiations
By July-, Assistant City Complete POAAPMNMSMA(Police Officers Association,Police X with both labor groups
2047Auaust 14, Manager,working with Management Association,Marine Safety Management
2017 the City Council Association)negotiations.
3. Meet,conferred,researching
By October 15, City Clerk and Police Ensure completion of customer service training for all City X available presenters.
2017 Commander Gonshak employees.
4. Once the Class and Comp
By October 15, Assistant City Manager Incorporate the classification and compensation job X study is complete,it will be
2017 and Police specifications into the Citywide Succession Plan. incorporated int6 the Citywide
Commander Gonshak Succession Plan
E
THREE=YEAR GOAL: ENHANCE PUBLIC SAFETY
WHEN WHO 'WHAT STATUS COMMENTS
DONE. 'ON' REVISE0
TARGET
1.
By July 1,2017 Police Commander Conduct analysis of Animal Control Services and report the results X Staff report in progress and
Bowles with a recommendation to the City Council for direction. projected to be completed by
July 1,2017
2.
By August 1, Police Chief Increase staffing'by two officers Jo enhance public safety through X Contingent upon FY17/18
2017,contingent increased patrol coverage and reducing Part I(serious)crimes. Budget and City Council
upon.City direction
Council approval
3.
By September Marine Safety Chief Develop and execute a training drill for Public Safety personnel to X First planning meeting with
15,2017 and Orange County improve and enhance offshore rescueand mutual aid capabilities. OCFA and Marine Safety
Fire Authority complete
Division Chief
4.
By October 1, Orange County Fire Report to the City Council the last six months of statistical data of X In progress
2017 Authority Division Paramedic Deployment Service Enhancements.
Chief
F