Supplemental - Pier Fire Incident Update PP
7 /to /2017 Ongoing & Future Tasks . Final Designs • Electrical (4 -8 Months) • Structural and Utilities (4 -8 Months) • Sewer Pump Station (4 -6 Months) . Review o Insurance Review (2 month) . Environmental Approval & Permitting CEQA (4 -8 Months) Coastal Commission (6 -12 Months) . JPA Formation & Funding Pier Construction Loan (2 -4 Months) . Construction All tasks including: structural repairs utility lines, sewer pump station, and new decking (9 -1 f Months) 7 /10 /zov Timeline from 1 Questions?