HomeMy WebLinkAboutItem HJanuary 22, 2001 �Ot J wti� Y STAFF REPORT p "I To: Mayor and Members of the City Council LIc V Attention: Donald F. McIntyre, Interim City Manager From: Stephen G. Badum, Director of Public Works/City Engineer Subject: ACCEPTANCE OF SEAL BEACH BOULEVARD SEWER FORCEMAIN REPLACEMENT, PROJECT #814 GENERAL DESCRIPTION The proposed action will formally accept the completion of the construction contract to construct the Seal Beach Boulevard Sewer Forcemain Replacement, Project #814. DISCUSSION: In May 2000, Council elected to award a project to Majich Bros., Inc. This was the second phase of the Sewer Replacement Projection Seal Beach Boulevard. In accordance with the plans and specifications, the Contractor has completed the above - referenced project. The Change orders consisted of removing additional deteriorated asphalt, relocation of a manhole, installation of conduit for future traffic signal projects and downtime for utility conflicts. The breakdown of costs are: Original Contract Price $993,811.00 Unit Price Work $995,056.00 Authorized Change Orders $130,503.64 Contract Total $1,125,559.64 Authorized Payments to date $1,125,559.64 10% Retention $112,555.97 This project was completed within the contract time and within budget. FISCAL IMPACT Funds were expended through the City's Capital Improvement Program budget under the Sewer Improvement Program. Agenda Item Acceptance of Construction Contract City Council Staff Report January 22, 2001 RECOMMENDATION Upon motion of the consent calendar, it is recommended that the City Council: By resolution, determine the work has been completed in accordance with the contract documents and declare the work to be accepted and the total amount of the contract is in the sum of $1,125,559.64. 2. Direct the City Clerk, within ten (10) days from the date of acceptance, file a "Notice of Completion" with the Orange County Recorder. 3. Direct City staff, upon expiration of thirty-five (35) days from the filing of the 'Notice of Completion, to make the retention payment to Majich Bros., Inc. in the amount of $112,555.97. P Pt"C�FE Y: WE o ancs, Stephen m, P. ctor Asst. City Engineer Public Works Department NOTED AND D: Donald F. McIntyre Interim City Manager Attachments: Notice of Completion Agenda Item January 24, 2001 Office of the Recorder County of Orange P. O. Box 238 Santa Ana, California 92702 Forwarded is a certified copy of Resolution Number 4872 "Declaring Work to be Completed for Project 814, Seal Beach Boulevard Sewer Forcemain Replacement," and attachment "A" thereto. Please record the enclosed Resolution with attachment and return same to my office. Thank you. Very truly yours, Joanne M. Yeo, City Clerk City of Seal Beach Encl.