Project Location and Key Features
2
2
Significant Project Features
3
Two new lanes in each direction (one GP and one tolled express lane)
18 bridge replacements plus new and widened bridges
Interchange reconfigurations
Merge lane improvements
Arterial
street improvements
New and replaced soundwalls
New bike lanes and sidewalks
Anticipated 6-year design-build contract duration
Project cost is approximately $1.9 billion
3
Access Points
4
4
Travel Time Benefits Comparison
5
5
Project Update
On January 31, 2017, OCTA executed the contract with OC 405 Partners and issued Notice to Proceed (NTP) No. 1
On July 26, 2017, OCTA closed a $629 million Transportation Infrastructure
Finance and Innovation Act (TIFIA) loan with the US Department of Transportation
On July 27, 2017, OCTA issued NTP No. 2 to OC 405 Partners
DB current tasks include:
Final Baseline Schedule
– construction anticipated to begin in early 2018
Design
Right-of-way, utility relocations, and other risk items proceeding well
6
6
Preliminary Bridge Construction Timeline
7
7
City Coordination
Design Reviews
Transportation Management Plan (TMP)
Utility Agreements and Relocations
Corridor Cities Task Force Meetings
Emergency Services Coordination
School District Coordination
8
8
Public Outreach Update
9
9
Next Steps
10
10
Project Contact Information