Loading...
HomeMy WebLinkAboutSupplemental Questions Mayor Pro Tem Sustarsic 1 Questions for 4/22/19 City Council Meeting Schelly Sustarsic Warrants: Check # 10518 Pro-Cast Products 1st St. Restaurant $ 4,574.70 What project was this for? Grease Interceptor Check # 10506 Miracle Recreation Equipment Almond Park $3,599.46 Was this for a repair or replacement? Replacement equipment Check # 10477 City National Bank $ 45,905.45 Lease Agreement #13-030 What is this for? Climatec energy efficiency debt service payment. Item F: Annual Slurry Seal Project CIP ST1701-ST1801 and Item G: Annual Slurry Seal Project CIP ST1901: These projects were completed under the original contract award amounts. What do we think the reason was for this? The actual quantities used in the field were less than the estimated contract bid quantities and thus lowered the overall cost as compared to the contract bid amount. Item I: Parking Related Municipal Code Changes and Parking Policy Revisions: Just a couple questions for clarification: Page 3 of Staff Report: New: “Re-parking restrictions in timed parking zones. Sets a 150 feet restriction.” Should this say Commercial? Yes for better clarification, thank you. We will make the change. Do we have residential “timed parking zones?” City streets with permit requirements are considered the time-restricted zones in the residential areas. 8.15.070.C. How will drivers know that the theater is open? Will there be signage? The signage that would be installed at that location notifying parkers of short-term parking would also include the operating hours for the theater. 8.15.095. How will the locations of the Taxi/Rideshare stops be determined? Will there be input from businesses and community in helping to determine these? The Traffic Engineer has authority to determine locations for active passenger loading and unloading. Proposals for two loading/unloading locations – one on the west side of Ocean Ave across from Bogarts Coffee and one in front of the Bay Theatre, have been submitted. 2 Item L: Pier Project: In the Project Change Orders (PCO’s) Summary Table on page 3 of the Staff Report, there is an entry of $685,129.06 for “Per Bid Contract Soft Costs.” I did not see these explained. What, specifically, do these charges include? “Soft Costs” is a construction industry term used to account for an expense item that is not considered direct construction cost. “Soft Costs” typically includes architectural, engineering, financing, inspection, management, and other pre- and post-construction expenses. For the Pier Improvements Project, the "soft costs" include construction management and inspection (Simplus) and construction support services by both design engineers (AKM and Moffatt & Nichol).