HomeMy WebLinkAboutItem I November 8, 1999 STAFF REPORT To: Mayor and Members of the City Council Attention: Keith R. Till, City Manager From: Stephen G. Badum, Director of Public Works/City Engineer Subject: STATUS REPORT— SEWER MASTER PLAN AND RATE STUDY ANALYSIS SUMMARY OF REQUEST: The proposed action will approve in concept the City's financial plan to implement.the first phase recommendations of the Sewer Master Plan. DISCUSSION: On February 9, 1997, City Council approved a professional services agreement with AKM Consulting Engineers to prepare the City's Storm Drain and Sewer Master Plans. In February 1999, the scope of this agreement was expanded to include an analysis of the City's sewer rates. In general, the Master Plan reveals the need to implement approximately $10 million in capital improvements and replacements over the next 10 years. Discussions with the Orange County Sanitation District indicate that matching funding up to $2 million may be available which would leave a balance of approximately $8 million to be financed by the City. The City's sewer rate structure is based upon usage only and there are no capital charges for improvements and replacements. Sewer user fees are currently levied at 22% of the users water bill. The current revenues cannot support the recommended capital improvement plan. It is proposed that a capital charge of$8 per month be added to the residential sewer bill to cover the first phase costs of the needed ten-year capital plan. During the course of the Master Plan review, it was determined that the Seal Beach Boulevard Force Main, which serves all of Old Town, Bridgeport, Coves, and Marina Hill areas of Seal Beach, is inneed of immediate replacement and has been designated as the first project of the ten year plan. The cost of the proposed project has been estimated at $1.3 million. The City has recently received 50% matching Federal funds in the amount of $650,000 to rehabilitate Seal Beach Boulevard from Adolfo Lopez Drive to the I-405. In order to maximize the effectiveness of this paving project, it would be appropriate to advance the sewer force main project and complete the needed work before or 1 AGENDA ITEMZf Status Report—Sewer Master Plan City Council Staff Report November 8, 1999 concurrently with the paving rehabilitation project. However, the City's cash balance in the Sewer Enterprise fund cannot cover the cost of this needed capital replacement. Bonded indebtedness could be used to generate the needed funds immediately to advance the force main replacement project and support the ten year capital program. Upon conceptual approval, staff will finalize the Master Plan and Rate Study, submit it to City Council for final approval, and initiate the rate revision process. Any future rate changes would be subject to a balloting of residential, commercial, and industrial rate payers. FISCAL IMPACT: There are no fiscal impacts at this time. Future decisions by City Council may result in a rate increase for sewer utility users. RECOMMENDATION: It is recommended that City Council: 1. Conceptually approve the City's financial plan to implement a capital charge to fund the recommendations of the Sewer Master Plan. 2. Conceptually approve the City's financial plan to obtain bond funding to advance the Sewer Force Main Project and the ten-year capital improvement plan. 3. Direct staff to proceed with the finalization of the Sewer Master Plan and Rate Study for Council approval. 4. Direct staff to initiate the sewer rate revision process. NOTED AND APPROVED .1-3 _/ 4-I en . Badum, Director Keith R. Till Public orks Department City Manager C:\pwd\council\report\1999-2000\Status Report—Sewer Master Plan.doc 2