HomeMy WebLinkAboutFY20-21 CIP Presentation (9-28-20) (SM2)(KT1)FY 2020-25
5-YEAR CAPITAL
IMPROVEMENT PROGRAM
SEPTEMBER 28, 2020
1
agenda
•General Fund Available Balance
•5-Year CIP Funding Overview
•Unfunded Capital Projects
•Specific Capital Projects
Tennis Center Locker Room/Gym Building
Pier Abutment Improvements
Main Street Improvement Program
Lifeguard HQ/PD Substation
Community Pool
2
general fund – available balance
$ 22,700,000 – Estimated Fund Balance at 6/30/20
( 9,950,000) – Committed Fiscal and Economic Contingency
( 1,396,000) – Committed for Pier Restaurant Project
( 4,550,000) – Committed for Swimming Pool Project
( 1,700,000) – Committed or Assigned for Various Purposes
( 3,000,000) – Projected CIP Transfers for FY 2020-21
$ 2,104,000 – Balance Available for CIP or Operations in Future
3
fiscal year 2020-25 CIP fund summary
Source
General Fund (001) $14,863,000
Tidelands (043)* $ 2,130,000
SB-1/RMRA (039) $ 2,000,000
Gas Tax (040) $ 2,350,000
Measure M2 (042) $ 2,100,000
Grants (080) $ 1,305,000
Sewer Enterprise (044) $ 5,590,000
Water Enterprise (019) $19,275,000
TOTAL $49,613,000
*Tidelands Fund is 100% subsidized by the General Fund
4
unfunded projects
•Storm Drain Master Plan Projects (est. cost = $106 million)
•City Facilities Improvements (est. cost = $ 40 million)
•City Parks Master Plan Projects (est. cost = $ 6 million)
•Citywide Concrete Rehabilitation (est. cost = $ 1 million)
•PCH Median Project Citywide (est. cost = $ 350,000)
•Alley Pavement Rehabilitation (est. cost = $ 1 million)
5
SPECIFIC PROJECTS
•tennis center locker room
•concrete pier abutment rehabilitation
•main street improvement program
•lifeguard headquarters/PD substation
•community pool 6
5-year capital improvement program
•Sets priorities and appropriates funds for FY20/21
•Provides a basis for project planning and identify
coordination needs for FY21/22 through FY24/25
•Develops, constructs, and maintains public
improvements
•Addresses significant maintenance and upgrade needs
•Responds to changing legislation, conditions and
priorities
7
tennis center locker room/gym
•Constructed in the 1970’s
•Approximately 3200 square feet in size
•Facility consist of (men and women):
Restrooms
Showers
Locker rooms
Coed gym (space converted in 2015 from an atrium)
•Sauna and spa no longer operational
•New roof Installed in 2019
8
tennis center locker room/gym
existing
gym
women’s
showers/Sauna
building foot
print
men’s
showers/spa
9
tennis center locker room/gym
Eastside Elevation Westside Elevation
Interior - Men’s Shower Area
10
tennis center locker room/gym
•Reconstruction of shower
Enclosures
•Major restroom Renovation of
restrooms
•General Renovations
Locker rooms
Lobby areas
Gym
•Install new Exterior siding
(west side)
•Properly abandon spa &
Sauna
Project Budget: $650,000
•Remove showers/ shower
enclosures
•Repair/replace building
siding (east and west sides)
•Properly abandon spa &
Sauna
•Minor Building Renovations
Option 1
Renovate Showers / Building
Option 2
Remove Showers
Project Budget: $100,000
11
tennis center locker room/gym
Project Phases
FISCAL YEAR – Project Allocations
2020-21 2021-22 2022-23 2023-24 2024-25 Totals by
Phase
Architectural Design $60,000 $ 60,000
CM / Inspection $60,000 $ 60,000
Construction $530,000 $530,000
Totals by Fiscal Year: $60,000 $590,000 $650,000
Project Budget* by Fiscal Years
12
*Option 1, shower / building renovations, budgeted
pier abutment improvements
13
pier abutment improvements
14
Seal Beach Pier
Pier Abutment Structure
concrete base deterioration – examples
pier abutment improvements
15
•Patch and repair cracks in the walking surfaces, walls, and ramps
•Seal deck expansion joints to eliminate water infiltration
•Install addition deck drains
•Reconstruct light fixture bases / install missing light fixtures
•Apply new concrete water proofing coating to wall surfaces
Project Budget: $400,000 (FY 2021-22)
Concrete Pier Abutment Restoration Scope of Work:
pier abutment restoration
16
Pier improvements
Projects
FISCAL YEAR – Project Allocations
2020-21 2021-22 2022-23 2023-24 2024-25 Totals by
Phase
Pier Abutment
Restoration $400,000 $ 400,000
Pier Restrooms
restoration $180,000 $180,000
8th St. / 10 St. parking
lot rehabilitation $350,000 $350,000
Beach Planter Ring
replacements $300,000 $300,000 $600,000
ADA Ramp / 10th
Street Parking Lot $300,000 $300,000
Totals by Fiscal Year: $1,230,000 $300,000 $300,000 $1,830,000
Tidelands Fund – Capital Projects
17
main street improvement
18
main street improvement
•Allocated $500,000
•Retained RHd/o to prepare concept design & conduct public
outreach (phase 1)
Formed Steering Committee
Planned 1st Public Outreach meeting
Postponed due to COVID-19
FY19-20 - Status
19
main street improvement
•Carryover FY19-20 budget
•Reconvene public outreach
•Incorporate economic
development elements
•Complete concept design
plan
•Define future infrastructure
projects
FY20-21 – Next Steps
20
main street improvement
21
Project Phases
FISCAL YEAR – Project Allocations
2019-20
(carry over) 2020-21 2021-22 2022-23 2023-24 2024-25 Totals by
Phase
Concept Design $ 100,000 $ 100,000
Engineering & CM $ 287,000 $ 237,000
Construction $ 500,000 $ 500,000 $1,000,000
Totals by Fiscal Year: $ 387,000 $ 500,000 $ 500,000 $1,387,000
Main Street Corridor – Program Budget
lifeguard headquarters/
PD substation
22
lifeguard headquarters/
PD substation
Lifeguard HQ /Police
Substation
Project Limits
23
lifeguard headquarters/
PD substation (Opt. 4) beach level – 1st floor
24
lifeguard headquarters/
PD substation (Opt. 4) pier level – 2nd floor
25
lifeguard headquarters/
PD substation (Opt 4) Dispatch level – 3rd floor
26
lifeguard headquarters/
PD substation (Opt. 4)
•ADA compliance in publicly accessible areas, only
•Use of conventional foundation
•Based on current height/footprint per existing regulatory
requirements
•No off-site work
assumptions
inclusions
•Replace existing building with appropriately sized facility
Existing Building = 5,257 SF
Proposed Building = ~8,556 SF w/enhanced circulation
27
lifeguard headquarters/
PD substation
Project Phases
Gut / Renovate
Existing Building
($)
DEMO Existing Building/
New Construction
($)
Architectural/Engineering $560,000 $770,000
Program/ Const. Management $750,000 $700,000
Environmental $83,000 $83,000
Deputy Inspection / Testing $50,000 $200,000
Construction $3,418,000 $7,160,000
Fixtures & Furnishings $250,000 $382,000
Electronic Systems / Equipment $170,000 $170,000
Total Project Costs*: $5,281,000 $9,500,000
OPTION 1 OPTION 4
Project Cost Estimates
28
*Construction costs are based on Nov 2019 values and include future escalation for January 2023 construction
Project Phases
FISCAL YEAR – Project Allocations
2020-21 2021-22 2022-23 2023-24 2024-25 Totals by Phase
Preliminary Design/
Environmental/Permitting $250,000
$ 250,000
Engineering/Design $ 550,000 $ 550,000
PM /Const. Management $ 350,000 $ 350,000 $ 700,000
Construction $3,350,000 $4,650,000 $ 8,000,000
Totals by Fiscal Year: $ 250,000 $ 550,000 $3,700,000 $5,000,000 $9,500,000
lifeguard headquarters/
PD substation
Project Phasing by Fiscal Year
*Construction costs are based on Nov 2019 values and include future escalation for January 2023 construction 29
community pool
30
McGaugh Pool
community pool
31
community pool
Proposed City Aquatic Center
-Navy Site Plan-
32
Seal Beach Boulevard Adofo Lopez Drive
outreach
2 public outreach sessions – 2/13/20 & 2/22/20
Parks & Recreation Commission - 2/26/20
community pool
SUPPORT
•Importance of teaching children to swim
•Providing exercise opportunities and
enhancing individual health
•Creating and providing for a sense of
community
•Providing outlets for local aging
population and youth
•Space for the swim team/club
•Issues with McGaugh Pool operation /
condition
CONCERNS
•High cost
•Lack of funding
•Other available pools
•Preference of McGaugh site
•Desire to see smaller site and/or an
option with less amenities
33
13 153 1 1 2 3
34
12
1
164
35
28
3
77
127
11
67
38
5
12
7
15
17
48
13
62
36
capital costs community pool
Project Phase
OPTION 1:
50M POOL
OPTION 2:
25Y STRETCH
(40M) POOL
1 CONSTRUCTION COSTS (POOL,BUILDING, AND SITE) $16,190,489 $14,966,777
2 CONSTUCTION COSTS (NAVY REPLACEMENT BUILDINGS) 1,135,000 1,135,000
3 FIXTURES, FURNISHINGS, & EQUIPMENT (FF&E) 615,000 565,000
4 ARCHITECTURAL & ENGINEERING SERVICES 2,086,255 1,951,255
5 CONSTRUCTION MANAGEMENT/SPECIAL INSPECTIONS 890,000 890,000
6 CITY CONTINGENCY (10% CONSTRUCTION & 5% SERVICES) 1,796,049 1,664,678
TOTAL PROJECT COSTS: $22,713,000 $21,173,000
*Construction costs are based on Nov 2019 values and include future escalation to the midpoint of construction (Nov 2023)
Project Cost Estimates
37
community pool
CATEGORY
ANNUAL COST
1 30-YEAR LEASE* $ 455,000
2 STAFFING / OPERATIONAL COSTS $ 500,000
3 DEBT SERVICE $1,250,000
4 MISCELLANEOUS/INCIDENTALS $ 100,000
TOTAL O&M COSTS**
$2,055,000
*Annual O&M costs does not include Navy in-kind contribution or potential sponsorship income
**Annual debt service costs are estimated based on the cost of the project
Project Annual O&M Costs
38
status
community pool
•Community Outreach conducted in February 2020
•Navy site appraisal / draft lease
•Environmental phase on-going
•Design phase on-hold
•Program management support consultant effort on-hold
39
fiscal year 2020-21 funding
•Tennis Center Locker Room (design) $60,000
•Lifeguard HQ/PD Substation (Phase I design) $250,000
•Main Street Improvement Program (carry over)
•Community Pool (carry over)
TOTAL $310,000
40
fiscal year 2020-25
summary of project costs
Project Title
FISCAL YEAR – Project Allocations
2019-20
(carry over) 2020-21 2021-22 2022-23 2023-24 2024-25 Totals
Tennis Center Locker
Room / Gym Renovation $60,000 $590,000 $650,000
Pier Abutment
Renovation $400,000 $400,000
Main Street
Improvements $387,000 $500,000 $500,000 $1,387,000
Lifeguard HQ/Police Sub
Station $ 250,000 $550,000 $3,700,000 $5,000,000 $9,500,000
Community Pool $200,000 $200,000
Totals by Fiscal Year: $587,000 $310,000 $2,040,000 4,200,000 $5,000,000 $12,137,000
41
next steps
42
•Facilitate in-depth conversation at the next Strategic Planning
meeting
•Obtain City Council and Community input on priorities for
these projects
•Once priorities are determined, develop a financing plan to
see these projects to completion
questions & comments
43