HomeMy WebLinkAboutCC AG PKT 2006-11-13 #G
e
e
e
AGENDA REPORT
DATE:
November 13,2006
TO:
Honorable Mayor and City Council
THRU: JohnB. Bahorski, City Manager'
FROM: Mark Vukojevic, P.E., Director of Public Works, City Engineer
SUBJECT: AWARD CONSTRUCTION CONTRACT FOR PIER DECK
REHABILITATION - PHASE I, PROJECT NO" 50217
SUMMARY OF REQUEST:
The proposed City Council action will approve the plans and specifications for the Pier Deck
Rehabilitation, award a construction contract to the lowest responsible bidder, John S. Meek
Company Inc., in the amount of $262,925, authorize the City Manager to execute the agreement,
and approve a budget amendment in the amount of $70,000 from the General Fund.
BACKGROUND:
The Seal Beach Municipal Pier originally was constructed in 1906, is approximately 1800-feet
long consisting mostly of poly-wrapped timber piles, timber support members and a timber deck.
The Pier was severely damaged by the winter storms in 1982/1983 and it was partially rebuilt
after the damage. Lifeguards and Public Works' crews have regularly inspected and monitored
various components of th,e Pier. The fender'piles, which are the outermost piles adjacent to the
boat ramps were professionally inspected and evaluated by a consultant in 1993. The concrete
portion of the Pier was professionally inspected and evaluated by a consultant in 1999. On
August 26, 2002, Council awarded a professional services contract to Han-Padron Associates to
inspect and evaluate the timber Pier.
Inspections and testing were conducted in October and November of 2002. The inspection
included a visual and tactile examination of all accessible components of the structure, above and
below the waterline, The report concludes that the Pier is in fair condition according to the
standards set by the American Society of Civil Engineers (ASCE) Standard Practice Manual on
Underwater Investigations. However, at that time several elements of the Pier were in need of
repair and replacement including structural components, utilities, preservation components and
aesthetic features. On February 10, 2003, a $500,000 budget amendment from general fund
reserves was approved by City Council for the structural repair of the Pier. Improvements were
completed in late 2003.
Overall, the Pier and its deck are in fair condition and because of its timber construction, surfaces
and appearance are rough and rustic. Routine inspections are performed by the Public Works
Department to identify components needing repair, adjustment, and preventative measures.
"Flipping over" the boards has been attempted in the past with limited success due to the
splintering/splitting of the decking.
Agenda Item ()
.'
e
At the October 24, 2005 City Council meeting, City Council received public comments
regarding the rough (non-uniform) surface condition of the Pier deck. City Council directed
Staff to provide additional information regarding the Pier. As outlined above, the Pier was
structurally assessed above and below the water line and repaired in 2003. The next major
structural inspection of the Pier is tentatively scheduled for 2008. Monthly inspections and
repairs are made by Public Works Staff for surface items such as decking, railing, lights, etc,
However, the historic aged timber surface can be rough and uneven. Pedestrians are cautioned
with signs at the entrance to the Pier regarding the uneven surfaces.
A study was conducted by Moffatt & Nichol in May of 2006 to study alternatives for
rehabilitation of the decking on the Pier. A life cycle cost analysis was prepared along with other
factors including aesthetics, safety, comfort, and fire resistance and the recommendation of the
report was to replace the decking on the Pier with an imported "Greenheart" hardwood. The
hardwood is a higher costing alternative than replacing the decking with the existing Douglas fir
wood, but has a longer life. Both options were bid, however, to identifY what the difference in
cost between the two alternatives actually came up to.
3 Bids were received and opened by the City Clerk on Tuesday, October 31, 2006 and are listed
below:
Douglas Fir Greenheart
1 John 8" Meek Company, Inc" $224,600,,00 $262,925.00
2 Buso Constructors, Inc. $278,900.00 $310,400.00
e 3 Connolly Pacific Company $252,700.00 $340,700.00
The bids received were higher than originally estimated during last year's budget process due to
a variety of factors. Re-bidding the project is not expected to net any further savings. It is
recommended that City Council move forward with the project including longer life Greenheart
wood and the recommended budget amendments as outlined in the Fiscal Impact section.
Staff has reviewed the submitted bid documents and found the low bidder to be in compliance
with the contract documents. Upon the successful execution of the contract documents, the
project is scheduled to begin in December. The contractor will have several. months to procure
the Greenheart Hardwood, but only 4 to 6 weeks to construct the improvements. There is no
daytime Pier closures scheduled with this project. The contractor will be working at night and
reopen the Pier every morning. Specific notices will be sent to surrounding residents to inform
them about the construction impacts.
FISCAL IMPACT:
City Council has budgeted $250,000 for the design, construction, and inspection of Phase I for
this project within the City's 5-year Capital Improvement program. Additional funds are
required to construct this project. A budget amendment in the amount of $70,000 is required
from the General Fund. The current estimated fiscal year ending undesignated general fund
balance is $11,945,115. Approval of this budget amendment will decrease the estimated ending
e undesignated fund balance by $70,000 to $11,875.115.
Agenda ltem_
e
e
e
.
RECOMMENDATION:
It is recommended that the City Council approve the plans and specifications and adopt
Resolution No. awarding a construction contract for the Pier Deck Rehabilitation - Phase
I, Project No. 50127, to the lowest responsible bidder, John S. Meek Company Inc., in the
amount of $262,925, and authorizing the City Manager to execute the agreement. Adopt Budget
Amendment No.07-08 in the amount of $70,000 from the General Fund.
Prepared By:
Sean P. Crumby, P.E.
Deputy City Engineer
Concur:
~4 "
Mark . Vukojevic, P.E.
Director of Public Works/City Engineer
Attachment:
Proposed Resolution No. _ authorizing Award Contract
Proposed Budget Amendment Resolution No, 07-08
Agenda Item_
e
RESOLUTION NUMBER
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEAL
BEACH A WARDING THE CONSTRUCTION CONTRACT FOR PIER
DECK REHABILITATION, PHASE I, PROJECT NO. 50217
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF SEAL BEACH DOES
HEREBY RESOL VB, DECLARE, DETERMINE AND ORDER AS FOLLOWS:
SECTION 1. The City Council hereby approves the contract between the City of Seal
Beach and John S. Meek Company Inc. for the Pier Deck Rehabilitation,
Phase I, Project #50217.
SECTION 2. The Council hereby directs the City Manager to execute the contract for the
Pier Deck Rehabilitation (phase 1), Proj ect #50217.
PASSED, APPROVED AND ADOPTED by the City Council of the City of Seal Beach at a
meeting thereof held on the day of 2006 by the following
vote:
AYES:
Council Members
e
NOES:
Council Members
ABSENT:
Council Members
ATTEST:
Mayor
City Clerk
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF SEAL BEACH )
I, Linda Devine, City Clerk of the City of Seal Beach, California, do hereby certify that the
foregoing Resolution is the original copy of Resolution Number on file in the office
of the City Clerk, passed, approved, and adopted by the City Council of the City of Seal
Beach at a meeting thereof held on the day of ,2006.
e City Clerk
e
RESOLUTION NUMBER
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEAL
BEACH, CALIFORNIA, AUTIlORIZING A BUDGET AMENDMENT,
NO, 07-08 FOR THE INCREASE IN THE CAPITAL PROJECT FUND,
CONTRAcr PROFESSIONAL SERVICES (PROJEcr 50217- PIER
DECK REHABILITATION, PHASE I)
WHEREAS, tbeliscal year 200612007 budget requires budgetary amendments as outlined below:
THE CITY COUNCIL OF mE CITY OF SEAL BEACH DOES HEREBY RESOLVE:
REVISEDI
ADOPTED PROPOSED BUDGET (difi)
QW ACCOUNT BUDGET BUDGET AMENDMENT
Contract Prof, Svcs, 045-333-44000 57,530,500 57,600,500 $70,000
Transfer In 045-000-31500 $6,951,700 $7,021,700 $70,000
General Fund - Transfer Out 001-080-47000 $3,328,296 $3,398,296 $70,000
Tidelands - Transfer In 034-000-31500 $1,513,296 $1,583,296 $70,000
Tidelands - Transfer Out 034-863-47000 $850,000 $920,000 $70,000
PASSED, APPROVED AND ADOPTED by the City Council of the City ofSoaI Beach on this
_dsyof 2006 by the following vote:
AYES:
Councilmembers
e
NOES:
Councilmembers
ABSENT: Councilmembers
ATTEST:
Mayor
City Clerk
STATE OF CAUFORNIA)
COUNTY OF ORANGE ) SS
CITY OF SEAL BEACH )
I. LInda Devine. City Clerk of Seal Beach, Cahfomia, do hereby certify that the foregoing rcsoluhon is
the original copy of Rosol uti on Number _ on file in tbe office oftbe City Clerk, passed,
approved, and adopted by the City Council of the City of SoaI Beacb, at a regular mooting tberoofbeld
on tbe day of , 2006.
City Clerk
e