HomeMy WebLinkAboutCC AG PKT 2006-11-13 #I
AGENDA REPORT
e
DATE:
November 13, 2006
TO:
Honorable Mayor and City Council
THRU: John B. Bahorski, City Manager
FROM: Mark Vukojevic, P.E., Director of Public Works, City Engineer
SUBJECT: AWARD CONSTRUCTION CONTRACT FOR WEST END
STORM WATER PUMP STATION REHABILITATION,
PROJECT NO. 50050
SUMMARY OF REQUEST:
The proposed City Council action will approve the plans and specifications for the interim
improvements to West End Storm Water Pump Station Rehabilitation, award a construction
contract to the lowest responsible bidder, SoCal Pacific Construction Inc., in the amount of
$2,363,777, authorize the City Manager to execute the agreement, and approve a budget
amendment transferring $641,000 in Redevelopment Agency Funds and $255,000 from the
Environmental Reserve Account.
e BACKGROUND:
The West End Pump Station was originally constructed in 1959 as a means to pump storm water
run-off from a 165-acre watershed covering portions of Marina Hill North, Bridgeport and Old
Town into the San Gabriel River. The station has two natural gas engines driven propeller
pumps each rated at 25,000 gallons per minute. The streets in the adjacent Mobile Home Park
drain directly into the wet well of the Pump Station. Consequently, during heavy rains the Park is
flooded whenever the water level in the wet well exceeds the street elevation. Capacity upgrades
and improvements to the pump station have not kept up with the growth of development in the
City.
A fire at the Station during a storm in 2000 completely damaged one of the two natural gas
engines leaving the station at half capacity. The burned engine was replaced by an engine
obtained from the County of Orange and reconditioned at the City's expense in October 2001.
Since, that time, both pumps and both engines have been rebuilt to maintain their functionality.
Other minor improvements were also made to the station at that time.
e
The West End Pump Station does not ha~e capacity adequate for the current standards and it
lacks proper controls. In early 2001, the City retained AKM Consulting Engineers to prepare a
Preliminary Design Report (PDR) for construction of a new Pump Station to replace the existing.
The PDR evaluated the hydrology of the drainage site among other things and found that the
existing pumps do not have sufficient capacity to handle the standard 25-year storm-flow criteria.
According to the PDR, the existing pumps can handle only a 2 to 3 year storm flow, Therefore,
the PDR recommended replacement of the existing station with a brand new station,
Agenda Item Z
e
e
e
During design of the Pump Station the project was split into two phases, The first phase, which is
the current proposed project, is designed to rehabilitate the existing pump station to maximize
the pumping capacity to approximately 200 cubic feet per second of water (a 100% increase in
capacity, 10-year storm flow), lower maintenance, and increase reliability of the station. Key
components within this project include structural improvements to the wetwell, mechanical,
building, piping, pumping and utility rehabilitation. The future phase will involve construction
of a second pump station for additional capacity
The City has acquired the property from Oakwood Apartments and it will be used as a
construction staging area for the first phase of the project, and will house the expansion of the
station in the second phase of the project. Negotiations with the Oakwood Apartments property
owners began in late 2004. Because the negotiations were not successful, eminent domain
procedures was initiated by Staff, In June and November of 2005 the City Council approved the
resolution to acquire the property.
Environmental st)ldies were initiated in 2003 to evaluate whether the proposed project could
have significant effect on the environment. The results of the analysis were finalized and
approved by Council in June 14,2004,
Permits have been required from various outside agencies for the construction of Phase II of the
project. Staff has successfully gained permits from the California Coastal Commission, the
Department of Fish and Game, and the Army Corps of Engineers, The Los Angeles County
Flood Control District has agreed to issue a permit when construction of Phase II nears.
The plans and specifications were designed by the City's Utility consultant AKM Engineers for
the first phase of the project and accepted by City Council on December 12, 2005.
3 Bids were received and opened by the City Clerk on Wednesday, November 1,2006 and are
listed below:
1 SoCal Pacific Construction Inc.
2 Denboer Engineering and Construction, Inc.
3 Orion Construction Corporation
$2,363,777.00
$2,386,250.00
$2,546,300.00
The bids received were higher than originally estimated during last year's budget process due to
overall fast rising construction costs. Re-bidding the project is not expected to net any further
savings. It is recommended that City Council move forward with the project including the
recommended budget amendments and transfers of funding as outlined ill the Fiscal Impact
section. Funding is proposed from the Redevelopment Agency Riverfront Project Area Funds
and from a recent one-time revenue in the Tax Increment Fund. These monies can only be used
on public projects benefiting the Redevelopment Area. In addition, in accordance with the
Environmental Reserve Tax (Section 4.45 of the Municipal Code), specific development fees
have been collected and are now available for use with this project. Expenditure of these funds
meet the specifications of the ordinance and have been reviewed by the City Attorney,
Staff has reviewed the submitted bid documents and found the low bidder to be in compliance
with the contract documents. Upon the successful execution of the contract documents, the
project is scheduled to begin in April. The contractor will have several months to procure
Agenda ltem_
materials, but can only construct improvements at the site during the summer dry season of 2007.
Specific notices will be sent to surrounding residents to inform them about the construction
impacts.
e FISCAL IMPACT:
$2.15 million has been budgeted in the current Fiscal Year for the construction and inspection of
this project within the City's 5-year Capital Improvement program and the City's Council
approved budget. Additional funds are required to construct this project and funding is available
from the Redevelopment Agency Riverfront Project Area Funds and from the City's
Environmental Reserve Account. A budget amendment in the amount of $641,000 is requested
from the Redevelopment Agency ($356,000 from Riverfront Project Area Fund Balance and
$285,000 from recent one-time revenue in the Tax Increment Fund) and $255,000 from the
Environmental Reserve Account.
RECOMMENDATION:
It is recommended that the City Council approve the plans and specifications, adopt Resolution
No. _ awarding a construction contract for the West End Storm Water Pump Station Pier
Deck Rehabilitation, Project No. 50050, to the lowest responsible bidder, SoCaI Pacific
Construction Inc., in the amount of $2,363,777 and authorize the City Manager to execute the
agreement; Approve Resolution No. _ authorizing a budget amendment transferring $641,000
in Redevelopment Agency Funds and $255,000 from the Environmental Reserve Account.
e
Sean P. Crumby, P.E.
Deputy City Engineer
Concur:
S,P.F.
Director of Public W orks/City Engineer
Allachment:
Proposed Resolution No. _ authorizing A of Contract
Proposed Budget Amendment Resolution No. 07-09
e
Agenda Item_
e
RESOLUTION NUMBER
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEAL
BEACH AWARDING THE BID FOR THE WEST END STORM WATER
PUMP STATION REHABILITATION, PROJECT NO. 50050
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF SEAL BEACH DOES
HEREBY RESOLVE, DECLARE, DETERMINE AND ORDER AS FOLLOWS:
SECTION 1. The City Council hereby approves the contract between the City of Seal
Beach and SoCal Pacific Construction Inc. for the West End Storm Water
, Pump Station Rehabilitation, Project No. 50050.
SECTION 2. The Council hereby directs the City Manager to execute the contract for the
West End Storm Water Pump Station Rehabilitation, Project No.50050.
PASSED, APPROVED AND ADOPTED by the City Council of the City of Seal Beach at a
meeting thereof held on the day of 2006 by the following
vote:
AYES:
Council Members
e
NOES:
Council Members
ABSENT:
Council Members
Mayor
ATTEST:
City Clerk
STATE OF CALIFORNIA )
COUNTY OF ORANGE )SS
CITY OF SEAL BEACH )
I, Linda Devine, City Clerk of the City of Seal Beach, California, do hereby certify that the
foregoing Resolution is the original copy of Resolution Number on file in the office
of the City Clerk, passed, approved, and adopted by the City Council of the City of Seal
Beach at a meeting thereof held on the day of , 2006.
e City Clerk
e
RESOLUTION NUMBER
A RESOLUTION OF lHE CITY COUNCIL OF lHE CITY OF SEAL
BEACH, CALIFORNIA,. AUTIl:ORIZING A BUDGET AMENDMENT,
NO. 07-1l9 FOR THE INCREASE IN lHE CAPITAL PROJECT FUND,
CONTRACT PROFESSIONAL SERVICES (PROJECT 50050- WEST END
STORM WATER PUMP STATION REHABILITATION, PHASE I)
WHEREAS, the fiscal year 200612007 budget requires budgetary amendments as outlined below:
TIlE CITY COUNCIL OF TIlE CITY OF SEAL BEACH DOES HEREBY RESOLVE:
REVISEDI
ADOPTED PROPOSED BUDGET (cliff)
DEPT ACCOUNT BUDGET BUDGET AMENDMENT
Contract Prof. Sves. 045-333-44000 57,600,500 58,496,500 5896,000
Transfer In 045-000-31500 57,021,700 57,662,700 5641,000
Developer Impact Fe.. 045-000-30865 5255,000 5255,000
Riverfront Project Area Fund
- Transfer Out 063-081-47000 $2,818,500 $3,174,500 $356,000
Tax Increment Fund
- Transfer Out 067-081-47000 $782,520 $1,067,520 $285,000
PASSED, APPROVED AND ADOPTED by the City Council of the City of Seal Beach on this
_day of 2006 by the following vote:
e
AYES:
CounciJrnembers
NOES:
Councilmembm
ABSENT: CouncIlmembers
Mayor
AITEST:
City Clerk
STATE OF CALIFORNIA)
COUNTY OF ORANGE ) SS
CITY OF SEAL BEACH )
l, Linda Devine, City Cieri< of Seal Beach, California, do hereby certify that the foregoing reaolution 15
the original copy of Resolution Number _ on file In the office of the City Clerk, passed,
approved, and adopted by the City CouncIl of the City of Seal Beach, at a regular meeting thereof held
on the day of , 2006.
e
City Clerk