AGENDA REPORT
DATE:
November 5, 2007
TO:
Honorable Mayor and City Council
THRU:
David N. Carmany, City Manager
FROM:
Vince Mastrosimone, Director of Public Works
SUBJECT:
RIVERS AND MOUNTAINS CONSERVANCY (RMC)
GRANT AGREEMENT
SUMMARY OF REQUEST:
The proposed City Council action will approve Resolution No. 5627 directing the City
Manager to sign the attached Ri vers and Mountains Conservancy Grant Agreement.
e
BACKGROUND:
The San Gabriel and Lower Los Angeles Rivers and Mountain Conservancy (RMC) is an
independent State agency within the Resources Agency of the State of California
established in 1999. Its jurisdiction includes the San Gabriel River and its tributaries, the
lower Los Angeles River and its tributaries, and the San Gabriel Mountains, Puente Hills,
and San Jose Hills. It was established to preserve open space and habitats in order to
improve watersheds, provide low-impact recreation and educational uses, and restore and
protect wildlife and habitat.
The voters of California passed the Water Security, Clean Drinking Water, Coastal and
Beach Protection Act of 2002 (Proposition 50) on November 5, 2002. It added to the
California Water Code, Section 79541, authorizing the Legislature to appropriate $100
Million for the acquisition, restoration, protection and development of river parkways.
Staff has previously submitted a grant request to the RMC asking for over a million
dollars in funding for the construction of the River's End Staging Area and Parking Lot
Project. $500,000 of the requested amount has been allocated from the RMC to facilitate
the construction on this project. Attached are the Grant Agreement Cover Sheet for this
grant along with referenced Exhibits A, Band C.
e
The City is requesting additional funding from the State Resources Agency in the amount
of $850,000. This funding will help restore the existing San Gabriel River trail and
trailside facilities. It will upgrade the site to feature new amenities such as informational
Agenda Item K
signage, bike trail restoration, native landscaping, storm drain compliance improvements
and seating.
e
Also, the City is requesting an amendment from the RMC for an additional $1.5 million
to complete this project. The costs to complete this project in its entirety, which includes
improvements to public parking, restaurant, adding additional picnic areas, and native
plant re-vegetation of a small dune area immediately adjacent to the subject project along
with additional design, pennitting and project management costs, are now estimated at
approximately $2.85 million. Included in this amendment request will be an updated cost
estimate IlI':d project timeline.
The action contemplated herein relates to the initial $500,000 RMC Grant. Additional
Council actions will be needed for the other two grants.
FISCAL IMPACT:
There will be no fiscal impact to the City.
RECOMMENDATION:
It is recommended that the City Council approve Resolution No. directing the City
Manager to sign the attached Rivers and Mountains Conservancy Grant Agreement and
send it to the State of California, Resources Agency.
e
Prepared By:
. ld L Spitz, P.
Associate Engineer
NOTED AND APPROVED:
ince Mastrosimone
DirectorofPublic~orks
~~
David N. CarmanY
City Manager
Attachments: Rivers and Mountains Conservancy Grant Agreement
Resolution No._ Rivers and Mountains Conservancy Grant Agreement
e
Agenda Item
RESOLUTION NUMBER 5627
e
A RESOLUTION OF THE CITY COUNCH. OF THE CITY OF
SEAL BEACH APPROVING THE AGREEMENT FOR GRANT
FUNDS FOR THE SAN GABRIEL RIVER TRAIL
ENHANCEMENTS PRQJECf THROUGH THE CALIFORNIA
RIVER PARKWAYS GRANT PROGRAM UNDER THE WATER
SECURITY, CLEAN DRINKING WATER, COASTAL AND
BEACH PROTECfION ACT OF z002 (pROPOSmON SO) AND
DIRECTING THE CITY MANAGER TO SIGN THE GRANT
AGREEMENT
WHEREAS, the Legislature and Govemor of the State of California have
provided Funds for the program shown above; and
WHEREAS, the Resources Agency has been delegated the respllIllibility for the
administration of tbis gnmt program, establishing necessary procedures: and
WHEREAS, the City had opplied for funding through the State Resources Agency
to construct the above named project and was given a total grant amount of $500,000
w,th the state to carry out the project.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
Seal Beach, does hereby authorize the City Manager to execute the Grant Agreement
with the Rivers and Mountains Conservancy pursuant to the Water Security, Clean
Drinking Water, Coastal and Beach Protection Act of 2002 (Proposition 50) to fund the
project up to the grant amount.
e
PASSED, APPROVED AND ADOPI'ED by the City Council of Seal Beach, at a regular
meeting held on the 5th day of November. 20CYI by the following vote:
AYES: COUNCILMEMBERS
NOES: COUNCILMEMBERS
ABSENT: COUNClL..\ffiMBERS
ABSTAIN: COUNCILMEMBERS
Mayor
ATIEST:
City Clerk
STATEOFCALIFORNIA }
COUNTY OF ORANGE } SS
CITY OF SEAL BEACH }
e
I, Linda Devine, City Clerk for the City of Seal Beach, California, do hereby certify that
the foregoing resolution is the original copy of Resolution Number 5627 on file in the
office of the City Clerk, passod, approved, and adopted by the City Council of the City of
Seal Beach at a regular meeting held on the ~ day of November , 2007.
City Clerk
Agreement Number: RMC3573
e
GRANT AGREEMENT
RIVERS AND MOUNTAINS CONSERVANCY (RMq
State of Califomia - The Resources Agency
e
GRANTEE City of Seal Beach
PROJECT TITLE Sen Gabriel River Trail Enhencements Develooment
PERFORMANCE PERIOD Januarv I 2006 I tbroul!h I Dec. 31 2008
Under the ,lcmls BJid conditiol1ll oCthis Agreement, Ibe Granttc agn:cs to complete Ibe Project 81 described in the project description, and the
State oCCalifornia, throu~ its Executive Omcer oClbe Rivers and Mountains Conscrvancy punuant to Ibe Water Security, Clean Drinking
Water, Coastal and Bcacp. Protection Bond Act oC 2002 (Proposition 50), ogccs to fund the Project up to the Grant Amount
.
PROJECT DESCRIPTION
"
The project will rcstoze tI1c cxlsting SIUl Gabriel River Troil and the 1railsidelilcilities from Ibe 1 d street Parking Lot to Marina Drive and
Uppc the site to feature new amenities. The rcstontion win include interpretive, wayfinding and Illgulatmy signagc.
Project is cmied out in COIIf'orlDlUlce with Ibe Tasldist IUld T~inc attacbed as Exhibit A. the Budget attacbcd as Exlubit B, and Ibe
Monitoring and Assessment Plan attacbed as Exhibit C (herein Bftor rcfc:rred 10 as the "Work Plan" IUld all As!ccmcnt Provisions as stated
borcin.
TOTAL GRANT AMOUNT NOT TO EXCEED I $500.000.
The General end Special Provisions attached are made a art of end incornorated into the Aereement
GRANTEE: GRANTOR:
City of Seal Beach . , J:UVERS AND MOUNTAINS CONSERV ~CY
STATE OF CALIFORNIA
City Hall-2II Eighth Street 900 South Fremont Avenue, Apnex, 2"" Floor
Seal Beaclh CA. 90740 Alhambra, CA 91802
BY (AlJTIIOIUZllD S1GNATUllI!) BY (AtrrHOIUZllD S1GNA1'UlUl)
P1UNTBD NAME AND nnJ! OF PIlR80N SIGNINO PIUNTI!D NAME AND 11TLIl OF PERSON SIONlNO
City Manallllr Belinda V. Faustinos, Executive Officer
DATIl SIGNI!O DATB""""IW
CERTIFICATION OF FUNDING (FOR STATE USE ONLY)
AMOUNT OF GRANT AGREEMENT NUMBER. FUND - 6031
$500 000 RMC 3573 Water Security, Clean Drinking Water,
ADJ. INCREASING ENCUMBRANCE APPROPRIATION Coastalll!ld Beach Prote!llion Bond Act
of2002
ADJ. DECREASING ENCUMBERANCE FUNCTION
TOTAL GRANT AMOUNT LINE ITEM ALLOTMENT CHAPTER STATUTE FISCAL
$500,000 3825-301-6031010 38 2005 YEAR
06107
T.BA NO. I B.R. NO. INDEX I OBJ. EXPEND PCA PROJECTIWORK
L120 418 30106 PHASE
.
I hen:by certify upon my personal knowledge that budgeted funds are available for this. encumbrance. .
SIGNATURE OF ACCOUNTING OFFICER DATE
"
e
Page 10f36
e
...
c
CI>>
E ~
m=
u CI>>
c E
as ._
.cl-
c"CI
wc!'?
-as""
e!:!!~
...:;:0
~lQ!!l
ii:1-~
a;<i
.- ...
... .-
.a.a
as ,-
C)~
cW
as
tJ)
e
...
'2
c
...
~
II
en
... .
~ .
~
~
..
...,
i
en
l:.
..L
"
...,
...
~
...
<
~
..
...,
~
ell
~
"
...,
~
~
~
..
...,
In
.J: ~
[;l - I~ .f.!
I!! I~ aI In
- .l!I
:> "
0 ~ N C') ~ N C') ~ ~ N I!! <: -
: ~ CUGl III CU CU CU CU CU CU aI 0
CU
lUl :a :a In In :a In > ~ <:
<: aI aI aI aI 0 ~
:> .J: .J: .J: .J: .J: .J: .J: .J: .J:
E 0. 0. 0. 0. 0. 0. 0. 0. 0. .. .~ g
<: E ,~ Ii E
0 0 aI 0
. :g (J <: <: (J
c 0 aI
.<: oil 0 c I~ ::E
<J In I 0 'is c
l3 l := :s .S! ~ e 0.
0 '0 .. I~
tl -
... :a e ~ "
[Q ,I 0 c c e
II 0 'C ~I I
I- ::E 0 (J .. 0.
Bir.blj~
e
RIVER'S END STAGING AREA ENHANCEMENT PLAN
City of Seal Beach
OPINION OF PROBABLE CONSTRUCTION COSTS
Prepared Saptambar 12, 2005
Prepared hasad on lha 1st Submittal Construction Documenta dated August 31, 2005
RBF Consulting
IN.: 1 G-l 03934.001
e
~'Rr~-"'-- - ..- , ,- ---~ --..,. c' ,~- _,_"'_C 'l!l:l'lt~'\1'- '11-- '--'I'I~'- "-~-- y=~',-- T"'''''~~~'-J
r1r~~ II ~ . ,"'.>-' ',.. .' ,"'~~_1~_ ..:. 'r~ "~. ". ~~ -~ ' . ,\.... ~ 1"""~ _ .,,:' ,.c, ,,, 'r -{':~"
':,'111: ",fh. ~"..~,~_,~,'}I'h'l,o}~~:~" V,:.:. ,:_',c,~__,,:.'''J~,c~ J::', .-.:r~\gL"..: J. ,~~~~, cc: i ~'!!lI~'lI'I~
1 Mohlllzation 1 LS $20 000.00 $20 000.00 SQ/5O
2 Damollllon
3 Claar and Grub 1 LS $5 200.00 $5.200.00 5llI5D
4 Ram""" H:. Pavement 15500 SF S2.50 $45 2SO.00 RMC
5 Remove Concrate Pawmant 9500 SF $2.00 $19000.00 RMC
5 Remove Concrate Curb 450 LF S5.00 S2 250.00 RMC
7 Ram""" Wood Bollards 1 LS $5 000.00 $5 000.00 RMC
8 Remove Wood Sian 1 EA $500.00 $500.00 RMC
9 . Salv80e Slans and Trash RaoeDlacle. 1 LS $1 000.00 Sl 000.00 RMC
10 Ramova Streat Llaht and Power Linea 8 EA 51 000.00 55 000.00 RMC
11 Remova Wood Wall 1 LS $150.00 $lSO.00 PROPIiO
12 Ram""" Tree 15 EA $SOO.OO $7 SOO.OO RMC
13 Ram""" Blcvcla Racks 1 LS $60.00 550.00 RMC
14 Ramave Concrate Barrier 1 EA SSO.OO S50.00 RMC
15 Ramova Chain Link Fenca. and Gete 225 LF $5.00 Sl 125.00 RMC
15 Remove Black Wall 1 LS 5200.00 $200.00 PROPIiO
17 Ram""" Shower. Cut and Caa Suoolv Line 1 LS $250.00 S250.00 PROPIiO
18 Adlust UUIRles ID Grade 1 LS $2,SOO.OO $2 500.00 RMC
19 Salvaaa Wood Wlndsurfina Rack 1 LS $250.00 $250.00 PROPIiO
20 Salvaoe Solar Powered Pay Station 1 EA !USO.OO $450.00 RMC
21 Subtotal nemolltlon $97,725.00
22 Construction
23 Concrete Curb and Guller 2300 LF 0.00 $46 000.00 RMC
24 . AsDhalt Slurrv Saal 34 ELT $350.00 $11900.00 RMC
25 Concrete Sidewalk - Natural Color 5120 SF 55.00 $25 500.00 RMC
25 Concrete Sidewalk -Inleoral Color - Sandblast Finish 12500 SF $5.50 $81 250.00 PROPIiO
27 5" Conaete Ribbon Curb 1300 LF 512.00 $15 SOD.OO RMC
28 5" Concrete Mow Curb 565 LF $10.00 $5 5SO.00 RMC
29 6" Concrete Curb 45 LF $15.00 $675.00 RMC
30 Pedestrian Ramn 3 EA $800.00 $2 400.00 RMC
31 Cast-In-Placa Concrete Seat Walls 515 LF 5100.00 $51 500.00 PROPIiO
32 StriDlno and Slanaoe 1 LS $5 000.00 $5 000.00 RMC
33 5' Concrete Wheel SIDn 97 EA $200.00 5 19400.00 RMC
34 LlohUno and ElaclrfcaJ 1 LS 7 000.00 S 57 000.00 RMC
35 Praca.t Concrete Bench 3 EA $1 SOO.OO !U 500.00 PROPIiO
35 Precast COncrate Trash Receotecle 9 EA $1 200.00 $10,500.00 PROPIiO
37 Precast Concrete Picnic Table 4 EA $1 500.00 $5.000.00 PROPIiO
38 Precast Concrete Ra""cllnn Recantacla 3 EA 51 000.00 $3 000.00 PROPIiO
39 Precast Concrete Bollard 1 EA $700.00 $700.00 RMC
40 Ra-lnst.11 Wood Wlndsurfino Rack 1 EA $300.00 S300.00 PROPIiO
41 D~nklno Fountain 2 EA 52000.00 $4 000.00 PROPIiO
42 Outdoor Shower and Drain 1 $3 500.00 $3 SOO.OO PROPIiO
43 Stona Kiosk 2 EA $8 500.00 $17000.00 PROPIiO
e
PLANNJNI3 . DESIGlN . CDNSTRUCTleN
14725 Alton Parkway, Irvine, CA 92818-2D27. P.O. Box 57D57,ll'YIne, CA 9281Q..7057. 949.472.3506. FAX 949.472.8373
OtrIceIIDCBtIId thraughout CIIOfomIa, Arfzona &. Nevma . www RtlF com
e
RIVER'S END STAGING AREA ENHANCEMENT PLAN
City of Seal Beach
OPiNION OF PROBABLE CONSTRUCTION COSTS
Prepared Septemher 12, 2005
Prepared based on the 1st Submillal ConstrucUon Documenlll dallld August 31, 2005
RBF Consulting
IN.: 10..103934.001
44 Stone Enlrv Monument 1 EA . $8 500.00 $8 500.00 RMC
45 CMU Sol~ Face Block Well 500 LF $60.00 ~30 000.00 RMC
46 Tubular Stasi Rolllno Gale 1 LS S10 000.00 $10000.00 RMC
47 Blevcle Rack ~ 1 EA $2 BOO.OO $2 800.00 PROP 50
48 Re-Instan Solar Powerad Parklno Machine 1 EA $1 200.00 $1 200.00 RMC
49 Subtotal Construction $424,275.00
50 Landscape
51 Im"ort Cleos A Toosoll 427 c:y $28.00 S11 956.00 5/lI5O
52 Soli oreoaratlon fine "radln". and fertmzer 52 000 SF $0.45 S23 400.00 5/lI5O
53 24'1 Box tree 49 EA $270.00 $13 230.00 PROP 50
54 5 Gallon shrub 1196 EA S2O.00 S23 920.00 PROP 50
55 1 Gallon shruh 338 EA $8.00 $2 704.00 PROP 50
55 Turf 22100 SF $0.65 ~14 365.00 RMC
57 Root cantrol barrler 1105 LF 17.50 $8 287.50 PROP 50
58 Waler QualllY Sum" Drain 19 EA $75.00 S1 425.00 RMC
59 Bark Mulch IT Thlck\ 29 900 SF $0.50 $14950.00 PROP 50
60 90-Dav "'ant estobllshmant celled 1 LS $9 000.00 $9.000.00 5/lI5O
61 Subtotal Landscape $123,237.60
62 IrrfllaUon
83 Completo irrigaSon system Installed, Including all water 52,000 SF $2.00 $104,000.00
mela.., backflaw p.......nla... canballe.., valves, equlpmen~
Ilolno. sleevlnn and trenchln". 5/lI5O
64 Subtotal liTigation $104,000.00
65
66 Subtotal $769,237.60
67 20% Contingency $153,647.60 5Ql60
68 estimated Total Bid $923,086.00
Since the LANDSCAPE ARCHITECT hu no contrd 0118I' the cost of labor, mBleJfsl., IIqulplnl!lnt or ..rvIcu fuml.hed by otherl or over the Cantractof(.)' method
of dBtermlnlng pnCM, or over the compBt/tfvB bidding or msrk8t condition., ill Opinion of PrabBble Canllruclfon COlt provided herein are to be mad. on the bul.
of ftI explllrlencelnd qUlr.fIc8lIonl and represenlllltl best Judgment.. an experienced and qualllled prafullonBlLANDSCAPE ARCHITECT. ramalar wfth the
construction Indusby, but the LANDSCAPE ARCHITECT cannot and dCl!lI nat IilUll"llntee thBl: PfOPDI8I., bkI. or actull! ProJect or ConItrucUon Coat will not vary
from Itl Opinion of Problbls Conatrucllon Coil If pr10rta thll Bldcing or NIIgotf8llng Phu., OWNER Vlishlll gl'88t8r ....u.nee uta ProjllCt Call, It Ihlllsmploy
an Indsp&ndent cost esllmllGr.
HjpdItI\10103934\Ac1mln\C~1stSllb_811pl1z.o&..FUNDING SOURCE.JdI
e
PLANNINtI . DEBIIaN . CONSTRUCTleN
14725 Alton Parkway, Irvine, CA 92818-2027. P.O. Box 57057, Irvine, CA 92819-7067.948.472.3505. FAX 949.472.8373
orne... located throughout CllifomII, Artzana & NeVllda . WIWoI RBF com
e
e
e
San Gabriel River Parkway Trail Enhancement (RMC3573)
Exhibit C: Monitoring and Assessment
The City of Seal Beach is a local government municipality In Orange County and Is Immediately adjacent
to the San Gabriel River. In order to evaluate the success of work Seal Beach on the San Gabriel River
Trail Enhancement grant program, the following monitoring and assessment plan has been drafted.
1) The City of Seal Beach will provide the State of Califomia Rivers and Mountains
Conservancy with a copy of all documents for review and approval.
2} The City of Seal Beach will provide the RMC with quarterly project reports outlining the
progress that has been made towards completion of project goals.
3) A final report will be compiled including pe~nent design, deliverables, quarterly reports,
4) The aMC will be Invited to participate In 'any outreach, advisory and/or stakeholders groups
formed for this project.