A RESOLUTION OF THE CITY COUIfCIL OF TIlE CITY
OF SEAL BEACH DECLARIIfG WORK TO BE COMPLETED
AS TO PLANS AND SPECIFICATIONS FOR PROJECT
301-2 - COBSTRUCTION OF STREET IMPROVJiro:RTS
AND PARKING LOT AT TIlE AVALON DRIVE ENTRANCE
TO GUM GROVE PARK - IN ACCORDANCE WITH CONTRACT
EIfTERED INTO BETWEEN SULLY-MILLER CONTRACTING
CO. AND CITY OF SEAL BEACH.
The City Council of the Ci~ of Seal Beach does hereby resolve:
WHEREAS, on the 9th day of March, 1972, the City of Seal Beach had entered
into a contract with Sully-Miller Contracting Co. for Project 301-2, Construction
of street improvements and parking lot at the Avalon Drive entrance to Gum Grove
Park, in the City of Seal Beach i and
WHEREAS, the City Engineer has submitted his approval of the final quantities
and cost figures;
NOW, THEREFORE. the Ci~ Council of the City of 'Seal Beach does resolve as
follows:
Section 1. That the work required to be perforined by said contractor has
been completed.
1
Section 2. That the total cost of said work is in the llID.ount of $5,879.50.
Section 3. That the work is hereby accepted and approved.
Section 4. It is further ordered that a "Notice of Completion" be filed,
on behalf of the City, in the office of the County Recorder of the County of
Orange within ten days of the date of this resolution.
PASSED, APPROVED AND ADOPrED by thel1.C C~cil of the City of Seal BEach
at a meeting held on the ~::t..I day of _d:" / , 1972, by the
following vote: '
, AYES: councilmen.d~ 4-t6"-'~,d..-xj~ -'d~ . j L~.ID-q, ~;:IL
NOES: Councilmen 77~ J
ABSENT: Councilmen ~~~
1
." .-i......... .....
...:-'._ '-.r
. .. - ......... ~ r.:k.
"".- ......".... ...... ",/'.
',....""'""... ~..",,..
A~:~""'~ ~ .. ~:-
...1'- '...;;
. ...:",
~ :......,.
:~
M~~
Mstor .
r