A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF SEAL BEACH DECLARING WORK TO BE COMPLETED
, AS TO PLANS AND SPECIFICATIONS FOR PROJECT 102 -
LAMPSON AVENUE IMPROVEMENTS, LOS ALAMITOS BOULEVARD
TO 10,100 FEET EAST OF LOS ALAMITOS BOULEVARD -
IN ACCORDANCE WITH CONTRACT ENTERED INTO BETWEEN
SILVERI & RUIZ CONSTRUCTION CO. AND CITY OF
SEAL BEACH.
, .
"
"
, I
'.~ .
The City Council of the City of Seal Beach does hereby resolve:
WHEREAS, on~the 24th day of September, 1968, the City of Seal Beach had
entered into a contract with Silveri & Ruiz Construction Co. for the construction
of Project 102, Lampson Avenue Improvements, Los Alamitos Boulevard to 10,100
feet east of Los Alamitos Boulevard, in the City of Seal Beach; and
WHEREAS, the City Engineer has submitted his approval of the final quantities ..,;
and cost figures;
NOW, THEREFORE, the City Council of the City of Seal Beach does resolve as
follows:
Section l. That the work required to be performed by said contractor has
been completed.
'. .
,
Section 2. That the total cost of said work is in the amount of $ll3,73l.l9.
Section 3. That the work is hereby accepted and approved.
"
't."'
Section 4. It is further ordered that a "Notice of Completion" be filed,
on behalf of the City, in the office of the County Recorder of the County of
Orange within ten days of the date of this resolution.
:
PASSED, APPROVED AND ADOPTED by th~ty Council of the City of Seal Beach
at a meeting held on the t- day of ~/T~UM y-- 196!1, by the following vote:,
AYES: Councilmen ~~ /O/l'~:' <-dj~./.~ _~_
;' ,
I,
"
"
.....:.
NOES: Councilmen
"
ABSENT: Councilmen
ATTEST:
~d1/JcaJ~
Clerk
, '
,
,
..... .. -....-,~' f
.... .'
.... ...;:' ,
"
<
-
I
I
.'
'.
.'
"
Resolution Number
:
:
'-. 'i
January 2, 1969
MEMORANDUM
To: Honorable City Council, c/o Lee Risner, City Manager
From: John R. Stratford, City Engineer
Subject: Progress Payment, Project l02, Lampson Avenue Improvements. Los Alamitos
Blvd. to 10.100 feet east of Los Alamitos Blvd.
In accordance with the Plans and Specifications of the subject project, Silveri
and Ruiz Construction Co. has completed said project. All quantities have been
verified in the field. See attached copy of contractor's invoice.
It is recommended that the City Council take the following action:
1. By resolution. determine that the work has been completed in accordance with
the contract documents and declare the work to be accepted.
2. By resolution. determine that the total amount of the work performed under
this contract is in the sum of $l13.73l.l9.
3. Within ten (10) days from the date of acceptance, file a Notice of Completion
with the Orange County Recorder.
4. Upon expiration of thirty-five (35) days from filing of Notice of Completion
make payment to Silveri & Ruiz Construction Co. in the amount of $11,373.12.
Respectfully submitted.
.
~,-;~
~ t. " '~f"" . .
-
I
. '. '.
" ,
~
~p -
Resolution Number
January 2" 1969
MEMORANDUM
To: Honorable City Council, c/o Lee Risner
From: John R. Stratford, City Engineer
Subject: Project 102, Lampson Avenue Improvements
Subject project has been completed by our contractor, Silveri & Ruiz Construction
Co. By separate memo I have recommended our. normal final scceptance procedure.
The required completion date for this project was December 15, 1968. However,
due to some days lost to inclement weather and to sdditiona1 work authorized
by the City, the project was not completed until December 20, 1968. Because
these delays were beyond the control of the contractor, it is hereby requested
that a formal extension of time be granted, thus removing the necessity for
payment of liquidated damages.
ohn R. Stratford