AGENDA REPORT
DATE:
December 10, 2007
TO:
Honorable Mayor and City Council
THRU:
David N. Carmany, City Manager
FROM:
Vince Mastrosimone, Director of Public Works
:
SUBffiCT: SEAL BEACH MUNICIPAL PIER DECK
REHABILITATION PROJECT NO. 50217 - CALIFORNIA
COASTAL COMMISSION PERMIT APPLICATION
SUMMARY OF REQUEST:
e
City Council adopt the attached Resolution No. _ authorizing staff to submit a
permit application to the California Coastal Commission for the Pier Deck Rehabilitation
Proj ect.
BACKGROUND:
The Seal Beach Municipal Pier was constructed in 1906; it is approximately 1800-feet
long consisting mostly of poly-wrapped timber piles, timber support members and a
timber deck. The Pier was severely damaged by the winter storms in 1982 and 1983 and
it was repaired to minimal working conditions. Lifeguards and Public Works' crews
regularly inspect and monitor various components of the Pier. On August 26, 2002,
Council awarded a professional services contract to Han-Padron Associates to inspect and
evaluate the timber Pier.
Inspections and testing were conducted in November 2002. The inspection included a
visual and tactile examination of all accessible components of the structure, above and
below the waterline. The report concludes that the Pier is in fair condition according to
the standards set by the American Society of Civil Engineers (ASCE) Standard Practice
Manual on Underwater Investigations. However, at that time, several elements of the
Pier were in need of repair and replacement including structuraJ components, utilities,
preservation components and aesthetic features.
e
Overall, the Pier and its deck are in fair condition and because of its timber construction,
surfaces and appearance are rough and rustic. Routine inspections are performed by the
Public Works Department to identify components needing repair, adjustment, and
Agenda Item 0
.
preventative measures. In the past "flipping over" the boards has been a method of repair
with limited success due to the splintering/splitting of the decking. However, the historic
aged timber surface can be rough and uneven. Pedestrians are cautioned with signs at the
entrance to the Pier regarding the uneven surfaces.
A study was conducted by Moffatt & Nichol in May 2006 to study alternatives for
rehabilitation of the decking on the Pier. A life cycle cost analysis was prepared along with
other factors including aesthetics, safety, comfort, and fire resistance and the
recommendation of the report was to replace the decking on the Pier with an imported
"Greenheart" hardwood. The hardwood is a higher costing alternative than replacing the
decking with the existing Douglas fir wood. The life expectancy of the hardwood is 25
years as opposed to 15 years of the Douglas fir wood. By choosing the hardwood the
benefit would be over 10 years longer life.
e
Due to the length of the pier and the associated cost, this project was divided into 4 phases,
each phase totaling approximately one-quarter the length of the pier. Currently, phase one
is complete, phase two's design is substantially complete, phase three design has begun and
phase four is on hold for future funding. Upon the successful execution of the contract
documents, the contractor will have several months to procure the Greenheart Hardwood for
phases two and three, but only 8 to 12 weeks to construct the improvements. There are no
daytime Pier closures scheduled with this project. The contractor will be working at night
and reopen the Pier every morning.
The City constructed Phase One of the subject project without a Coastal Commission
permit citing Section 3061O(d) of the Coastal Act which renders certain types of repairs
and maintenance activities exempt from permit requirements. However, the Commission
does not view pier deck replacement projects as meeting all criteria necessary for
exemption status under this Section. Newer guidelines established in 1978 that the City
further referenced are not applicable as well. Thusly, the City received a notice of
violation from the Coastal Commission that can be cleared by applying for a Coastal
Commission permit. Staff has prepared the necessary (attached) permit application to
cover Phases 1-4 of the Pier Deck Rehabilitation Project. The approval process to obtain
this permit is approximately 4-6 months through the Coastal Commission.
FISCAL IMPACT:
There is no fiscal impact to the City to apply for the permit from the California Coastal
Commission.
RECOMMENDATION:
e
It is' recommended that the City Council adopt the attached Resolution No.
authorizing staff to submit a permit application to the California Coastal Commission for
the Pier Deck Rehabilitation Project.
.
Prepared By:
Reviewed By:
~At.E
Assistant City Engineer
,
D . . Spitz, P.E.
ssociate Engineer
.,
NOTED AND APPROVED:
~~
DavidN. carmanyD
City Manager
e
Attachments: Coastal Commission Permit Application, additional exhibits available for
viewing.
e
RESOLUTION NUMBER
e
A RESOLUTION OF THE CITY COUNCn. OF THE CITY OF
SEAL BEACH AUTHORIZING THE DIRECTOR OF PUBLIC
WORKS FOR THE SUBMITTAL OF AN APPLICATION TO THE
CALIFORNIA COASTAL COMMISSION FOR THE
REHABll.lTATION OF THE DECKING ON THE SEAL BEACH
MUNICIPAL PIER
WHEREAS, The City of Seal Beach wishes to rehabilitate the decking on the Seal
Beach Municipal pier: and
WHEREAS, Section 13252 of Title 14 of the California Code of Regulations requires a
permit application to the Califomia Coastal Commission to perform the
required construction acbvities; and
WHEREAS, the City has prepared an application to the Califomia Coastal Commission
for a permit to rehabilitate the decking on the Seal Beach Municipal Pier.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF SEAL BEACH DOES
HEREBY RESOLVE, DECLARE, DETERMINE AND ORDER AS FOLLOWS:
Section 1. Authorizes the submittal of an application to the California Coastal
Commission for the Seal Beach Municipal Pier Deck Rehabilitation Project.
e
Section 2. The Director of Public Works or hislher designee, of the City of Seal Beach is
hereby authorized and empowered to execute in the name of the City of Seal Beach all
necessary applications, contracts, agreements, amendments, and payment requests hereto
for the purposes of securing a permit with the Califomia Coastal Commission for the Seal
Beach Municipal Pier Deck Rehabilitation Project.
Section 3. The City will comply with all permit requirements for the development of the
project.
PASSED, APPROVED and ADOPTED by the City Council of the City of Seal Beach at
a regular meeting held on the 10th day of December. 2007 by the following vote:
AYES: Councilmember
NOES: Councilmember
ABSENT: Councilmember
ABSTAIN: Councilmember
Mayor
ATTEST:
City Clerk
e
Resolution Number llXllX
.
STATEOFCALlFORNIA }
COUNTY OF ORANGE } SS
CITY OF SEAL BEACH }
I, Linda Devine, City Clerk of the City of Seal Beach, California, do hereby certify that
the foregoing resolution is the original copy of Resolution Number _ on file in the
oftice of the City Clerk, passed, approved, and adopted by the City Council of the City of
Seal Beach at a regular meeting thereof held on the lOth day of December. 2007.
<;ity Clerk
e
e
e
e
e
Attachment
~
California Coastal Commission
Permit Application
(Detailed application on file for viewing
in the Office of the City Clerk)
STATE OF CALIFORNIA-THE RESOURCES AGENCY
ARNOLOSCHWARZENEGGER.GOVERNOR
_CALIFORNIA COASTAL COMMISSION
~OUTH COAST DISTRICT OFFICE
200 OCEAN GATE. 10TH FLOOR
LONG 8EACH. CA 90802-4418
VOICE AND TOO (582) 590-5071
FAX (582) 590.5084
e
e
PERMIT APPLICATION INSTRUCTIONS
A completed application includes the ApPLICATION FOR COASTAL DEVELOPMENT PERMIT, the appendices to
the application, and Required Attachments.
· Please answer all questions. If a question is not applicable to your project, indicate 'N.A.'
· Refer to pages 8 - 9 of the ApPLICATION for a list of Required Attachmimts.
· Incomplete applications will not be accepted for filing.
· All exhibits must be legible.
The following checklist is provided for the convenience of applicants in gathering necessary application
materials; it is not a complete statement of filing requirements.
Page Item
7 1
7 2
7,8 4,5
8 6
8 7,11
8 9
8 10
8 11
Appendix B
Appendix D
Appendix E
IZI Proof of applicant's interest in the property. ................................................................
Assessor's parcel map(s) showing the proposed development site and all adjacent
IZI properties within 100 feet of the property boundary. ...................................................
Stamped envelopes (no postage meter please) addressed to neighboring property
IZI owners and occupants and other interested parties and a list of the same. ...............
IZI Vicinity map. ..................... ..................................................,............ ...........................
IZI Two sets of project plan(s), site plan(s), and applicable other plans.. (All plans must
be stamped and signed 'Approved in Concepf.)
Copy of any environmental documents (DRAFT AND FINAL EIRs, EISs, NEGATIVE
IZI DEClARATION) if prepared for the project and any comments and responses. ............
Verification of all other permits, permissions or approvals applied for or granted by
IZI public agencies. ............. ................................ .................................. .......... .................
o Copy of geology or soils report (if necessary). ............................................................
IZI Local approval of the project. ......................................................................................
IZI Has the Notice of Pending Permit been posted in a conspicuous place? ...................
IZI FiI,~ng fee. .......................,.................................................,..................................,.....
Have you and the agent (if appropriate) signed the application at the appropriate lines on pages 9,
IZI 10, and 131
Revised 9/18/07
APPLICATION FOR COASTAL DEVELOPMENT PERMIT
. SECTION I. APPLICANT
1. Name, mailing address, and telephone number of all applicants.
City of Seal Beach, Vince Mastrosimone, Director of Public Works
211 8lh Street
Seal Beach, CA 90740
(562) 431-2527
(Area codak/aytime phone numbelj
Note: All applicants for the development must complete Appendix A, the declaration of campaign
contributions, :
2. Name, mailing address and telephone number of applicant's representatives, if any. Please include
all representatives who will communicate on behalf of the applicant or the applicanfs business
partners, for compensation, with the Commission or the staff. (It is the applicant's responsibility to
update this list, as appropriate, including after the application is accepted for filing. Failure to provide
this information prior to communication with the Commission or staff may result in denial of the permit
or criminal penalties.)
N/A
e
(Area codak/ay/lme phone numbSlj
SECTION II. PROPOSED DEVELOPMENT
Please answer all questions. Where questions do not apply to your project (for instance, project height for a
land division), indicate Not Applicable or N.A,
1.
Project Location. Include street address, city, and/or county. If there is no street address, include
other description such as nearest cross streets.
Main Street and Ocean Avenue
street
Orange County
county
N/A
number
Seal Beach
city
Assessor's Parcel Number(s} (obtainable from tax hill or County Assessor):
199-105-03
e
FOR OI"FICE USE ONLY
ApPLICATION NUMBER
RECEIVED
FILED
FEE
DATE PAID
.
e
e
2. Describe the proposed development in detail. Include secondary improvements such as grading, septic
tanks, water wells, roads, driveways, outbuildings, fences, etc. (Attach additional sheets as necessary.)
The Seal Beach Municipal Pier originally was constructed in 1906, is approximately 1800-feetlong
consisting mostly of poly-wrapped limber piles, timber support members and a timber deck. The Pier
was severely damaged by the winter storms in 1982/1983 and it was partially rebuilt after the
damage. Ufeguards and Public Works' crews have regularly inspected and monitored various
components of the Pier. On August 26, 2002, Council awarded a professional services contract to
Han-Padron Associates to inspect and evaluate the timber Pier.
s
Inspections and testing were conducted in October and November of 2002. The inspection included a
visual and tactile examination of all accessible components of the structure, above and below the
waterline. The report concludes that the Pier is in fair condition according to the standards set by the
American Society of Civil Engineers (ASCE) Standard Practice Manual on Underwater Investigations.
However, at that lime several elements of the Pier were in need of repair and replacement including
structural components, utilities, preservation components and aesthetic features.
- Continued on separate sheet-
a. If multi-familv residential, state
,_ - ,---; ,-- --'-"_Nu~b~r~f~nils:--,-; ~;:";_' :,-",: ,_~; ';:.'Nu~~erofil~rQbm~-~(Unlr '-- ,-:":TYPe~!o~~~t'ill:,'."-
" '. - -" - -, -,",. '"' . . -, - -. - " - - - - ; - - - -. ~
. -, -- ___ :__" .',>. _ -:,__:_", (bolh-~!<I~tingand_pll!llosed):_, -,- -'-__ -pro~sE!d:_::,,--
... 'i-t_ ,,_"U -....' __ _" ',__-' = . _"_ . u _ , - -- - __...'
Exis1lng unils Proposed new unils Netnumber of un~ on Drental
comple1lon of pltlJocl
N/A
N/A
N/A
Dcondominium
Dstock cooperative
Dlime share
Dother
N/A
b. If land division or lot line adjustment, indicate:
'o. ro,: -. _ - -." - -~ ,,- -- .'ow__ 'l'---~ -. '.- - "_ _ ... - ,- - __ . , . - r -. ..-. -,
_: -- --. "~ ; -:i':__N,uin!le[Qfrots" ~. -,';" ',;' ,:~ ~';--'~' - '-~ _$i?e;rjf!oJs fsl ~e CitiiiterUi!!rfK?Bfe Ifetorgross. ilcriliiijeF-
- .... -.... - -__ '_ _, _ _ ' _ = - _ i '_.. _-: i - -~ : _ = _:..... _.! _ OR _ _ - - __ _ -. - -;~ . -, - - -. - -;; .
ExIsIIng Lots Proposed new lots Net numberof1ols on Existing Proposed
comnleUon of nm....
~ ~ ~ ~ ~
2
Revised 9/18107
e
e
e
3.
4.
$1,200,000
+26 MLLW
N/A
N/A
N/A
Estimated cost of development (not including cost of land)
Project height: Maximum height of structure (ft.)
. above existing (natural) grade ................................
· above finished grade ............................................
. as measured from centerline of frontage road ......
5. Total number of floors in structure, including
subterranean floors, lofts, and mezzanines..................... N/A
6. Gross floor area excluding parking (sq.ft.)..................... N/A
Gross floor area including covered parking and
accessory buildings (sq.ft.)............................................ N/A
7. Lot area (within property lines) (sq.ft. or acre)..................... N/A
-.-'i_ot~rage~" i _ Exisiing(sq.ttora;;;) :.N~~fr!Poseri{;q.ff:orfiP~/ -:_ Tot~1(sqJ[-o~~;_":_
':.. --. . - -" - -_." . ",: ",- - , . . ,- -", -.- -. -, -
Building
Paved area
Landscaped area
Unimproved area
-, , =,"....... _ ' : .. ". " -;: ~ . 'n - -"' _ - .'-,
- ; - - -';,'- - :; ;~:,: G@ni{To~ar(~~ci_~~_eq~ai lol'~i9i'is-~~6WiJ il! ~t a";'"reJ"'__
8. Is any grading proposed? ............................................................................0 Yes
IZI No
-" , '"' ,. ' , -- - - n.- ._. -; -- i: - ~
Ifies;-comkletfs'tIi'--_~I/~~invf ~~ ' ,- .'."a, . 'L ~. '~:' - _ .",: -- ,- -- - ~ .
, - c, - - -- ,n -,
-- -. - .. " --
a) Amount of cut cu. yds. d) Maximum height of ft.
cut slope
b) Amount of fill cu. yds. e) Maximum height of ft.
fill slope
c) Amount of import or cu. yds. n Location of borrow
export (circle which) or disposal site
Grading, drainage, and erosion control plans must be included with this application, if applicable. In certain areas, an engineering
geology report must also be included. See page 7, items # 7 and 11. '
Please list any geologic or other technical reports of which you are aware that apply to this property:
Pier Deck Study 2006
3
Revised 9/1 B/07
. 9. Par1<ing:
__ - _ .__-:..... ~ ._" - - ~ ... - ."." n. _ _" _". ,. ".r." "
Numbfrofi1a~n.Rsp~pesX'~fd;ptite_~t~er,~~~d~irtP(CQlJle~Ctr ,-.:-: -~ _- ,_-_,:,,~- -, ,- __' "-;i-.: ->;:, to.
- o. _ _. _._ - I!'_ :. _ '.' - __ _=_ -._"
Existing Spaces Proposed new spaces Net number of spaces on completion of project
o
o
o
Is any existing parking being removed? ........................................................ 181 Yes 0 No
Ifyes,howJl1anyspaces? ~ size 6000 gf fr A~
Is tandem par1<ing existing andlor pro~sed? ............................................... 0 Yes 181 No
If yes, how many tandem sets? size
10 Are utility extensions for the following needed to serve the project? (Please check yes or no)
a) water b) gas c) sewer d) electric e) telephone
0 0 0 0 0
Yes Yes Yes Yes Yes
e 181 No 181 No 181 No 181 No 181 No
Will electric or telephone extensions be above-ground? .............................. 0 Yes 181 No
11. Does project include removal of trees or other vegetation? ......................... 0 Yes 181 No
If yes, indicate number, type and size of trees
or type and area of other vegetation
SECTION III, ADDITIONAL INFORMATION
The relationship of the development to the applicable i~ems below must be explained fully. Attach additional
sheets if necessary.
1. Present use of property.
a. Are there existing structures on the property? .......................................
181 Yes 0 No
"~ye~_ ~~"&cri~~'-" ;~r ~':: '_~:-:f-::~. _ ~~: ~~.~ ~-: ',:: ~ -> ~ L~_~:~ ~:~__{;~~; ~:~~~ :~.-~(; , ~i~: ~;~~,~~-~~~;, - ,: ~~: co_ ;~ "'~ ~~:_:~ ': - i: '-.'~, ~: -~. ,~ _'~'
,End of pier contains restaurant structure leased by Ruby's. Additionally, vacant building sits
next to Ruby's. At approximately 900 feet is a lifeguard tower. At approximately 1200 feet is
a boat launch attached to the side of the pier.
e
4
Revised 9/18/07
.
e
e
b. Will any existing structures be demolished? ..........................................
Will any existing structures be removed? ..............................................
DYes
DYes
IZI No
IZI No
- . - - - _ -= ... :.... '!: "- _ . -w.... -. : - -: ", _ -' _ _......;... _"';;:" _ _ 0.:: -- _ , _ ~ :- - ... -
If~s !9 ,eithe;q~Stion~ despiilie th~ type:o[d~velo'plpenl to 6e C!iimoli~.eailirerrrO.V9d.: iri~ii~ing me. ~lOcl!ltio~:~. if
a~~fiF-~p~; . _:.;_.~, ;m. ; ~ ,~~' _ - ,~~~~-.: =~', :-~ :."' - _--=;_ ~ .-: ~,-~~:.... -_;:~,~: _:_~-~ _".., :--_-- --:-. ,(~,: -~ :
N/A
,
2. Is the proposed development to be govemed by any Development
Agreement?................................................................................................. ..
3. Has any application for development on this site including any subdivision
been submitted previously to the Califomia Coastal Zone Conservation
Commission or the Coastal Commission? ....................................................
If yes, state previous application number(s)
4. a. Is the development between the first public road and the sea (including
lagoons, bays, and other bodies of water connected to the sea) ...........
b. If yes, is public access to the shoreline and along the coast currently
available on the site or near the site? ....................................................
DYes IZI No
DYes IZI No
IZI Yes 0 No
IZI Yes 0 No
, _ r c' --_~. ''':" _. . "~- ,- _ : _ , " ,i - .;. - , -. -. _ :0-';' _ : - -, '. " - : - ': '_. ~ ."'':
IfWS. in.dicat~tfie:tOcptiorr anfi n!ltuie.ofth~ ~~s;' inc(udin!iflt.e.!ii~i!ih~f19iii ~.Pl'9j~ct ~it.e, ifappllcabfe.": ..;:...
_ '... ,_ _ _- _ ... - . -: _ ... .' , r'". -, M. ,~_ _ _ _R : :f..' _ _ '" , c' - , -
The Seal Beach Pier extends from the beach seaward. Beach access will not be impacted as
construction will take place on the pier.
c. Will the project have an effect on public access to and along the
shoreline, either directly or indirectly (e.g., removing parking used for
access to the beach)? ............................................................................
IZI Yes 0 No
~ ..... _ .', _.-'..~:" . '::-~ .,,:~~....r:; R'"::' _ ,'.' ","' ,__:r. _~-..: '.- - ;;_= :r-::" -;-,:- -~ ".. _
If yes, describetlie{lffect . :.'. ., .v, . " "' .. ,.. ..~ n .,n" . ,.::';. '.."'.
. .~ -- , : 1::- _....::. - .... ii .-- \ .. ' .:... .- .';-.'!: . ...i" . ~ ;.;:" - .. -:f - _ , ::" _ __..~. " .-.-
; ..- .- ,;
." '
.., -- -
. ,.
.During construction the project will occupy approximately 6000 SF of parking area for
equipment staging. Additionally the pier will be closed at night for construction.
5
Revised 9/1 B/07
e
5. Does the development involve diking, filling, draining, dredging or placing structures in open coastal
waters, wetlands, estuaries, or lakes? (Please check yes or no)
a) diking
D
Yes
IZI No
c) dredging
DYes
b) filling
D
Yes
IZI No
d) placement of structures
DYes
IZI No
IZI No
Amount of material to be dredged or filled (indicate which) NIA
Location of dredged material disposal site N/A
Has a U.S. Army Corps of Engineers' permit been applied for? ...................
6. Will the development extend onto or adjoin any beach, tidelands,
submerged lands or public trust lands? ........................................................
cu. yds
For projects on State-Qwned lands, additional information may be required as set forth in Section IV,
paragraph 10.
Will the development protect existing lower-cost visitor and recreational
facilities? ......................................................................................................
7.
e
Will the development proVide public or private recreational opportunities? ..
DYes IZI No
IZI Yes D No
181 Yes
181 Yes
o No
o No
~: -'~r..': :: ~ _..- _;-~"_' ,-~ ~ ~~;- ," ",~- .' :--r=, ' . - _:;~-: :-. --" -;:-,-~: , : -, ': -= ~~~
Ifye~ expialn. - _ , ,_ - _ _ -. _ "' _ ," _ _, -' _ _" , , _ _ _.. _ ,- - ,
- . ' ," .~' : - -. . - "_ ' :'~ - -. -- : ,,_ ' '. ,,,,.., -," '" , ,- ~. " "'M - ,- -; ._' _" _ '
The project aims to restore the natural function of the pier decking because the current
surface is in need of repair due to its rough and uneven surfaces. Many pedestrians
including those walking and fishing will benefit from this new surface.
8. Will the proposed development convert land currently or previously used for
agriculture to another use? ........................................................................... DYes 181 No
If yes, how many acres will be converted?
9. Is the proposed development in or near.
a. Sensitive habitat areas (Biological survey may be required) ...........................
b. Areas of state or federally listed rare, threatened, or endangered
species ..................................................................................................
c. 100-year floodplain (Hydrologic mapping may be required) .............................
d. Park or recreation area ..........................................................................
e 10. Is the proposed development visible from:
a. State Highway 1 or other scenic route ...................................................
6
Revised 9/18/07
DYes 181 No
0, Yes 181 No
181 Yes 0 No
181 Yes 0 No
DYes 181 No
.
b. Park, beach, or recreation area .............................................................
c. Harbor area .............................................................. .............................
11. Does the site contain any: (If yes 10 any of the following, please explain on an attached sheet)
a. Historic resources .................................................................................
~ Yes
~ Yes
o No
o No
DYes
DYes
DYes
~ No
~ No
~ No
b. Archaeological resources ......................................................................
c. Paleo~tological resources ......................................................................
12. Where a stream or spring is to be diverted, provide the following information:
Estimated streamflow or spring yield (gpm) N/A
If well is to be used, existing yield (gpm) N/A
If water source is on adjacent property, attach Division of Water Rights approval and property owner's
approval.
SECTION IV, REQUIRED ATIACHMENTS
e The following items must be submitted with this form as part of the application.
1. Proof of the applicant's legal interest in the property. A copy of any of the following will be
acceptable: current tax bill, recorded deed, lease, easement, or current policy of title insurance.
Preliminary title reports will not be accepted for this purpose. Documentation reflecting intent to
purchase such as a signed Offer to Purchase alqng with a receipt of deposit or signed final escrow
document is also acceptable, but in such a case, issuance of the permit may be contingent on
submission of evidence satisfactory to the Executive Director that the sale has been completed.
The identity of all persons or entities which have an ownership interest in the property superior to that
of the applicant must be provided.
2. Assessor's parcel map(s) showing the page number, the applicant's property, and all other
properties within 100 feet (excluding roads) of the property lines of the project site. (Available from
the County Assessor.)
3. Copies of required local approvals for the proposed project, including zoning variances, use
permits, etc., as noted on Local Agency Review Form, Appendix B. Appendix B must be completed
and signed by the local govemment in whose jurisdiction the project site is located.
4. Stamped envelopes addressed to each property owner and occupant of property situated
within 100 feet of the property lines of the project site (excluding roads), along with a list
containing the names, addresses and assessor's parcel numbers of same. The envelopes must
be plain (i.e., no return address), and regular business size (9 1/2' x 4 1/8'). Include first class
postage on each one. Metered postage Is not acceptable. Use Appendix C, attached, for the listing
of names and addresses. (A1temate notice provisions may be employed at the discretion of the
District Director under extraordinary circumstances.)
e
7
Revised 9/18/07
.
e
e
5. Stamped, addressed envelopes (no metered postage, please) and a list of names and
addresses of all other parties known to the applicant to be interested in the proposed
development (such as persons expressing interest at a local govemment hearing, etc.).
6. A vicinity or location map (copy of Thomas Bros. or other road map or USGS quad map) with the
project site clearly marked.
7. Copy(s) of plans drawn to scale, including (as applicable):
· site plans
· floor plans
. building elevations
. grading, drainage, and erosion control plans
· landscape plans
· septic system plans
Trees to be removed must be marked on the site plan. In addition, a reduced site plan, 8112" x 11" in
size, must be submitted. Reduced copies of complete project plans will be required for large projects.
NOTE: See Instruction page for number of sets of plans required.
8. Where septic systems are proposed, evidence of County approval or Regional Water Quality Control
Board approval. Where water wells are proposed, evidence of County review and approval.
9. A copy of any Draft or Final Negative Declaration, Environmental Impact Report (EIR) or
Environmental Impact Statement (EIS) prepared for the project. If available, comments of all
reviewing agencies and responses to comments must be included.
10. Verification of all other permits, permissions or approvals applied for or granted by public
agencies such as:
· Department of Fish and Game
· State Lands Commission
. Army Corps of Engineers
. U.S. Coast Guard
For projects such as seawalls located on or near state tidelands or public trust lands, the Coastal
Commission must have a written determination from the State Lands Commission whether the
project would encroach onto such lands and, if so, whether the State Lands Commission has
approved such encroachment. See memo to "Applicants for shorefront deve/opmenf dated
December 13, 1993. '
11. For development on a bluff face, bluff top, or in any area of high geologic risk, a comprehensive, site-
specific geology and soils report (including maps) prepared in accordance with the Coastal
Commission's Interpretive Guidelines. Copies of the guidelines are available from the District Office.
SECTION V. NOTICE TO APPLICANTS
Under Certain circumstances, additional material may be required prior to issuance of a coastal
development permit. For example, where offers of access or open space dedication are required,
8
Revised 9/1 B/07
.
e
preliminary tiUe reports, land surveys, legal descriptions, subordination agreements, and other outside
agreements will be required prior to issuance of the penni!.
In addition, the Commission may adopt or amend regulations affecting the
issuance of coastal development pennits. If you would like notice of such
proposals during the pendency of this application, if such proposals are
reasonably related to this application, indicate that desire. ...................................
~ Yes 0 No
SECTION VI, COMMUNICATION WITH COMMISSIONERS
Decisions of the Coastal Commission must be made on the basis of infonnation in the public record
available to all commissioners and the public. Pennit applicants and interested parties and their
representatives may contact individual commissioners to discuss pennit matters outside the public hearing
(an "ex parte" communication). However, the commissioner must provide a complete description of the
communication either in writing prior to the hearing or at the public hearing, to assure that such
communication does not jeopardize the fairness of the hearing or potentially result in invalidation of the
Commission's decision by a court. Any written material sent to a commissioner should also be sent to the
commission's office in San Francisco and the appropriate district office for inclusion in the public record and
distribution to other commissioners.
SECTION VII, CERTIFICATION
1. I hereby certify that I, or my authorized representative, have completed and posted or will post the
Notice of Pending Pennit card in a conspicuous place on the property within three days of
submitting the application to the Commission office.
2. I hereby certify that I have read this completed application and that, to the best of my knowledge, the
information in this application and all attached appendices and exhibits is complete and correc!. I
understand that the failure to provide any requested information or any misstatements submitted in
support of the application shall be grounds for either refusing to accept this application, for denying
the pennit, for suspending or revoking a pennit issued on the basis of such misrepresentations, or for
seeking of such further relief as may seem proper to the Commission.
3. I hereby authorize representatives of the California Coastal C~mmission to conduct site inspections
on my property. Unless arranged otherwise, these site inspections shall take place between the
hours of 8:00 A.M. and 5:00 P.M.
Signature of Authorized Agent(s) or if no agent, signature of Applicant
NOTE: IF SIGNED ABOVE BY AGENT, APPUCANT MUST SIGN BELOW.
SECTION VIII. AUTHORIZATION OF AGENT
I hereby authorize
e and to bind me in all matters concerning this application.
to act as my representative
Signature of Applicant(s)
(Only the applicant(s) may sign hem to BlJihorlz9 an agenQ
9
Revised 9/1 B/07
e
e
e
APPLICATION FOR COASTAL DEVELOPMENT PERMIT
APPENDIX A
DECLARATION OF CAMPAIGN CONTRIBUTIONS
Government Code Section 84308 prohibits any Commissioner from voting on a project if he or she has
received campaign contributions in excess of $250 within the past year from project proponents or
opponents, their agents, employees or family, or any person with a financial interest in the project.
In the event of such contributions, a Commissioner must disqualify himself or herself from voting on the
project.
Each applicant must declare below whether any such contributions have been made to any of the listed
Commissioners or Alternates (see last page).
CHECK ONE
~
The applicants, their agents, employees, family and/or any person with a financial
interest in the project have not contributed over $250 to any Commissioner(s) or
Altemate(s) within the past year.
D
The applicants, their agents, employees, family, and/or any person with a financial
interest in the project have contributed over $250 to the Commissioner(s) or
Altemate(s) listed below within the past year.
Commissioner or Alternate
Commissioner or Alternate
Commissioner or Alternate
Signatum of Applicant or Authorized Agent
Date
Please type or print your name Vince Mastrosimone
10
Revised 9/1 B/07
.
e
e
APPENDIX B
LocAL AGENCY REVIEW FORM
SECTION A (To BE COMPlETED BY APPLICANT)
Applicant Vince Mastrosimone
Project Description Replace the decking on the Seal Beach Municipal Pier with an imported
"Green heart' hardwood
Location City of Seal Beach Municipal Pier
,
Assessor's Parcel Number 199-105-03
.~EC~IQ~-B-~~~~;~~~p~.B~ ~ci~ ~~;N~~~.B~lip!N~ i~~~ci~I~~_~Aiir~N~t;~~
Zoning Designation PLU / R Public Land use / Recreation
General or Community Plan Designation "Beach"
Local Discretionary Approvals
IXI Proposed development meets all zoning requirements and needs no local permits other than building
permits.
D Proposed development needs local discretionary approvals noted below.
Needed Received
D D
D D
D D
D D
D D
D D
D D
D D
D D
D D
CEQA Status
IXI Categorically Exempt Class Section 15301, Class 1
D Negative Declaration Granted (Date)
D Environmental Impact Report Required, Final Report Certified (Date)
D Other
, .'.,~':.' .:' .__po u_-' '-: -, 'i- '-~''''''J~~''
." ". "-: - - '-"',
, -"i. , -
- .'., --
du/ac
du/ac
Design/Architectural review
Variance for
Rezone from
Tentative Subdivision/Parcel Map No.
GradinglLand Development Permit No.
Planned Residential/Commercial Development Approval
Site Plan Review
Condominium Conversion Permit
Conditional, Special, or Major Use Permit No.
Other
Item Tvoe C
Prepared for the City/County of Seal Beach
Date
Revised 9/18/07
by
TiUe Director of Development Services
11
.
e
e
Application No.
APPENDIX C
LIST OF PROPERTY OWNERS AND OCCUPANTS WITHIN 100 FEET AND THEIR ADDRESSES
(MAKE ADDITIONAL COPIES OF THIS SHEET AS NECESSARY)
APN: 199-103-01
900 Seal Way
Owner: City af Seal Beach
12
Revised 9/18/D7
e
APPENDIX D
(Permit Application)
DECLARATION OF POSTING
Prior to or at the time the application is submitted for filing, the applicant must post, at a conspicuous place, easily read by
the public and as close as possible to the site of the proposed development, notice that an application for the proposed
development has been submitted to the Commission. Such notice shall contain a general description of the nature of the
proposed development. The Commission furnishes the applicant with a standardized form to be used for such posting. If the
applicant fails to post the completed notice form and sign the Declaration of Posting, the Executive Directcir of the
Commission shall refuse to file the application. 14 Cal. Code Regs. Section 13054(d).
Please sign and date this Declaration of Posting form when the site is posted: it serves as proof of posting. It should be
returned to our office wil!1 the application.
Purs\lant to the requirements of California Administrative Code Section 13054(b), I hereby certify
that on, 12/11/07
laate at posnng) .
of Pending Permit for application to obtain a coastal development permit for the development of
Seal Beach Municipal Pier Deck Rehabilitation Project
I or my authorized representative posted the Notice
e
laescnpoon at aevelapmem)
Located at 10 Main St. Seal Beach Municipal Pier, City of Seal Beach
199-105-03
laaaress at aevelapmem or assessors partel numoerJ
The public notice was posted at Lifeguard Station at 10 Main St.
la conSpiCUOUS place, easilY seen oy me puallc ana as C1ase as posslale 10 me sne at me proposea aevelOpment)
(signature)
(data)
NOTE: Your application cannot be processed until this Declaration of Posting is signed and returned to this office.
FOR OFFICE USE ONLY
PERMIT NUMBER...................
RECEIVED ............................
DECLARATION COMPLETE......
e
....
APPENDIX E
PERMIT ApPLICATION FEE SCHEDULE
~FFECTIVE JANUARY 1, 199B, AU. PERMIT APPLICATION FEES ARE DEPOSITED IN THE COASTAL ACCESS ACCOUNT OF THE STATE COASTAL
CONSERVANCY FUND. MONIES IN THE ACCOUNT ARE AVAILABLE TO PUBLIC AGENCIES AND OTHER ORGANIZATIONS FOR THE DEVELOPMENT,
MAINTENANCE, AND OPERATION OF PUBLIC SHORELINE ACCESS FACllmES (PUBLIC REsoURCES CODE SECTION 30620(c)(2)).
e
I. RESIDENTIAL PROJECTS
A, New single-family dwellings
De minimis waiver ..........................................................................................
Administrative permit......................................................................................
Regular calendar
If 1,500 or less square feet 2...................................................................
If 1,501 to 5,000 square feet 2 ................................................................
If 5,001 or more square feet 2.................................................................
B. Additions or improvements to single-family dwellings
De minimis waiver ..........................................................................................
If handled as an amendment to a previous coastal development permit,
see Amendments (Section III.D.) below.
If not a waiver Q[ an amendment to a previous coastal development permit,
the fee is assessed according to the schedule in A. above (i.e., based on
the calendar and/or size of the addition, plus the grading fee, if applicable).
C, Multiple residential projects (including residential subdivisions,
resubdivisions and condominium conversions) 4
2-4 units.........................................................................................................
5-16 units.............................. .................................. .......................................
17-166 units........................ ............. ..............................................................
167 units or more ...........................................................................................
D. Lot line adjustment................................................".....................................
E. Divisions of land where there are single-family
residences already built and only one new lot is created.........................
F. Grading fee for residential projects
0$ 200
0$ 2001
0$ 2503
0$ 5003
0$ 1,0003
0$ 200
0$
0$
o
o $ 20,000 3
o $ 6003
6003
2,000 3
$ 120 /unifl
o $ 6003
1 Fee changes if removed from the Administrative Calendar and rescheduled on the Regular Calendar. Additional fee amount must be paid before
item is scheduled for hearing on the Regular Calendar.
e 2 Including gross internal floor space of main house, attached garage(s), covered patios, plus any detached structures intended for human
habitation (e,g., guest houses, detached bedrooms, in-law units); not including patios or decks open to the sky, detached garages, barns, art
studios, tool sheds, and other outbuildings not primarily intended for human habitation.
3 Grading fee applies; see Item F.
4 If land division' and construction of residences are proposed together, ~% fee is based solely upon the construction of residences.
.
For residential projects that are not scheduled on the
administrative calendar, if more than 75 cubic yards of
grading is proposed, an additional fee applies................................................ 0 $ 200
II. OFFICE, COMMERCIAL, CONVENTION, INDUSTRIAL
A. New structures
Up to and including 1,000 sq.ft. (gross}..........................................................
1,001 to 10,000 sq.ft. (gross}..........................................................................
10,001 sq.ft. up to 25,000 sq.ft. (gross}..........................................................
25,001 sq.ft. up to 50,000 sq.ft. (gross}..........................................................
50,001 sq.ft. up to 100,000 sq.ft. (gross) ........................................................
100,001 or more sq.ft. (gross) ........................................................................
Major energy production or fuel processing facility.........................................
B, Additions or improvements
Regular calendar: see II.A. above
Otherwise: see III. below
e
III. FEES FOR PROJECTS NOT COVERED IN I. OR II. ABOVE
A. Administrative permit......................................................................................
B. Emergency permit ..........................................................................................
C. Amendments
Immaterial amendments....................................... ..................................
Material amendments................. [50% offee applicable to underlying
permit if it were submitted today]
0$
0$
0$
0$
0$
0$
0$
0$
0$
0$
0$
500
2,000
4,000
8,000
12,000
20,000
20,000
2001
2005
200
D. Extensions 7 and Reconsiderations
Single-family residences ..................................:..................................... 0 $ 200
All other developments........................................................................... 0 $ 400
E. Request for continuance
1st request ............................................................................................. 0 No charge
Each subsequent request
(where Commission approves the continuance}..................................... 0 $ 100
F. De minimis and other waivers......................................................................... 0 $ 200
e
5 When followed by a regular pennit8ppDcation, the $200 emergency application fee is credited toward the follow-up pennit fee.
7 II pennit extension i5 objected to by Commission and application Is set for a new hearing, then a new application fee is required, based on type 01
development and/or applicable calendar. 15
G. Public works facilities.........................................[if public agency is applicant] IZI No charge
H. Temporary events..................... ~f not scheduled on administrative calendar] 0 $ 500
.
IV. ANY OTHER DEVELOPMENT NOT OTHERWISE COVERED
Development cost up to and including $100,000....................................................
$100,001 to $500,000.................................................................... .........................
$500,001 to $1,250,000..........................................................................................
$1,250,001 to $2,500,000..................................................................................,...,
$2,500,001 to $5,000,000.......................................................................................
$5,000,001 or more .................................................................. ..............................
TOTAL SUBMITTED
ADDITIONAL NOTES
0$
0$
0$
0$
0$
0$
600
2,000
4,000
8,000
12,000
20,000
$
1. Fees are assessed at the time of application, based on the project as proposed initially. If the size of a proposed
dwelling or the amount of proposed grading is amended during the application review process, the fee is not changed.
_ 2. If different types of development are included on one site under one application, the fee is based on the sum of each fee
., that would apply if each development were applied for separately, not to exceed $20,000 (except as indicated in
footnote 4).
3. Fees for after-the-fact permits shall normally be double the regular permit fee unless such added increases are waived
by the Executive Director when it is determined that the permit could be processed by staff without significant additional
review time resulting from the processing ofthe violation.
4. The fee for development consisting of a change in intensity of use shall be based upon development cost as set forth in
part IV.
5. Permits shall not be issued without full payment of all applicable fees. If overpayment of a fee occurs, a refund will be
issued.
6. If a permit application is withdrawn, a refund will be due only if no significant staff review time has been expended (e.g.,
the staff report has not yet been prepared). Denial of a permit application by the Commission is not grounds for a
refund.
7. The application fee shall be determined from the type and size of the proposed development, except where size is not
readily determined and where the project is a change in intensity of use. In addition, if there is conflict over the
applicable fee, the Executive Director may use the project cost to determine the fee.
8. In addition to the above fees, the Commission may require the applicant to reimburse it for any additional reasonable
expenses incurred in its consideration of the permit application, including the costs of providing public notice.
9. The Executive Director shall waive the application fee where requested by resolution of the Commission.
_SEE SECTION 13055 OF THE COMMISSION'S REGULATIONS (CALIFORNIA CODE OF REGULATIONS, TITLE 14) FOR
., FULL TEXT OF THE REQUIREMENTS.
TO BE COMPLETED BY STAFF
16
SUBMITTED FEE VERIFIED BY:
DATE:
Is SUBMITTED AMOUNT CORRECT?
o Yes. Applicant has correctly
characterized the developmen~
and payment is appropriate.
o Applicant did not fill out form, 0 No. Wh'fl
thus staff has marked the form
to compute the fee, and applicant
has paid fee.
REFUND OR ADDITIONAL FEE REQUIRED? (STATE REASON)
o Refund amount
:
)
o Additional fee amount (
REMINDER: RECORD FEE PAyrJlENT IN PERru11T LOG
FINAL FEE VERIFIED BY: (TO BE COI./P!.ETED AFTER COMMISSION ACTION) DATE:
e
e
17
NOTICE OF
PENDING PERMIT
A PERMIT APPLICATION FOR DEVELOPMENT ON THIS SITE IS
PENDING BEFORE THE CALIFORNIA COASTAL COMMISSION.
PROPOSED DEVELOPMENT:
S~"l ttlG~ Uf.' ~\
Ute. k 121 h"lfilitA + iOJ1
LOCATION: 10 1-1..;t\ ~trce"
Seal &tat ~ ?,'oe (
APPLICANT: C;i-V -If Stal ~~..(h.
DATE NOTICE POSTED: It.. \\ f1 0,
FOR FURTHER INFORMATION, PLEASE PHONE OR WRITE THE
OFFICE LISTED BELOW BETWEEN 8 A.M. AND 5 P.M., WEEKDAYS.
CALIFORNIA COASTAL COMMISSION
SOUTH COAST DISTRICT OFFICE
200 OCEANGA TE, 1 Olli FLOOR
LONG BEACH, CA 90802-4402
(562) 590-5071
.
-- Description continued from page 2 of project application--
Overall, the Pier and its deck are in fair condition and because of its timber construction,
surfaces and appearance are rough and rustic. Routine inspections are performed by the
Public Works Department to identify components needing repair, adjustment, and
preventative measures. "Flipping over" the boards has been attempted in the past with
limited success due to the splintering/splitting of the decking. However, the historic aged
timber surface can be rough and uneven. Pedestrians are cautioned with signs at the
entrance to the Pier regarding the uneven surfaces.
A study was conducted by Moffatt & Nichol in May of 2006 to study alternatives for
rehabilitation of the decking on the Pier. A life cycle cost analysis was prepared along
with other factors including aesthetics, safety, comfort, and fire resistance and the
recommendation of the report was to replace the decking on the Pier with an imported
"Greenheart" hardwood. The hardwood is a higher costing alternative than replacing the
decking with the existing Douglas fir wood, but has a longer life
e
Due to the length of the pier and the associated cost, this project is split up into 4 phases,
each totaJing approximately one-quarter the length of the pier. The attached plans will
detail phases one and two, and will outline the future phases three and four still to be
designed.
Phase one is completed, phase two's design is substantially complete, phase three has just
started design and phase four is on hold due to funding levels. Upon the successful
execution of the contract documents, the contractor will have several months to procure
the Greenheart Hardwood for phases two and three, but only 8 to 12 weeks to construct
the improvements. There is no daytime Pier closures scheduled with this project. The
contractor will be working at night and reopen the Pier every morning. Specific notices
will be sent to surrounding residents to inform them about the construction impacts.
e