SUBJECT: ACCEPTANCE OF SEWER PUMP STATION 35-
PHASE 2 PROJECT No. 49886
SUMMARY OF REQUEST:
The proposed City Council action will adopt Resolution No. and
formally accept completion of construction for Sewer Pump Station 35 - Phase 2
Project No. 49886.
BACKGROUND:
e
On July 24, 2006, City Council awarded a construction contract to Socal Pacific
Construction, Incorporated in the amount of $894,725 for construction of Sewer
Pump Station - Phase 2 Project No. 49886. In accordance with the contract
documents, Socal Pacific Construction, Incorporated has completed the project
for a final construction contract amount of $957,247.71. Change orders in the
amount of $62,522.71 accounted for 7.0% of the construction contract amount
which is within the 10.0% contingency amount typically budgeted for this type of
project.
FINANCIAL IMPACT:
City Council budgeted $2.4 million of Sewer Capital Funds for the design,
construction, and inspection for both phases of the Sewer Pump Station 35
Project. The net cost of the project 'including design, construction, change
orders, and inspection for both phases is $2,257,375.48. The project was
completed under budget and $142,624.52 in remaining funds will be returned to
the Sewer Capital Fund Account.
RECOMMENDATION:
e
Upon motion of the consent calendar, it is recommended that the City Council:
1. By resolution, determine the work has been completed in accordance with
the contract documents and declare the work to be accepted and the total
amount of the contract is in the sum of $957,247.71.
Agenda Item IV
e
e
e
2. Direct the City Clerk, within ten (10) days from the date of acceptance, to
file a "Notice of Completion" with the Orange County Clerk-Recorder.
3. Upon expiration of thirty-five (35) days from the date of filing of the "Notice
of Completion", direct City staff to pay Socal Pacific, Incorporated
retention funds in the amount of $95,724.77.
SUBMITTED BY:
f"-V1nM-"lmono
Director of Public Works
NOTED AND APPROVED:
-
""I )
David Carmany
City Manager
Attachments:
A Resolution No. Declaring Work Completed
B. Notice of Completion
e
RESOLUTION NUMBER
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEAL
BEACH, CALIFORNIA DECLARING WORK TO BE COMPLETED
PER CONTRACT DOCUMENTS FOR SEWER PUMP STATION
35 - PHASE 2 PROJECT No. 49886
WHEREAS, on July 24, 2006, the City of Seal Baach entered Into a contract with
Socal Pacific, Incorporated; and
WHEREAS, the City Engineer has detennlned that the work has been
substantially completed in accordance with the contract documents.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF SEAL BEACH
DOES HEREBY RESOLVE:
That the work required 10 be performed by said Contraclor has
been completed.
That the Iotal cost of said work Is In the amount of $957,247.71.
That the work Is hereby accepted and approved.
It is further ordered that a 'Notice of Completion', exhibit A, be flied
on behalf of the City In the Office of the Orange County Recorder
within ten (10) days of the date of this resolulion.
PASSED, APPROVED and ADOPTED by the City Council of the City of Seal
Beach at a regular meeting held on the 10th day of March , 2008 by
the following vote:
Seclfon 1.
Section 2.
Section 3.
Seclfon 4.
AYES: Councllmember
e NOES: Councllmember
ABSENT: Councilmember
ABSTAIN: Councilmember
Mayor
ATTEST:
City Clerk
STATE OF CALIFORNIA )
COUNTY OF ORANGE } SS
CITY OF SEAL BEACH }
I, Linda Devine, City Clerk of the City of Seal Beach, California, dO hereby certify
that the foregoing resolution Is the original copy of Resolution Number _ on
file In the office of the City Clerk, passed, approved, and adopted by the City
Council of the City of Seal Baach at a regular meeting held on the 101h day
of March , 2008.
e
City Clerk
e
RECORDING REQUESTED BY
AND WHEN RECORDED MAIL TO
CITY OF SEAL BEACH
Attn: City Clerk
211 . 8th Street
Seal Beach, CA 90740
Space of above this line for Recorder's use.
- No Recording Fee Pursuant to Government Code Section 6103, 27383 ....
NOTICE OF COMPLETION
Notice pursuant to Civil Code Section 3093, must be filed within 10 days after completion.
Notice Is hereby given that
1.
2.
e 3.
4.
5.
6.
7.
The undersigned is owner or corporate officer of the owner of the interest or estate stated
below in the property hereinafter described:
The full name of the owner is: City of Seal Beach
The address of the owner is: Citv of Seal Beach. 211 8th Street. Seal Beach. CA 90740
The nature of the interest or estate of the owner is: In Fee. Citv of Seal Beach.
A work of improvement on the property hereinafter is described as substantially completed on
March 10.2007. The work was Sewer Pumo Station 35 - Phase 2 Proiect No. 49886.
The name of the contractor, if any, for such improvement was: Socal PacifiC. Incoroorated.
The date of the Contract Award was: Julv 24. 2006.
The property on which said work of Improvement was completed In the City of Seal Beach,
County of Orange, State of California, and is described as follows: 200 Seal Beach
Boulevard. Seal Beach. California 90740.
Date:
Signature of owner or corporate officer of owner
named In paragraph 2 or his agent.
VERIFICATION
I, the undersigned, say: the Director of Public Works declarant of the foregoing notice of
completion; have read said notice of completion and know the contents thereof; the same is true
of my own knowledge.
I declare under penalty of perjury the foregoing is true and correct.