AGENDA STAFF REPORT
e
DATE:
April 14, 2008
TO: Honorable Mayor and City Council
THRU: David Carmany, City Manager
FROM: Vince Mastrosimone, Director of Public Works
SUBJECT: Primer on Construction Management Options for Fire Station #48
SUMMARY OF REQUEST:
The City Council is asked to receive and file this report on Construction
Management options for the reconstruction of Fire Station #48.
e
BACKGROUND:
The City has commenced a project to replace Fire Station #48, 3131 Beverly
Manor Road. To date the City has retained an Architect to provide conceptual
drawings and design development drawings for the project. There have been
numerous meetings with the Architect and the Orange County Fire Authority
(OCFA) to ensure the proposed design meets the operational criteria of OCFA.
As of March 12, 2008, OCFA has approved the building floor plan and site plan.
There is a significant issue to be decided in the near future regarding the project
contracting format and project delivery method. Some of the options include:
· Traditional Design, Bid, Buiid using in-house staff for construction
management (Agency Construction Management)
· Traditional Design, Bid, Build using an outside construction management
firm (Agency Construction Management)
· Construction Management At-Risk
In the first two methods, the City relies on traditional ways of building the project.
The City retains the design team to develop the construction plans, conducts a
public bid process, awards a construction contract and oversees the construction
of the project. The City may opt to oversee and manage construction with in-
house staff or hire a consultant to do so. In either case, once the project is
awarded to a general contractor, the risk for completing the project within the
price bid is transferred to the contractor. The construction manager (CM) is often
retained early in the process to provide expertise during the design phase.
e
In construction management at-risk, it allows the City to choose the CM before
the design stage is complete. The CM is chosen based on qualifications, and
then the entire operation is centralized under a single contract. The architect and
CM work together in order to develop and examine the design. Then, the CM
gives the client a guaranteed maximum price (GMP), and coordinates all
subcontract work. At this point, the role of the CM changes to the equivalent of
Agenda Item T
general contractor. By hiring the CM during the design phase, early coordination
is possible, which can increase the speed of the project and strengthen ..
coordination between the AE and the CM. Also, because all costs and fees are in _
the open, it eliminates bid shopping and reduces delays.
In the case of traditional construction management or construction management
at-risk, the construction management services can command a fee of 4%-6% of
construction costs.
Many Orange County public agencies are using the construction management at-
risk model. The GMP feature is an attractive element of the method. This is a
method City staff is carefully researching.
A document entitled "An Owners Guide to Construction Management" developed
by the Construction Management Association of America, Inc. is attached for
your perusal. It provides an outstanding overview of each of the three options.
The purpose of this agenda item is to introduce the City Council to various
construction management options without the pressure of having to make a
decision immediately. Staff expects a recommendation for a construction
management option will be made in May.
FINANCIAL IMPACT:
None
e
RECOMMENDATION:
It is recommended the City Council receive and file this report on Construction
Management options for the reconstruction of Fire Station #48.
NOTED AND APPROVED:
0---=1
David Carman ,City Manager
Attachments:
A. An OWners Guide to Construction Management
e
e
Rn Owne(s Guide To
ConstrucNon Management
e
Assuring Project Success
Under Any Delivery Method
Copyright 2002
e
The Construction Management Association of America, Inc.
All Rights Reserved
e
RCHNOW~EDGMENTS
CMAA gratefully acknowledges the time and efforts of those who served as contrib-
uting editors in developing this Owner's Guide to Construction Management.
Without the collective efforts of these individuals, this document would not have
been possible.
Al GravaIlese, Daniel, Mann, Johnson & Mendenhall
Blake V. Peck, P.E., CCM, McDonough Bolyard Peck
Bob Fraga, U.S. Postal Service
Chris Reseigh, Parsons Brinckerhoff Construction Services
Eclward Mislavsky, Project Planning Group, loc.
Gregory Henk, Transportation Corridor Agency
Herb Saunders, Parsons Brinckerhoff Construction Services
Jerry Gold, O'Brien Kreitzberg
Joe McAtee, P.E., Urban Engineers, Inc.
Joseph Whitehouse, Construction Management Services, loe.
Mike Swanson, DLR Group
Neil E Katz, Hill International
Richard CuIlerton, Metropolitan Washington Airports Authority
Rick Fennema, GREYHAWK North America, LLC
Robert Wilson, ECMAA, Gilbane Building Company
Robert York, The)CM Group
Ron Pennella, StructureTone
Thomas Quaranta, Parsons Brinckerhoff Construction Services
e
Construction Management Association of America
7918 Jones Branch Drive, Suite 540
Mclean, VA 22102
703-356-2622
www.cmaanet.org
e
e
Preface
e
Construction management evolved as a professional practice distinct from design and
construction in the early 1960's in response to increasing complexities in the construc-
tion industry. Highly sophisticated construction systems led to the specialization of both
design and construction professionals. Additionally, increasing regulatory mandates,
litigation and other risks created a need for a new professional to be an advocate for the
Owner and bridge the gap between the Owner, the Designer and the Contractor. Today,
construction management is well established, and recognized around the world as an
indispensable profession.
A Construction Manager (CM) provides the Owner with specialized knowledge,
experience and resources to navigate through the complexities of a construction program
or project Construction management services may be tailored to satisfy the needs of the
novice or sophisticated Owner. The CM adds value by providing the resources and
expertise needed to manage quality, cost, schedule, scope and risks associated with
design and construction to help the Owner achieve its objectives.
A major construction effort is a complex and risk-laden venture. It involves the
expenditure of a large sum of capital as well as the application of technologies of which
many are aware, some are conversant, but few are expert It requires the Owner to do
business with several groups of people whose interests are not its own and to venture into
a field with its own set of rules, some of which are not written down anywhere. It is an
intensive process demanding constant attention in order to achieve success.
The federal government has a construction budget that is measured in billions of
dollars and a plan for accomplishment that is measured in decades. Many state govern-
ments have construction efforts of hundreds of millions of dollars and multiple years.
Although the federal and state governments have standing staffs to manage their typical
construction program, they often need specialized expertise or supplemental staff to help
manage certain projects.
Smaller government organizations are like smaller businesses, having the same
organizational needs for construction expertise matched against an equal need to reduce
expenses. Moreover, many times the smaller private Owner cannot afford to build a staff
and fully develop sufficient expertise to embark upon a construction program.
The use of professional construction management services to oversee all or parts of
the planning, design and construction process is recognized in both the public and
private sectors as an effective and efficient means of achieving successful delivery of
constructed projects under any contract format
The Construction Management Association of America (CMAA) presents this
document as a guide to public and private Owners in selecting a critical component of
the construction project: the CM.
This guide will benefit those Owners who will embark on a construction project and
who will seek expertise in the planning, design and construction process. It introduces
the construction management practice and describes how it can enhance the success of a
project
e
e
Contents
ExecuNve SummarIl....................................................................................l
1.0 Denning ConstrucNon Management .................................................... 3
The Project Participants ................................................................... 3
Needs of the Project .........................................................................4
2.0 Con~acNng and Project DeliverIl S~stems ........................................ 6
Contracting Methods .......................................................................6
Project Delivery Systems .................................................................. 7
3.0 Wh~ Construction Management? ........................................................8
CM as Agent or At Risk..................................................................... 8
Role of the CM.................................................................................. 8
e
4.0 Selecting the CM ................................................................................. 10
Preliminary Decisions and Information ........................................10
Qualification Based Selection of CM .............................................. I I
Methods of Paying for Services ...................................................... 14
Standard Contract Forms ............................................................... 15
e
e ExecuNve Summarq
e
ProfeSSional CMs can be instrumental in achieving successful construction
projects and may be used in a variety of contracting methods and proj ect
delivery systems.
There are many issues an Owner must consider in undertaking a project,
such as time and cost constraints, the need for fIenoility, pre-construction
service needs, design process interaction, and financial constraints. The project
team should enhance and reinforce the strengths of the Owner to provide a
comprehensive set of resources and skills to accomplish the project.
While a wide and somewhat bewildering variety of ways to organize a
project have been developed to satisfy the needs of Owners and projects, all
share the same basic set of players: the Owner, the CM, the Designer, other
consultants, Contractors. and Subcontractors. Regardless of resources, Owners
must choose a particular organization. contract and award, and combine them
into a desired and appropriate contracting method for each project.
Construction management is a professional services discipline applied to the
planning, design and construction process of capital improvement projects.
Professional CMs address the needs of projects and Owners by providing
management services and expertise tailored to project needs and independent of
the chosen contract format or project delivery method. It is this management
approach that makes construction management unique. CMs apply and integrate
comprehensive project controls to help manage the critical issues of time, cost,
scope, quality and safety.
As an Owner, it is necessary to choose a project delivery method and
contracting format that efficiently delivers the project. A contractingjormatis an
arrangement for the distribution or allocation of construction project risk (most
frequently cost or performance risk) between the parties to a contract. A project
delivery method is designed to achieve the satisfactory completion of a construc-
tion project from conception to occupancy. Construction management has been
used successfuIly in all contracting and delivery systems by Owners who do not
continuously maintain the staff expertise or numbers necessary to deal with the
complex responsibilities involved in the management of major projects. In
addition, the CM usuaIly helps the Owner identify which delivery system is best
for the project.
A number of contracting formats exist including fixed price, guaranteed
maximum price, cost plus fixed or variable fee, and unit price contracts.
Construction projects in the United States have traditionally been delivered
through the design-bid-build project delivery method. Because of financial,
organizational and time constraints, alternative project delivery methods have
evolved to fit particular projects and client needs. These include multiple primes;
developer manager; design-build; and design, build, operate and transfer.
Construction management comes in two general forms. In agency construc-
tion management, the Owner utilizes a CM as its principal agent to advise on or
manage the process over the life of the project regardless of the project delivery
e
OWNER'S GUIDE
Construction
management is a
professional
services discipline
applied to the
planning, design
and construction
process .
I
method used. In construction management at risk, the Owner utilizes a CM to
consult in the Pre-Design and Design Phases of a project. However, the CM's role ..
also includes a construction performance role during the Construction Phase.At ..
that time, the CM converts to the legal equivalent of a general contractor once a
price is established for the completion of the construction work.
Typically, professional construction management services are procured on
the basis of an objective evaluation of the qualifications of competing firms. As is
the case with any professional service contract, the issue of price does not enter
into the ranking of construction management firms based on their qualifica-
tions. The Owner and the selected CM then jointly, through negotiation, develop
a final scope of services to support the timely delivery of the project. Develop-
ment of a construction management budget grows out of this scope and is the
first step in the detailed planning of the project Among the methods recognized
and co=only used in the compensation of firms for professional construction
management services are salary times multiplier plus direct expenses, billing
rates, and cost plus fixed fee.
e
e
2
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
e
1.0 Denning Construc"on Management
e
There are several issues an Owner must consider in the selection of a method of
accomplishing a project:
. Time needs of the project-Does it have to be done quickly? Will the
schedule be affected by outside influences? will the schedule be lengthened
by cash flow considerations?
. Needs of the project for flexibiIity- How much change will be required
during the construction? How much of the project will be fully defined by
the Owner and Designer prior to its being constructed? If other than the
Owner, how much influence will the user have over the design and construc-
tion?
. Preconstruction service needs-How much assistance will the Owner need
in the definition and planning of the project with respect to quality and
safety, and with respect to cost versus scope versus time?
. Design process interaction-How well does the Owner understand the
design process and the cost impacts of decisions made in the course of
design development? How complex is the design process for the project?
. Financial constraints-How is the project financed? How does the financ-
ing influence the schedule, type of contract, risk and other requirements of
the project?
The Project Pamcipants
While a wide and somewhat bewildering variety of project organizations have
evolved over time to satisfy the needs of Owners and projects, all share the same
basic set of players:
. The Owner- Tbe private or public organization ultimately responsible for
the proper execution of the project.
. The Construction Manager (CM)-A provider of professional services to
the Owner, the CM organizes the effort, develops the management plan,
monitors the participants' progress against the plan and identifies actions to
be taken in the event of deviance from the plan. The CM also provides expert
advice in support of the Owner's decisions in the implementation of the
project. The CM can be a firm, a team of firms, or an'individual.
. The Designer(s)- Employed by the Owner to provide design services in
support of the project. While Designers can be contractually responsible to
the Owner. they report progress to the CM and are monitored by the CM for
compliance with the scope statement and both the design and construction
budgets.
. Other Consultants-Providers of specialized services, such as real estate
acquisition firms, geotechnical engineering firms, environmental engineers,
e
OWNER'S GUIDE
3
It is the matching
of services
to project/Ovvner
needs that makes
CM a cost effective
approach to
managing
project delivery.
4
permitting consultants, etc., employed by the Owner in support of the
project Their efforts are coordinated and monitored by the CM.
. The Contractor-The organization or individual who undertakes responsi-
bility for the performance of the work, in accordance with plans, specifica-
tions and contract documents, providing and controlling the labor, material,
equipment, and subcontractors to accomplish the work.
.
Needs of the Project
Several forms of project organization have been developed that are designed to
meet the needs of specific projects and Owners. The integration and coordina-
tion of the complex interrelationships occurring in a typical construction
process require substantial expertise. Some Owners may have extensive opera-
tional organizations with vast knowledge of the business of the Owner or of a
particular facet of the construction industry such as finance or building mainte-
nance. Other Owners may not have the organizational resources or expertise on
board to meet the needs of a particular project. Whatever level of expertise the
Owner may have, the organization of a project can be designed to enhance and
reinforce the strengths of the Owner's existing staff to provide a comprehensive
set of skills to accomplish the project
Expertise applicable to virtually any project includes:
. Project scope development
. Land acquisition
. Permitting
. Financing
. Cash flow management
. Design acquisition and management
. Cost estimating
. Cost and schedule control
. Contract administration
. Document control
. Construction inspection
. Quality control
. Value engineering
. Risk management
. ConstructibiIity review
. Contracting and proj eel delivery systems
. Dispute avoidance and resolution
. Commissioning
. Activation
Construction management is a professional services discipline applied to the
planning, design and construction process. CMs provide a program of manage-
ment techniques and expertise tailored to Owner and project needs and inde-
pendent of the chosen contract form or project delivery method. It is this
e
e
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
e
e
e
management approach that makes construction management unique. CMs
apply and integrate comprehensive project controls to manage the critical
issues of time, cost, scope and quality. It is the matching of services to projectJ
Owner needs that makes construction management a cost effective approach
to managing proj ect delivery.
A significant advantage of using a CM is that the organizational structure
is not dependent on a single model or set of models. Generally, CMs fall within
two categories, "agency" or "at risk."
In "agency construction management" the CM assumes the position of
professional advisor or extension of staff to the Owner. The Owner lets most of
the contracts, and certain cost and performance risk is placed on the Contrac-
tors. In these cases, the CM is in a position to offer advice unencumbered by
any interests other than those of the Owner and the project. The term agency
infers, as is intended, a delegation of function to the CM by the Owner. As a
consequence, it is possible that certain tasks and responsibilities place the CM
in a legal agent relationship with the Owner. The necessity for openness and
candor between the CM and Owner is paramount.
When the CM's role includes a construction performance function, it is
known as the "CM-at-risk" approach. In this approach, which can often occur
under a guaranteed maximum price (GMP) contract format, the CM will
assume additional obligations and will undertake construction responsibilities
during the Construction Phase. At that time, the CM is typically placed in a
legal position similar to that of a Contractor entering into a traditional con-
struction agreement which provides for the completion of the construction
work for an established price.
Regardless of the form of contract agreement, the CM is performing
professional tasks throughout all the phases of program project implementa-
tion.A contract agreement will establish the scope of services and will also
define the relationship of the parties.
OWNER'S GUIDE
5
2.0 ContracNng and Proiect Oeliverq Sqstems
e
Rs an Owner, it is necessary to choose an overall project delivery and contract-
ing strategy which efficiently delivers the projeclAn understanding of the
difference between a project delivery method and a contracting format is
important because it impacts these decisions.
ContracNng Formats
A contractingfurmat is an arrangement for the distribution of construction
project risk-most frequently cost or performance risk-between the parties to
a contract Cost risk is the risk of being able to do something within a given
budget limit. This risk distnbution is accomplished through methods of arriving
at or limiting the amount of money to be paid. Performance risk is the risk of
being able to complete the project on time and at the level of quality as agreed.
This is distnbuted through the technical terms of the contract, either by describ-
ing requirements for the finished product only, or by describing speciJi.c methods
by which a task is to be performed. Contracting formats require some form of
specific scope statement in order for the parties to make an accurate economic
judgment as to cost or price.
A number of contracting formats have evolved as a result of the desire of
Owners or Contractors to either shift or share the risk (usually cost) of a project
through contractual provisions or to increase the speed of delivery of construc-
tion.
Public, and quite frequently private, works are usually procured through a
sealed bid, fixed price contract or the equivalent. In these contract arrangements,
most of the price risk is intended to shift to the Contractor. In order to provide a
reasonable and enforceable scope definition to the Contractor so that bids can be
developed, fixed price contracts are almost always based on a completed design.
The need to have a completed design in hand prior to the commencement of
construction requires a longer lead time for the construction process and
requires a linear approach to project delivery that reduces flexibility.
Seeking more fienble alternatives, the private sector developed a host of
risk-shifting and risk -sharing contract variations, including negotiated fixed
price, guaranteed maximum price (GMP), cost plus fixed or variable fee, time
and material, unit price, prepurchasing, and others. These contracts run the
spectrum from the lump sum, where all of the cost and schedule risk is placed on
the Contractor, to cost reimbursable situations, where the Owner agrees to pay all
costs. Most of these methods are now also being implemented, to some extent, by
public sector Owners.
Performance risk shifts are accomplished by the writing of end-product or
performance contracts. When applied to a complete project, these are typically
known as design-build contracts. If this form is coupled with a GMP, theoreti-
cally the Owner has little risk either in cost or satisfaction beyond the GMP. Since
a substantial part of the desired outcome from these projects is subjective, the
The need to have a
completed design
in hand prior to the
commencement of
construction requires
a longer lead time
and a linear
approoch to
project delivery
.
e
6
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
e
The key to
successful
management of
the construction
process is the
placement of risk
in the hands of
those who are
best equipped
to manage it
e
e
OWNER'S GUIDE
risk of misunderstanding is large and can easily result in either disputes over what
is included in the GMP or in disappointment on the part of the Owner in the final
project as delivered.
Project Deliver~ Metl10ds
A project delivery method is a system designed to achieve the satisfactory comple-
tion of a construction project from conception to occupancy. A project delivery
method may employ anyone or a number of contracting formats to achieve the
delivery. Project delivery methods define scope as part of their process.
Construction projects in the United States have traditionally been delivered
through the design-bid-build sequence, securing the services of a Designer who
will design the project, aid in the procurement of a Contractor, and often inspect
the work of the Contractor for compliance with the specification. This sequence
usually leads to the sealed bid, fixed price contract believed by many to offer the
least capital cost to the Owner as well as the one generally required by public
procurement regulations to assure fairness in the procurement process. However,
this "traditional" project delivery system allows the use of many contracting
methods, since there is no inherent constraint on the allocation of price risk.
Because of financial, organizational and time constraints, other project
delivery methods have evolved to fit particular projects and client needs. These
include:
· Multiple Primes-The Owner uses separate contracts for various construc-
tion disciplines such as general construction, structural, mechanical, electri-
cal, etc.
· Developer Managcr- The Contractor will acquire (or have constructed) a
facility to suit the needs of the Owner who in turn commits to lease the
facility.
· Design, Build, Operate and Transfer-The Contractor will design, build,
operate and maintain a facility for a fixed period before transferring it over to
the Owner.
· Design-Build-The Owner utilizes a single contract to acquire the services of
both Designer and Contractor to construct a facility.
These delivery methods all share the characteristic of placing the Owner in
what is a potentially unequal relationship with the Contractor. These systems may
at times require the Owner to place the fate of the project in the hands of an
organization or organizations whose interests may be in conflict with those of the
project or of the Owner, due to contractually assigned risks.
In addition, these delivery methods all share the same disadvantages in that
the Owner is required to have sufficient staff resources to fulIy define the project
or be willing to allow another entity to define it The Contractor or Designer or
Developer has clear risks that it has assumed in its arrangement with Owner and
has developed the expertise to manage these risks.
Parties who bear the risk in an endeavor are due their rights to control their
destiny. The greater the risk profile, the greater the need to control. Loss or per-
ceived loss of control leads to fear of a negative outcome. This fear leads to an
assertion of the right to control, resulting in frequent disputes. Therefore, the key
to successful management of the construction process is the placement of risk in
the hands of those who are best equipped to manage it
7
3.0 Whij ConstrucNon Management?
e
Construction management has been used successfully in all delivery
methods for Owners who do not continuously maintain the staff expertise or
numbers necessary to deal with the complex responsibilities involved in the
delivery of major capital projects. The CM frequendy helps the Owner
identify which delivery method is best for the project
The construction management approach utiIizes a firm (or team of
firms) with construction, design and management expertise to temporariIy
expand the Owner's capabilities so that the Owner can successfully accom-
plish its program or proj ect.
A CM frequendy has a role in both traditional and alternative project
delivery methods as a trusted advisor to the Owner in oversight of the party
at risk in the arrangements.In such cases, the CM may have a reduced scope
of work, but participates in the decision-making process on behalf of and in
concert with the Owner. This can be particularly helpful in design-build
where substantial scope definition responsibility and project control have
been assigned to the design-builder, and there exists no natural check on the
design-builder.
CM as Rgent or Rt Risk
As previously mentioned, construction management comes in two general
forms:
. Agency CM- The CM acts as the Owner's principal agent to advise on
or manage the process from project conception to completion.
. CM at risk-The CM provides professional management assistance to
the Owner prior to construction and advice on constructibility, budget
and schedule considerations. The CM later converts to the equivalent of a
General Contractor during construction.
The key difference between these two forms is that the CM at risk is in
fact a distinct delivery method due to its responsibility for construction
performance. Agency construction management, on the other hand, is a
distinct set of services that can be applied to any delivery method.
Role of lt1e CM
Use of a professional consultant in construction management improves the
Owner's confidence in the success of the project This enhanced confidence
grows out of the ability of a professional CM to make expert recommenda-
tions regarding:
. Most effective use of available funds
. Enhanced control of the scope of the work
. Optimal project/program scheduling options
8
Construction
management
includes
a significant
component
orten missing from
proied delivery
systems-
a comprehensive
management and
control effort
e
e
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
e
Well formulated
and priced
construction bid
packages are the
key to minimizing
changes and
avoiding disputes
and delays during
construction
e
Using a consultant
eM allows the
Owner to make use
of expert advice
/hat is unaffected
by any potential
con~ict of interest
e
OWNER'S GUIDE
. Best use of individual project team members' expertise
. Maximum avoidance of delays, changes and claims
. Enhanced design and coustruction quality
. Optimum flexibility in contracting/procurement options
Construction management includes a significant component often missing
from the project delivery systems-a comprehensive management and control
effort applied to the project for the Owner, beginning in the early program
planning stages and continuing through project completion. It involves the
application and integration of comprehensive project controls to the design and
construction process and generally includes the following:
. Development of a written scope understood by all of the participants
. Development of thorough design criteria for issue to the Designer
. Design quality assurance throughout the design process
. Consideration of material, systems and process alternatives
. Constructibility review
. Code compliance review
. Milestone cost estimating-to ensure design complies with the budget
. Matching construction spending to funds availability
. Construction specification enforcement
. Continuous schedule enforcement
The implementation of these management activities turns the planning,
design and construction process into one which maximizes the Owner's control
over the project's scope, quality, time, and cost, and adds predictability of the
outcome of the project from start of programming to completion of construc-
tion.
Early development of the scope of the project provides information for the
establishment of a baseline budget and schedule. Because of the continuous
monitoring of the schedule and project cost during the progress of the project,
the impact of changes and new information on this baseline can be evaluated
and corrective action taken when most effective. Well formulated and priced
construction bid packages, developed during the planning and design process,
are the key to minimizing changes and avoiding disputes and delays during
construction. This is the Owner's most powerful tool in assuring a positive
outcome for the project
The addition of a CM does not lessen the Owner's control over the project,
but enhances it through the Owner's acquiring as adjunct staff an organization of
experts in the design and construction process that will enable the Owner to
make informed and timely decisions during the evolution of the project
When an Owner implements a program or project using a consultant CM, it
allows the Owner to make use of the expert advice available, advice that is
unaffected by any potential conflict of interest. The Owner is still able to obtain
the advantages of the many procurement methods, but with much greater
control over and confidence in the outcome.
9
4.0 SelecNng ff1e eM
.
CMAA reco=ends the selection and use of a CM for projects which are
complex by virtue of their nature or size, or for which the Owner does not have
an adequate capacity to manage the project effectively.
Typically, professional services of this sort are procured on the basis of an
objective evaluation of the qualifications of competing firms. There are accepted
practices that are used by both private entities and public bodies to select the
best qualified CM for the project.
Preliminartj Decisions and InformaNon
At the outset of the CM selection process, certain information should be docu-
mented and certain decisions should be made regarding the concept of the
project and the needs of the Owner in realizing project objectives.
A brief, detailed description of the project, including size, purposes, goals
and objective parameters, must be developed in order to convey to the CM
proposer the activities and approximate level and type of skills that will be
necessary. If any studies or other documents are available, they should be called
to the attention of the proposers.
The Owner's needs and expectations with respect to scope, schedule and
budget should be included in the description. Finalization of schedule should not
take place until the selected CM has advised the Owner regarding the
achievability of the proposed schedule and associated project cost
Owner's Internal Delegation and Management
On all projects, the ability to react to changing circumstances is critically impor-
tant.The project decision-making process must be designed to deliver informed
decisions in the most timely manner possible. It has been said that the most
frequent cause of project disruption is delayed decisive action.
It is very important that contractual authority-authority to obligate the
Owner to pay money-be delegated to a qualified individual or small group of
people so that decisions can be rendered in a timely manner and by those who
are most familiar with the project. These decisions may concern change orders,
contracts, dispute settlements, minor purchases and contracts in support of the
project.
Some Owners' governing bodies may establish budget gt1idance for parts of
a project, with specific decision authority within those budgets delegated to a
part of the permanent staff, subj ect to review. These practices are highly recom-
mended so that the Owner will gain credibility with the Contractor and consult-
ant co=unity.
Decisions with regard to the project organization, as envisioned by the
Owner, including the reporting relationships among the Owner and all other
parties to the design and construction effort, should be made and summarized
for reference in the selection process.
10
Professional services
are procured on
the oosis of an
objective evaluation
of the qualifications
of compeJing firms.
There are accepted
pradices used by
both private entities
and public bodies
to select the best
qualified firm
.
.
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
.
The committee is
responsible for one
of the most critical
decisions in the
projecHhe
selection of the OV\
.
The RFP should be
drahed with the
understanding
that. . . the more
consistent the
presentations by
the respondents
the easier the
evaluaJion will be
.
OWNER'S GUIDE
The Selection Committee.
A CM selection committee should be formed from the Owner's staff early in the
selection process so that the committee can learn as much as possible about the
project and the Owner's expectations of the CM.
The committee is responsible for one of the most critical decisions in the
project-the selection of the CM. The committee will be comparing the ap-
proaches offered by several firms, their skilJlevels and the experience of their
personnel, with the expectations and needs of the project and the Owner's
organization. Each individual on tbe committee should understand how the
selection process will be structured. The committee should include the indi-
vidual on the Owner's staff who will be responsible for the project.
While it is not necessary that all members of the committee be familiar with
the design and construction process, at least one member should. If the Owner
does not have an individual on its staff who can provide this expertise, it may be
appropriate to retain a consultant for the selection process. Individuals such as
senior members of the engineering or architectural community can be used for
this purpose. It is also important that the committee be free from any conflict of
interest in the selection of a CM.
OualincaNons Based SelecNon of l11e eM
Laws and regulations generally govern the process of selection for public work,
and practices will vary among the states. The process, however, generally follows
three steps: a statement of qualifications; a technical proposal; and a price
proposal and fee negotiation.
Statement of Qualifications.
A request for qualifications (RFQ) should be advertised in national and local
publications which will reach the CM community. The requested statement of
qualifications is usually a document which descnbes in general the qualifica-
tions of a firm (or team of firms) to perform the work. It will often include the
following types of information:
. Firm name and address
. Types of services usually offered
. Names of principals
. Numbers of staff, organized by discipline
. Description of similar work completed including date, size and Owner
contact
. Description of similar work in progress, including date, size and Owner
contact
. Annual volume, backlog and capacity
. Record of performance; I.e., cost control, quality, schedule, and safety
Federal Standard Form (SF) 254 contains substantially this same type of
information and is maintained by most firms.A related form, SF 255, contains
similar data and is designed to specifically address a particular project.
The selection committee should evaluate the firms' submissions and make a
judgement as to which firms appear qualified to perform the work. This will bave
the effect of reducing the number of competing firms to what is commonly
known as a "short list"
11
Technical Proposal
Those that are judged to be qualified are requested to submit a technical proposal.
This solicitation, issued as a request for proposal (RFP). is a request for informa-
tion about a firm's qualifications and intentions to perform the services desired.
The technical proposals are usually written for a specific project.
The RFP should provide prospective respondents with a description of the
project and information reganding the method of comp~nsation.Additionally, the
RFP should contain information about the project such as the project budget,
major constraints, unusual services that may be required, and particular goals of
the Owner.
If the Owner has sufficient understanding of the expected scope of services, it
may be advantageous to organize the RFP on that basis. The RFP may also be
organized as a series of questions to be answered by the respondents.
The RFP should seek the following information from the proposers:
. The respondent's approach to the project in terms of organization, process,
tools and techniques, staff and quality assurance/quality control, etc.
. The respondent's experience with projects of similar nature, including Owner
references
. Resumes of key staff to be assigned full time and those to be available as
resources
Owners should keep in mind that proposals are often a CM's largest non-
project expense. CMs appreciate an RFP that allows them to efficiently present
their qualifications. It is appropriate for the RFP to include the criteria for the
evaluation of the proposals as well as the weighting to be used.
It is desirable for the selection co=ittee to be involved in the development
and organization of the RFP.The RFP should be drafted with the understanding
that the selection committee will have to evaluate a number of technical proposals
and that the more consistent the presentations by the respondents the easier the
evaluation will be. A mandatory outline of the technical proposal is useful in
organizing the data for comparison by the selection co=ittee. Additionally, a
page limitation is suggested to keep the presentations to a manageable size.
The page limitation should not include data such as resumes and brochures.
The RFP should be examined by an experienced person for clarity and internal
consistency.
Evaluation Process.
The evaluation process may be time consuming and difficult. The selection
committee should proceed with a logical and methodical evaluation of each
proposal and grade each against the evaluation criteria stated in the RFP. The final
ranking of CMs should be determined by averaging ranks assigned by each
panelist rather than averaging the panelists' scores. This serves to reduce the
influence of anyone member of the panel and to ensure that the relative best of
the proposals are identified. The CM proposal with the best average numerical
ranking should be selected as the finalist to proceed to the next steps of submit-
ting a cost proposal and negotiating the work effort.
In some cases, more than one respondent may appear qualified, and inter-
views or oral presentations may be the only appropriate method to differentiate
between the top respondents. Interviews should be scheduled to provide the
respondents, with the best opportunity to show their capabilities. Questions
12
The compatibilify
belween those
of the CM and
those of the Owner
is a critical
consideration. . ,
the eM will be
a trusted part of
the Owner's
proiect team
.
.
Unless the RFP is
extreme~ detailed
and specific,
the total costs of
lwo proposals
will prooob~ not
be comparable
.
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
.
The Owner and
the selected OV\
should jointly agree
on a final scope of
services designed
to support the
time~ delivery of
the project
.
.
OWNER'S GUIDE
should be formulated in advance by the selection committee to clarify points in
the RFP response and to stimulate contrasting views among the respondents.
Since the Owner will be placing the fate of the project into the hands of the CM,
the compatibility between the goals and culture of the CM and those of the
Owner is a critical consideration. On large or complel: projects, where the
competition is close, two or more rounds of interviews may be necessary
(keeping in mind, however, that preparing for interviews can be extremely costly
for a consultant).
Price as a Part of the Proposal.
As is the case with any professional service contract, the issue of price should not
enter into the ranking of CM firms based on their qualifications. The selection
committee should keep in mind that the CM will be a trusted part of the Owner's
project team and that the most important factors are the capabilities of the
selected CM.
Some Owners will request a cost proposal as a part of the RFP. This can be
useful in evaluating the thought given to the approach to the project and the
proposer's organization for it. Price proposals included as part of the RFP
response may also save time in the negotiation of the agreement.
Unless the RFP is extremely detailed and specific on the issues of cost, the
total costs of two proposals will probably not be comparable. Scopes of work as
envisioned by each proposer may not be the same, particularly in assumptions
about staffing levels. Qualifications of personnel may be sufficiently different to
cause significant difference in price as well as level of service. Costs or multipli-
ers (of cost) may be structured so as to appear lower than they effectively are.
One proposer's direct cost may be included in the multiplier or assumed to be
furnished by others. In essence, costs in the proposal stage are very soft numbers
and should be analyzed in detail and with great care before comparisons are
made.
When price proposals are solicited with the RFP, they may be required to be
submitted in a separate, sealed and labeled envelope to be opened only when the
qualifications-based selection phase has been completed.
Negotiation and Development of Scope of Services and Cost.
Upon evaluation of the responses to the RFP, the firm judged most qualified is
requested to provide a proposed scope of services. After thorough discussions
designed to assure that both parties are in agreement on the desired level of
service, the selected CM prepares a written scope of services proposal.
Decisions made and approaches discussed at this time will ultimately affect
the success or failure of the project. Definition of necessary tasks and the
application of estimated labor and expense to each task is an efficient way to
develop a budget. To be addressed in the scope of services are:
. Development of a specific project scope statement
. Development of procurement strategy
. Development of a project schedule and budget
. Acquisition of special consultants
. Acquisition of Designers
. Acquisition of Contractors and Suppliers
. Quality. cost and schedule control
. Testing, startup and turnover
13
The scope of services should include deliverables or other tangible
methods for measuring performance. Where applicable, physical examples
of reports or other expected outcomes should be included or referenced.
CMAKI Construction Management Standards of Practice is not intended to
be a scope statement in support of a contract, but it provides information
about the functions typically provided by a CM.
The Owner and the selected CM should jointly, through negotiation.
agree on a final scope of services based on the selected CM's scope proposal
and designed to support the timely delivery of the project. Development of a
CM budget grows out of this scope and is the first step in the detailed
planning of the project.
If the Owner and the most qualified CM are not able to reach agreement
on price and scope, negotiations are commenced with the next qualified
firm.
Mel110ds of Paqing ~r Services
Several methods are recognized and commonly used in the compensation of
firms for professional construction management services. All result from a
negotiation between the Owner and the CM as to the proper level of staffing
for particular tasks that constitute the CM's scope of services.
Salary Times Multiplier Plus Direct Expenses.
A typical approach is based on a CM's direct salaries times a multiplier. The
multiplier is a number that is derived from the sum of the CM's indirect
salary costs (such as FICA and unemployment insurance and salary ben-
efits) and overhead costs (general and administrative office and other
indirect costs) divided by the total salaries paid. This ratio is used by the CM
to recover these costs. An agreed profit rate is then applied to the product of
the direct salary times the multiplier. Direct project expenses are paid
separately. Frequently, an administrative or handling charge may be made on
the direct expense.
Salaries are the actual salaries of the individuals working on the project.
Direct expenses are the necessary and ordinary expenses associated with the
CM's performance. These may include items ranging from paper and pens,
to automobiles, travel, separate offices, furniture, computers, software, etc.
Some Owners may provide office space or buy some equipment for the use
of the CM during the project to avoid lease payments. Some direct expenses
may be avoided by use of Owner assets.
Billing Rates.
An alternative to the use of salary times multiplier is the use of classified
billing rates. These rates are typically based on average salaries for a speci-
fied range of employee skills, experience and education. An amount of
money is added based on the CM's overhead and profit multiplier and the
resultant sum is used for all individuals in that classification. The classifica-
tions have to be carefully defined to avoid confusion.
Cost Plus Fixed Fee.
Some payment arrangements fix the amount of fee (profit) that the CM will
be paid to a lump sum. These arrangements also spell out how and in what
increments the fee will be paid. The CM is paid actual salaries times a
14
Compensation
for professional
Construction
Management
services results from
a negotiation
between the Owner
and the OV\ as to
the proper level of
staffi ng for the
scope of services
.
.
.
CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA
.
.
.
The use of
standard forms
increases the
predictability of
project outcomes
and the consistency
of pricing
OWNER'S GUIDE
multiplier to cover all overhead costs and a separate lump sum as profit. The
Owner should recognize that payment of the fee should be related to time,
progress or other factors.
Fee as a Percent of Construction Cost
This form of compensation iJ; not recommended as it iJ; arbitrary and not related
to the effort that may be required. For example, a greater effort may be required
for a smaller dollar value project due to technical complexity or schedule com-
pression.
Standard Contract Forms
A number of organizations publish contract forms related to the design and
construction industry. CMAA provides a number of model forms of agreement
specific to the implementation of construction management services for use by
CMs and Owners:
. CMAA Document A-I Standard Form of Agreement Between Owner and
Construction Manager (for Agency); or
. CMAA Document GMP-I Standard Form of Agreement Between Owner
and Construction Manager (where a Guaranteed Maximum Price will be
provided).
Other published standard forms compatible with these CM agreements are:
. CMAA Document A-2 Standard Form of Contract Between Owner and
Contractor
. CMAA Document A-3 General Conditions of the Construction Contract;
Owner-Contractor Contract
. CMAA Document A-4 Standard Form of Agreement Between Owner and
Designer
. CMAA Document GMP-2 Standard Form of Contract Between Construc-
tion Manager and Contractor
. CMAA Document GMP-3 General Conditions of the Construction Contract;
Construction Manager-Contractor Contract
The advantages of CMAA standard forms of agreement are:
. They provide the most detailed specification of the duties of the CM.
. The Owner-CM agreement iJ; fully integrated with the Owner-Designer,
General Conditions and Owner/CM-Contractor agreements.
Use of standard forms increases the predictability of project outcomes,
increases the consistency of pricing, and simplifies management. The forms are
regularly updated and,maintained consistent with the industry practice. Stan-
dard forms may be modified as required by the project or the Owner's needs, but
such modifications should be undertaken only with the advice of an attorney
knowledgeable of the forms and the implications of changes to them.
15
eM"" PublicaNons
.
R dditional information on construction management such as services provided,
definitions, and procedures may be obtained from CMAA. Following is a list of
pertinent available publications:
. Construction Management Standards of Practice
. Contract Administration Procedures
. Time Management Procedures
. Quality Management Guidelines
. Cost Management Procedures
.
.