Loading...
HomeMy WebLinkAboutCC AG PKT 2009-01-26 #QAGENDA STAFF REPORT DATE: January 26, 2009 TO: Honorable Mayor and City Council THRU: David Carmany, City Manager FROM: Vince Mastrosimone, Director of Public Works SUBJECT: PIER SAFETY ASSESSMENT INSPECTION REPORT - RECEIVEAND FILE SUMMARY OF REQUEST: The proposed City Council action will receive and file the Structural Safety Assessment Inspection of the Seal Beach Municipal Pier CIP No. BP0904. BACKGROUND: The Seal Beach Municipal Pier is approximately 1800-feet long consisting mostly of poly-wrapped timber piles, timber support members and a timber deck. The Pier was severely damaged by the winter storms in 1982/1983 and it was partially rebuilt after the damage. The pier also experienced significant fire damage in 1992 and 1994 that required extensive repairs. In April 2008, the Pier suffered damage to the boat launch due to high surf which was later repaired. Regular monitoring and inspections of the structural safety of the pier is needed approximately every five years. Lifeguards and Public Works crews have regularly inspected and monitored various components of the Pier. The fender piles, which are the outermost piles adjacent to the boat ramps were professionally inspected and evaluated by a consultant in 1993. The concrete portion of the pier was professionally inspected and evaluated by a consultant in 1999. In 2003, Han-Padron Associates inspected and evaluated the Pier and provided the Ciry with a detailed assessment of the Pier's condition. Overall, the Pier was in fair condition. On October 13, 2008, Council awarded a professional services contract to Moffatt & Nichol to inspect and evaluate the City's timber Pier. Inspections and testing were conducted in November of 2008. The inspection included a visual and tactile examination of all accessible components of the structure, above and below the waterline. The report concludes that the Pier is in Agenda Item Q Page 2 fair condition according to the standards set by the American Society of Civil Engineers (ASCE) Standard Practice Manual on Underwater Investigations. However, at this time, several elements of the pier are in need of repair and replacement including minor structural components, utilities connections, preservation components and aesthetic features, Several significant findings identified in the report include repairing the wraps to avoid infestation of marine borers, repair broken bracing to provide full lateral capacity, and termite treatment. Several significantly damaged railings should be replaced with treated lumber. Loose utilities should be reattached, even if the element is no longer operational. Loose, uneven, or gapping deck boards should be repaired. The Public Works Department will be reviewing the associated costs and studies, investigate grant opportunities and will bring back information regarding the Pier improvements to City Council for consideration at a future meeting during the budget sessions. FINANCIAL IMPACT: The cost of the inspection report is $61,300 and was budgeted for in the City's 2008/2009 Budget. The report identifies approximately $230,000 of improvements to the pier which will be programmed in the 5 year Capital Improvement Program. RECOMMENDATION: It is recommended that City Council action receive and file the presented information on the Pier. U MITTED B NOTED AND APPROVED: ~'~~a Vi a Mastrosimone David Carma y, City Manager Director of Public Works Attachments: A. Pier Safety Assessment Inspection Report STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 STRUCTURAL SAFETY ASSESSMENT INSPECTION OF THE SEAL BEACH MUNICIPAL PIER CIP No. BP0904 November 20, 2008 Prepared for: ~ seat ~~ THE CITY OF SEAL BEACH 211 EIGHT STREET SEAL BEACH, CA 90740 by: ®®~ MOFFATT & 1VICHOL 3780 Kilroy Airport Way, Suite 600 Long Beach, CA, 90806 M&N JN: 3874-24 1 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 TABLE OF CONTENTS Paae No. 1 EXECUTIVE SUMMARY ............................................................................... 3 2 INTRODUCTION ........................................................................................... 4 3 FACILITY DESCRIPTION ............................................................... ............... 5 3.1 LOCATION .................................................................................... ...............5 3.2 EXISTING PIER .......................................................................... 5 .. ............... 4 INSPECTION ................................................... 6 ............................... ............... 4.1 OBSERVED CONDITIONS ........................................................... ............... 7 4.1.1 Topside Inspection -Deck Area .......................................... ............... 7 4.1.2 Substructure Inspection ...................................................... ...............8 4.1.3 Pile Inspection ............................................ 9 ........................ ............... 4.1.4 Utilities ................................................................................ ............... 9 4.2 COMPARISON OF PREVIOUS INSPECTION RESULTS ............ ............. 13 4.3 Structural Condition Assessment .................................................. ............. 13 4.4 RECOMMENDATIONS ................................................................. .............15 5 STRUCTURAL CAPACITY RATING ............................................... ............ 16 Appendix A -Plans and Sections .......................................................... .............. 1 Appendix B -Photographs ...................................................................... .............. 2 Appendix C -Inspection Data .............................................................................. 3 Appendix D -Inspection Procedures ..................................................... .............. 4 Above-Water Inspection -Topside ................................................. ..............4 Above-Water Inspection -Underside ............................................................ 4 Underwater Inspection .................................. 5 .................................. .............. Appendix E -Cost Estimates Summary .................................................. .............. 6 Appendix F -List of Key Personnel ........................................................ .............. 7 Appendix G -References ...................................................................... .............. 7 2 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PEER 2008 1 EXECUTIVE SUMMARY As part of the City of Seal Beach's Pier Inspection Program, Moffatt & Nichol performed a routine structural safety inspection of the Pier between October 17 -October 20, 2008. The inspection and this subsequent report were based on the recommendations of the American Society of Civil Engineers (ASCE) Underwater Investigations Standard Practice Manual (No. 101) and included a visual and tactile examination of all accessible components of the structure, above and below the waterline. The Pier is a timber framed structure typically supported on wrapped timber piles. The majority of the structure is approximately 25-years old, with the exception of the first 400 feet, generally over the beach, and end platform. Various repairs have been made to the structure over its lifetime. The most recent prior inspection was performed in 2002. Repairs were made as a result of that inspection, which appear to have been all completed. Several of the issues identified in the prior inspection are similar to this 2008 inspection. The Pier is assessed to be in Fair to Satisfactory condition with some minor to moderate deterioration in structural elements. Several concerns which should be addressed include repairs to approximately a dozen pile wraps and treatment of railings and benches infested with termites. Other priority repairs include replacement of broken bracing and attachment of loose utilities. These repairs are estimated at $200,000 to complete. Other repairs are recommended to be completed within the next five years including replacement of the non-critical termite damaged rails and benches, replacement of corroded connection hardware, and rehabilitation/repairs of elements noted as marginal in the inspection report. Inspection of the buildings was not part of the Scope, but should be considered as termite damage was observed. 3 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 2 INTRODUCTION This report was prepared as part of the City of Seal Beach Routine Inspection Program. This report provides inspection results, structural analysis, repair recommendations, and estimates of repair costs for waterfront facilities. All of these services, including this report, were provided by Moffatt & Nichol, under the responsible charge of Elizabeth Greer P.E., in accordance with The City CIP No. BP0904. The inspection was performed from October 16 through October 20, 2008. The scope included visual and tactile inspection of the top side, underside, and undewwater elements of the Municipal Pier This project provided the engineering services necessary to perform a routine inspection and to assess the apparent general condition of the structural members of the Seal Beach Pier in accordance with the standards set by the American Society of Civil Engineers (ASCE) Underwater Investigations Standard Practice Manual (No. 101). "The repair recommendations contained herein are preliminary and are to be used for general costing purposes. A design level inspection may be warranted if more accurate quantities are required. The actual method of repair must be left to the discretion of the Engineer of Record." In accordance with ASCE Underwater Investigations Standard Practice Manual the objectives of a routine inspection include: • Assessing the overall condition of the [undenroater] portions of the structure • Assigning an [underwater] condition assessment rating Developing recommendations for follow-up action • Determining the recommended interval to the next routine inspection The above water inspection was conducted using a similar approach. 4 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 3 FACILITY DESCRIPTION 3.1 LOCATION 3.2 EXISTING PIER The Seal Beach Municipal Pier, originally constructed in 1906, is approximately 1800-feet long making it one of the longest on the coast (4). It consists mostly of polyethylene-wrapped timber piles, timber support members and a timber deck. The Fender piles are the outermost piles adjacent to the boat ramps. There is a concrete approach structure at the entrance. The Pier weathered both the '33 earthquake and the '39 hurricane undamaged (4); however; it was severely damaged by the winter storms in 1982/1983 and was partially rebuilt after the damage. The pier also experienced two significant fires in 1992 and 1994. Repairs made to these areas included replacement of a significant portion of the deck and several elements of the substructure. Figure 1 in Appendix A provides a plan and elevation of the overall structure. Currently, the City is performing a deck replacement program. This included replacement of the older Douglas Fir (DF) decking with a more durable hardwood, Greenheart. The replacement is being completed in phases based on need and funding availability. To date, the decking has been replaced from the beginning of the Pier to approximately Bent 37. 5 Imaoe No. 1- Pier Arial Maa STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 The Pier deck is typically a 20' wide structure, supported on four piles: two vertical and two outside battered. There are several platform areas at which the pier widens to 30'. These are typically supported by five piles per bent. Most of the bents have some type of transverse bracing (typically 4x10), and longitudinal bracing at approximately every other span. Photo A shows a typical pier area. The superstructure consists of timber decking and stringers supported by pile bents generally spaced at 20 feet on centers. The piles are approximately 16" in diameter. Most of the piles, Bents 20-75, were replaced after the 1983 storm damage repair. A total of 83 bents and approximately 414 piles make up the substructure. Figure 2 in Appendix A provides detail of the pile bents. The City periodically performs assessment inspections, and the Lifeguards and Public Works crews regularly inspect and monitor various components of the Pier. 4 INSPECTION The inspection was performed by a team of six engineer inspectors including three engineer divers. Appendix G provides a list of the inspection team. Inspection generally included visual, tactile and limited probing on the pier structural elements and appurtenances. Buildings were not included in the inspection; however, some notes are included in the inspection summary. 6 Photo A - Tvoical Pier Area STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix E -Inspection Procedures provides a detailed description of the methods implemented. The results of the inspections were documented and summarized in table format. This is included in Appendix C -Inspection Data. Figures 3 through 5 in Appendix A show the location of ident~ed concerns. 4.1 OBSERVED CONDITIONS 4.1.1 Topside Inspection -Deck Area Photo B -Deck Wear Handrails -There are some loose rails and loose/damaged posts. There is a significant amount of termite damage that appears active at several locations along the pier. The worst termite infestation is at the end of the pier. • Appurtenances -Several benches have termite damage. The worst case being the far south facing bench. Boat Landings -The gangways appeared structurally in fair condition. Lifts were not operated as part of the inspection; however, operation of the gangway on Boat Landing Number 1 was observed during a routine landing. • Other Structures -The buildings were not specifically included in the inspection; however signs of termites were identifies in several end 7 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 buildings and the life guard tower. Potential dry rot and some exposed rebar was also observed at the Ruby's Dinner. 4.1.2 Substructure Inspection The substructure was inspected by boat at a relatively high tide (+6.0), by free divers (in the surf zone), and by land. The results are summarized below: • Stringers - No noticeable damage to the stringers was recorded. Several of the stringers were replaced as part of the recently completed deck replacement, Phase 1. • Pile Caps -Prior inspection (HPA 2002) noted "the pile caps exhibited some light to moderate checking". This is consistent with M8~N findings; however, no additional concerns were noted. Pile caps are often subject to dry rot; however, this is often difficult to identify by observation alone. It is recommended that when decking replacement is performed, cores be taken at a random interval or where any concems, such as dark stains or "fuzz", are observed. Cross Bracing -Most cross bracing was in satisfactory condition. A few braces are marginal and should be replaced as construction allows. There is one location in the surf zone with broken longitudinal braces. • Connecting Hardware -Several of the connections show signs of wear and rust. This is most. pronounced in the surf zone. Photo C shows an example of a cross bracing bolt with significant corrosion. • Boat Landings -The tops of several fender and guide piles have signs of dry rot. Two guide piles at Boat Landing No. 1 have had a sealant material applied to the top of the pile. The top of these piles, below the 8 Photo C -Corroded Bolts STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 seal, has lost the majority of its section apparently from dry-rot. This is consistent with the findings of the previous report. These piles were drilled to determine the extent of the rot. The most northerly pile was observed to have extensive core damage; however, the exterior is still relatively sound. The metal guide plates were in fair condition, with minor chaffing. The most northerly plate on Landing No. 1 has some chaffing damage as well. 4.7.3 Pier Pile Inspection The piles in the dry were inspected from the beach. Ocean piles were inspected by scuba divers supported by a boat crew. The diving conditions were generally favorable. Most diving was performed a relatively high tide (+6.0) with surf zone piles being inspected from the shore at a low tide (+0.0). The results are summarized below: • Underwater Pier Piles -The timber piles in the tide zone have a protective wrap of polyethylene which generally extends to a few feet above the high tide line (Elev. 9.0 to 11.0). The piles are in serviceable condition and without indications of loss of capacity. However, damaged, loose, missing or short wraps were observed in approximately a dozen piles. • Shoreward Piles -Shoreward piles were in generally satisfactory to good condition. There is one pile at Bent 15 that is questionable. It appears the City has also had concerns on this pile and had placed red ribbon around it. There is evidence of prior coring on this pile. Another identified concern is a short pile wrap in a potential surf zone (Bent 24). It is noted that the inspection was completed in early fall, prior to winter sand erosion. Elevation from top of deck to beach at Bent 24 is 21'-6" 4.1.4 Utilities The utilities are predominately supported under the deck in the utility corridor on the north side of the Pier. Their general condition was assessed by visual inspection. No testing of any of the utilities was performed. 9 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 • Fire Water -Fire water is supplied to the pier by a 6-in. steel pipe with services to stand pipes along the pier. Overall, the pipe itself is in fair shape, but moderate to significant corrosion exists at many points, with the worst conditions being observed in the surf zone and shoreward. The backflow preventer/fire riser at Bent 1 exhibits light to moderate corrosion (see Photo D). Downstream of the riser, the pipe is concealed by planking, with cutaways at low points in the pipe where there would otherwise be interference with the planks At these locations where it is possible to see the flanged joints, significant corrosion is visible (see Photo E, Bent 14 between grid lines G & I). Further downstream, the planking ends and the line are easily seen. Again, the piping itself appears to be in fair condition for the most part, but moderate to significant corrosion exists at or near the flanged joints (see Photos F and G). 10 Photo D -Backflow Preventer Photo E -Flange Photo G -Flanoe Con'osion Photo F -Flanoe Corrosion STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Piping supports for the 6" fire water line show moderate corrosion in most cases (see Photo G, and there is evidence of repairs to the line, assumed to have been made after the Domestic Water -Domestic water is supplied by a 2" PVC line. appears to be in good condition, with light corrosion observed at The line some hangers and supports. At the fish cleaning sink at Bent 62, the 3/4" combination ' galvanized steel/PVC water line to the sink is unsupported (see Photo J). • Sewage - A 4" PVC line provides for wastewater discharge. The line appears to be in good condition, with light corrosion observed at some hangers and supports. • Power/Communication -Electrical and service conduits are located in the pier including a 4" PVC power distribution line. Several electrical conduits and loose lines were observed, predominately at the end of the Pier (see photos 10 & 14. What appears to be a broken light fixture is dangling from its cable between fender piles at Bent 78 under the southeast corner of 11 Photo J - Unsuoaorted Waterline STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 the old bait and tackle building (see Photo K). Light to medium corrosion was observed on hangers and supports. A loose support was observed between Bents 25 & 26 (see Photo L). ~r (~ P. • Gas - A steel gas line is located outside the pier, on the north face. It supported by uni-strut connections attached to the north edge girders. This facility was constructed in the late 1990's as part of the pier fire repairs. It is generally in good condition with the exception of a few locations where it has lost support, as in this location at Bent 21 (see Photo M). In some areas the wrapping is moderately worn and frayed (see Photo N at Bent 62). Photo N - Pioe Wrap • Lighting -Lighting fixtures on the topside of the pier appear to be in good ' condition. One of the caps on a power receptacle mounted on a light pole on the north side of the pier at Bent 76 was missing at the time of the inspection. 12 Photo L - Suoaort Photo K -Cable Photo M -Gas Lost Suooort STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 4.2 COMPARISON OF PREVIOUS INSPECTION RESULTS The plans developed in this previous inspection were used during this inspection for comparison. The follow (partial) list of repair recommendations is taken from the 2002 inspection: • replace the six broken stringers • encapsulate the bottom of Pile 42-J with concrete • repair broken cross braces repair leaking utility • replace damaged utility hangers • replace approximately five firewater line "Ts" replace approximately four waterline valves • repair pile wraps • deck and guard railing repairs • connecting hardware repair boat landing pile chafing plate repairs • installation of pile top caps termite treatment & replace damaged timber Through the results of this inspection, it appears virtually all of the major recommended repairs are shown in the 2002 report were completed. This ' includes bracing repairs and pile wrap repairs. Some 2002 identified items including rusted connections and railing repair may not have been addressed and may have progressed further. It should be noted the 2002 inspection report ident~ed several similar issues as identified by this inspection. While most of these were completed, it is likely these will be continuing issues that should be addressed during future inspections. 4.3 Structural Condition Assessment The Pier is assessed with a Fair to Satisfactory rating based on ASCE recommendations. This overall condition rating based on the observed conditions including the completion of the majority of repairs identified in the 2002 inspection report. This rating indicates the condition of the entire structure 13 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 and its ability to perform its intended function; not every element making up the structure may meet the requirements of the overall rating. The following table describes the criteria for determining ratings. TABLE 2-4 Routine Underwater Condition Assessment Ratings' ROUTINE CONDITION ASSESSMENT RATINGS Rating Description 6 Good No visible damage or minor damage is noted. Structural elements may show very minor deterioration, but no overstressing is observed. No repairs are required. 5 Limited minor to moderate defects or deterioration are observed, but no Satisfactory overstressing is observed. No repairs are required. 4 Fair All primary structural elements are sound, but minor to moderate defects or deterioration is observed. Localized areas of moderate to advanced deterioration may be present but do not significantly reduce the load-bearing capacity of the structure. Repairs are recommended, but the priority of the recommended repairs is low. 3 Poor Advanced deterioration or overstressing is observed on widespread portions of the structure but does not significantly reduce the load-bearing capacity of the structure. Repairs may need to be carried out with moderate urgency. 2 Serious Advanced deterioration, overstressing, or breakage may have significantly affected the load-bearing capacity of primary structural components. Local failures are possible and loading restrictions may be necessary. Repairs may need to be carried out on ahigh-priority basis with urgency. 1 Critical Very advanced deterioration, overstressing, or breakage has resulted in localized failure(s) of primary structural components. More widespread failures are possible or likely to occur, and load restrictions should be implemented as necessary. Repairs may need to be carried out on a very high priority basis with strong urgency. 'ASCE Underwater Investigations Standard Practice Manual 14 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 4.4 RECOMMENDATIONS Based on this inspection, the Seal Beach Pier has some concems that need to be addressed. Following is a summary of the recommended actions, listed by priorities. Several of these concerns are not critical and can be scheduled as future repairs. Immediate Repairs -Repairs that should be completed as soon as possible include repairs to'the wraps to avoid infestation of marine borers, broken bracing to provide full lateral capacity, and termite treatment. Several significantly damaged railings should be replaced with treated lumber. Loose utilities should be reattached, even if the element is no longer operational. Loose, uneven, or gapping deck boards should be repaired. Figures 6 and Figure 7 in the Appendix - A show concept repair details. Priority Repairs -Several repairs can be scheduled within the next five years as budgetary constraints allow. These include replacement of the non- critical termite damaged rails and benches, replacement of corroded connection hardware, and rehabilitation/repairs of elements noted as marginal in the inspection report. Some of these repairs may also be deferred to a later date is closely monitored. Additional Inspection -Inspection of the caps and stringers should be incorporated into the deck replacement program. This can be completed with an inspector working with the contractor's removal operations. In addition, inspection of the pier building should be performed. Future Pier Inspection - Assuming the recommended repairs are completed, a future inspection should be performed in approximately five years. This is consistent with the ASCE Standards of Practice which recommends a maximum interval of five years between underwater inspections for wrapped timber piles in an aggressive environment. It is recommended that future inspections are performed in the early spring, when sand erosion is greatest. 15 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 5 STRUCTURAL CAPACITY RATING Previous analysis by Moffatt & Nichol concluded the pier has the capacity to for H10 loading. (ASSTHO 20 kip vehicle with max rear axle load = 16 kips) This was approximately the same result estimated by HPA in the 2002 assessment report (Appendix E) which indicates an axle load capacity of 18.5 kips = H11.5. The deck upgrade under the current program provides a stiffer and stronger decking than the historic Douglas Fir decking; however, code distribution of loads would not be affected, hence the rating would be the same. Based on the inspection results, we do not believe any change in capacity rating is warranted and rating should be limited to H10 or equivalent vehicles. 16 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix A-Plans and Sections I ~ _._ __. _ . _ - I --- . __. _ PLAN 19 24 25 30 35 40 45 50 55 60 65 70 III ,~,/ 80 82 ~ i i ELEVATION Figure 1 NOTE: •NOVEMBER 13, 2006 100 0 100 200 -, 25' Figure 2 TYPICAL PIER SECTION ~Al 1/7'-1'-C TYPICAL SECTION AT PLATFORM AREAS /B1 T-- ~---r-- -rt----t --- -- --- --- -- - - G -- - --- - - -- --- -_- _--- --- ---- -_- -- -- - --- -- -- --- --- - - 1 ~ ____- CX~1 (M) MW YISSSYO OI SNM 12 13 14 15 16 17 18 19 xw~xa 21 2° 22 23 ~ 24 4 NMYIXNL POST IEO flAp X.IMIIAI POST w 9LT Ym 9PIli - - _ - - - - - C 6 C ~_ - - - _ - - ~~ - G~ - - - --~--- --~-- _.--.~-_-i ~ - - E E __ - -_~ _ -_ +~4 ! ~ ~- -- -- -- --- _ _ _ _ _ _ _ - - -- _ _ _ -- --- - _ _ _ _ -- c H _ _ c -_ - _ Y ~ 1 i _ _ __ _ i 11lE CORY09OI1 `YMONK i1MF LEGEND: 4 Q Brakan a4Ngar T lada8m wlw 6mnagN crm Woe• v mbeing • PO• Cancem Q PO• wop domoged n mleeing 4 FFe IN• Cwroalm 0 LavN II NryPelNn ParhXmad 4 prli hoard O Low dedun9 D FdIN ewMN soppcrt g Nand raY eanneellon / Photo NumEer Figure 3 ~' - °' 2" '°' SCALC: 1"=20~ WOID 9adQ Blip¢X -T_-_T_-_T_-_~-_T_~_-_T_-_T-_7-_-~_-_T__T_!?__T-_- Figure 4 LEGEND. Q Brekan elrnya T ledolbn vdr. Oamog.d avv brace a mledng • Pil. Canc.m Q PII..rap damaged a ma.Fg p Fk. Iln. CaraNm 0 L.vA 1 N.p.ellan PerlarmM 4 O.d~ board O l...e elacklny n Faled candurt .appal g Xond roY cann.cllon 1 Plwla Nun$.r 20' 0' 20' 10' s~~~: ,~~=ZO' BOl1T IANDIND N0.1 60 ~___~_~ MY pOT (YNDID r--_-r---i- 1. M Figure 5 LEGEND: Q Brakvn vlrNgr J Ivdelbn rdve Damaged ciao brae r mlealn9 • Pdv Cacrn Q Ple wop damopad r mlannp 4 ikv Ihv Corroela 0 LM II Fvpvclla prlamad 4 Deck bmtl O Leee Notldnp D Folad anduli vupprl 2U' lP 20~ ~D' g hand rel eonneclia i Phole Numbr ~I ~IDDII pEIX Ylglp XNL ~ ~ I I L1Rl~PPMipE M.Tf110XE ~ TDiYNE DINAfE /]2 1{141f M¢ MM p 1V T a1a Al aC W R+*1 ¢ao ¢ao ® ® xio pploie xla auao RTpI RTA nus ® ¢ua IY 9RT YY B¢T In*I lTM Y- r e•-Ir I - r r-lo Ip' I r-lo I/!' I v-w IR' r-lo In' C E G I B D F H J TRANSVERSE CROSS BRACING DETAIL 1 TRANSVERSE CRO33 BRACING DETAIL 2 IA'•1'-C 1/r-1'-C ¢+ao wo RAYa¢ aAaR iM m 6 pal Qg1Y paa aFI 6 +a! 6+Ip0 WYTflZ aeaa ITP1 p /~ C _--o C~F.~ ~~ ~ C W{ / ~ SE/IL EAOI PFR RgI11RE RFA rISPEf.'110N '~ OCTOBER S00! ~~ •' , .. "' ,~ MOFFATTAMCHOL REPAIR OETAL9 NO 1 Figure 6 LONGITUDINAL CROSS BRACING 3 1O1°~~.~7w c.~s 1°®° "'° ° ~"~°d,~v~ ~° "+-'+ -- ale'-Y-O• ~.. A lue~ x. rauRE e ' _ . . a ,xae !!! [ MMil1 Y! OIIIiM ILLI[111M{( I ,x~1 !u r uwn u ~ 1 a f r IWGMWL. YIM • LxIMIMMI xM W Ml !x[I PLLIEMIIOE KI IA•. l1T IIR1 I OIGYIFIOIYIL XYItl . I / f0lDliroE ~ NIIMY Iw! • ~ - 6110 YW ~~ -~r. , a M ]I. Q BMO ~ .1 ,• MMNY xM. L Y.T.IL•/_!' IMM • ieW om InM - Glr K Mi o roar i L scar lr rr~ as YJy I¢W MK IMi L e G ®! 6lmr w[ ua¢r m s i 01xL IMM.to Ml I Ir ImxM! wow YR.Wm I !YY YM~ Y$' e611NFYlYE 10.11 1. sa YML ee l1.1® T ~1w11M1 Y u not L Y.Y . 1!-Y Mx uxcw NL OIG:S IILI !M6 m •f Iµrt01LO e.11M~ M IMY SF4 EIIFMI I !!C NM IGEY IIO I e[I!@I LOlao Ll - OH16M! Gx!!CI MM b1Y SECTION A rr• ro!r • r-Y m wlxxu aLr xYS I 1 1ry•-1•-s aim wna11 IMI - I r• MYiYY I F ~ -_ ~_ Y.1!• auwrz wrzwn Mo 1 b - k•. Mxr IrR) elMUU lrlm Y! axn xY eml melMa -_ __ _ ~'~ I eMle11 I I i 0 4 r I o ~ ~~ I 1y 11 rm o O~ii ms: oMn w t le-r wxux 1 YI OIx o PILE WMP DETAIL 7 IAA-ea e W W DRAIL DETAIL r-re 1 Crfl .~ ~enQ~eccQ, ~ ~ _~~~ ~ ROYIINE PRII NeiPEC11011 1 OCIOfiFIf 400! +t 1 ®® MORRATT&MCIIOL uYMn cerMLa xo! py •1 1 I U ~G / ~ e~ i¢. iu m ! i°° air-x. '1 n, , rim Muunei _ , ,,, _ ~ ... i . i STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix B -Photographs Y V d C V O a Y Q L a Y U d C O 3 v 0 L a N a V d C Y u v D C W a 0 .. 0 r a N a z m d c Y u d 0 C W d i a 0 0 L a N V .~ Y N a c _c N d f0 n .~. O L a Y u v 0 C O 3 Y L d a N Y u v O d z .~ n 0 L d ~+ a Y u d D LL 0 N a Y O L d ~Q_ ra uo~ ~~e ~~ ~~ ~°~ ~-~-GAL---- -~~: ~ =~: ~ ~ ~a~ ~o m E m 0 v Y_ E L d Y 3 L V C m L Y 0 fn m 0 O L d a m m E m D m Y ~~ d L 3 z U c m m r r N N T a~+ t a v m m E d E L L a+ ~3 L u C d m L Y H I en O r O L a v m m E m 0 v E L d F L Y 3 L u c m m L Y 7 N V M Y 0 t a ~~~~ ~ ~ ~ a ~°~ ~~'~ a m E m 0 m ~.. E 9 C N C r LL M Y t d Y d 0 a m Y 0 «~. O L a .~ z rn M y L a .~ C .~ m 10 E m 0 m .. .~ L d m air O L a N T L 7 C Y f~ E .` v N f0 LO a 0 O L a r u c m m v° Y 0 t a d tl0 R E f0 0 d Y E v ~"~ b ui a~+ O L a .~ z t v c m m I m y O r a Y N d N ~O Y Q t a .~ v c m x t a v Y l0 e'I Q ~.. m C_ C f~ J Of Y L a v m C7 0 z v c m J M r a ~, ~, ~ ~ y ~ ~~~~ a N .~ Q Q L d a.+ d N .~ m ate. 0 L a a .~ z a 0 r a y a N G Y L a r' 1i h ~: ~~ ,4 l . ~ j`'~ e.; :\ y . N d .~ ~. n ate. Q t a a+ N d fh n O 0 L d .q L N n r t d o- i ~ C• ! - ~ ~ a ~ N i+ LL N r N 7 M a Y L a N V m C .` d L L A L U .ti ~V V t a d V N m C d Y O m I ~+ O L a N C 0 Y d C C V d Y N 7 OC I rn a Y Q L a u m m c Y O to 0 a~+ 0 L a v v m L m C d Y O V CO O1 Y Q L a ~~ v ~r,A i m C Y m N 0 0 .. 0 r a d u A L m d Y V [O ei Y O L a .Q ~ ~~ O. I ~EY ` ~JI~fW° ~JISUl:fl.~L~~ :a ° ~ ~ ~ ~ 'a ' ~ o. N i+ 0 m v N Y Q L a d u A m 3 m Z O O O L a m 'u m V LG 'O d u m n d 0 Y L a N 6/ O [L 'O m N 7 C O y O t a o- ~ ~ O ` i j~ m Y u 0 m m N 0 J a~+ O L a m u m m 3 d 2 O Y t d N N O O L a Y L a a ~ a ~IX Cllx.tL:.IC~J~5V l.:~R.5W17 ~ E ~ B ~ ®~ ` + 0; v d .~ a v z a m c .` Y N a v m m a m s d m c .` .. N W a~. 0 L a 00 C Y u O iO io C .~ 10 O ate. O L a C Y u 0 m N 0 0 J N .~ a ~~ N Y 0 m d V N 7 C M 01 a Y 0 t a N d 00 C .` Y H d L L _~ U ti a .~. O t 4 d V f0 V m C a Y O fL a 0 0 L a N C O i:+ u N C C d N 7 2' I rn a a~+ O L a 00. ~ ! ~ : ~ o- d u m m c Y O O7 O O L a v m m c m Y t0 rn a 0 t a V 3 ~ f0 C Y O fn I N 0 0 Y Q t a W u m m` c d Y O m I .i Y r a o• `~` :E; ~ e N Y m v d Y N 7 C O O O L a w V 10 m 3 a~ Z O N O O t a m "u 10 L m a m u 10 a d C O N a~• O L a N V m m i+ N 7 K I O a~+ 0 z a t.:J~v.n.f 'C. lm ~ a m Y u O fG W N s N O O O t a a u m m 3 v a 0 0 0 t a N ~~-. O L a V L a .a- IQ ~ a .~ a L d 00 C .~ a+ a0 ate. O L d V d .~ d d K d Oq C .` a+ H O O L d 00 C Y u 0 m m c .~ m 0 .~. 0 L d C Y V O fL d N O O J „i O1 O a+ O L d ^ fi~ i +y'05Y 6 _ ~ ~~ ~~~ a .. 3 m v c a m 3 m 0 0 J ~D Y 0 L a a m 3 v N J M N O O L a a m 3 d N Q s L d L 3 0 C7 v C .~ n C 0 .. 0 L a v m m m d a Y L a 0 z a v 'a a M L a a v a c m d U n C Y t d t Y 3 0 L l9 v c .y m v N 0 L a d 'a d C io L U a 0 .. 0 r a v a v w c m v u i a°a a M Q L a Y C m F J N N y O L a v a u 0 a 0 r a on c Y V d 3 v c m m a 'a a v .~. 0 L a Y N a J L d ++ 3 0 0 L a v a 'a a a a a c to O 0 L a N d 3 d N J ate. O L a m N 0 J d Q 'a a w c 0 Q M t a yN 0 a a N d a 'a N ~-/ w O L a a 3 d N 0 J r a ~~ ~. .e ~ i ,. Fc L`t~L'1 N Ol L 3 v N 0 J N .~ O d N d V 3 d N 0 v 0 «. 0 r a N L 3 m N O m 0 Y L a W u L 00 J d N 0 J n N Y 0 L a w a 'a v c m Y 0 L a I _~ • . ~~~a ~°~ ~ ~~ ~~ N C 0 V u v c c a U N d 7 f0 N Q. a «. 0 r a N C O Y u v c c a u N v 7 f~ L d N_ N Q r O t a .~ d Y f0 3 m 0 a a N C N N N L a C 'a+ u a c c 0 U N f0 L d N_ 0 N O Y L d ema ~ Y ~~~ d a 'a v v Y N N Y L a L a a N a N a~+ L a v a 'a v C 10 H O Q L a v m c 0 v _~ 0 N a N 7 G N M O L a '+Oi n~L7VJL7 d a .a c c m .. H O y O L a w a .a v c m M H V 0 t a v a 'a f0 H Y O L a w u N a~+ m LL n N L a d N O O J N .~ C 'a a m 3 N N Q L a V V~VYJ~ ~'Q~~ Y~ ti } E k0. r: ~ ` Lam' ''-~L'e ~ - ®_ .: •p~ :.~.::a d 0 .. L N a~+ 7 a m ao n 0 L a m m O .. 7 t N O Y Q N n 0 t a d u 2 d N v r m 3 v I b n O L a a LL N W N 0 L a m u .2 W H L d N 3 d LL 0 Y+ 0 L a v M C W a 3 0 Y u m m n 0 L a w m c m LL lD Y t a v a a c m Y N O a+ O L a m a a v m 0 a a c N O L a N ++ O d a w a a m 0 +r O L a d d .a C m Y H fh 0 Y L a 0~0 C m LL 00 00 a 41 t a w a a v c m n O L a d m C 10 LL v v r N 7 C V1 01 O Y L a Y N O J Q a a N A rn Y L d N C O 'a+ u d c c O U 01 O M t a N C O .y u d c c u° ~D Y d STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix C -Inspection Data Seal Beach Pier Inspection Summary October 2008 Location Issue Recommendation Comment Bent 1 Span 1 Deck 1 Misc 1 Bent 2 Span 2 Deck 2 Misc 2 Bent 3 Span 3 Previous damage to stringers from below OK Deck 3 Misc 3 Bent 4 Span 4 Deck 4 Misc 4 Bent 5 S an 5 Deck 5 Misc 5 Bent 6 S an 6 Previous damage to stringers from below (Repaired) OK Deck 6 Misc 6 Bent 7 S an 7 Deck 7 Misc 7 Bent 8 S an 8 Deck 8 Misc 8 Bent 9 S an 9 Deck 9 Misc 9 Bent 10 San 10 Deck 10 Misc 10 Bent 11 San 11 Deck 11 Misc 11 Bent 12 San 12 Deck 12 Misc 12 Bent 13 S n 13 Deck 13 Misc 13 Bent 14 Inspactlon Summary-Finalxls 1 Of 8 Seal Beach Pier Inspection Summary October 2008 Location Issue Recommendation Comment Span 14 Partial Split in Rail Post Monitor. Replace at next o portuni M Deck 14 Misc 14 Bent 15 Marginal Transverse Brace Re lace at next o portuni R2 ent 15 Span 15 Deck 15 Pile 15C appears marginal. South side appear to have dry rot. There is evidence of previous cores. Missin Nails on Center Raii iscuss core findin s with Ci Add nails 2 R1 Misc 15 Bent 16 San 16 Deck 16 Misc 16 Bent 17 San 17 Deck 17 Misc 17 Bent 18 San 18 Loose Blockin Toenail in R1 Deck 18 Misc 18 Bent 19 San 19 Deck 19 Misc 19 _ Bent 20 San 20 Loose Gas line. Reconnect to su orts R1 Deck 20 Misc 20 Bent 21 Span 21 Ma final two span brace. Re lace at next o portunit R2 Deck 21 Misc 21 Bent 22 Span 22 Deck 22 Misc 22 Bent 23 San 23 Deck 23 Misc 23 Bent 24 Pile 24B -Wrap is short appears below hi h waterline Extend Wra R1 San 24 Deck 24 Misc 24 Bent 24a Piles E & G -Missing nails in wra Add nails R1 Span 24a Deck 24a Misc 24a Loose bottom rail north side Renail R1 Inspection Summery-Finel.xla 2 of g Seal Beach Pier Inspection Summary October 2008 Location Issue Recommendation Comment Bent 25 Pile 25 C Wrap missing at cross brace Extend Wrap R1 San 25 Deck 25 Deck Boards checkin !s lit Monitor. Replace at next op ortuni M Misc 25 Bent 26 San 26 Deck 26 Misc 26 Bent 27 Span 27 Deck 27 Misc 27 Bent 28 Bent 28 Bents 28-38 Corrosion on Bolts (Onion) Monitor. Repair at op ortuni R2/M Span 28 Deck 28 Slit Board Sand/fill if needed R1 Misc 28 Bent 29 Bents 28-38 Corrosion on Bolts (Onion) Monitor. Re air at opportuni R2/M Span 29 Deck 29 Misc 29 Bent 30 Bents 28-38 Corrosion on Bolts (Onion) Monitor. Repair at o portuni R2/M Span 30 Deck 30 Misc 30 North Rail 30-33 Termites Treat R1 Bent 31 Bents 28-38 Corosion on Bolts (Onion) Monitor. Re air at o porluni RZ/M S an 31 Deck 31 Misc 31 North Rail 30-33 Termites Treat Ri Bent 32 Bents 28-38 Corrosion on Bolts (Onion) Monitor. Repair at op rtuni R2/M Span 32 Deck 32 Misc 32 North Rail 30-33 Termites Treat R1 Bent 33 Bents 28-38 Corrosion on Bolts Onion Monitor. Repair at o ortuni R2/M S an 33 Deck 33 Misc 33 North Rail 30-33 Termites Treat R1 Bent 34 Bents 28-38 Corosion on Bolts Onion) Monitor. Repair at o ortuni R2/M Span 34 Deck 34 Misc 34 Bent 35 Bents 28-38 Corrosion on Bolts (Onion) Monitor. Re air at opportuni R2/M S an 35 Inapeclion Summery-Finalxls 3 of 8 Seal Beach Pier Inspection Summary October 2008 Location Deck 35 Issue Recommendation Comment Misc 35 Bent 36 S an 36 Bents 28-38 Corroslon on Bolts (Onion) Broken Lon itudinal Brace Monitor. Repair at o portuni Replace R2/M R1 Deck 36 Misc 36 Bent 37 Span 37 Bents 28-38 Corrosion on Bolts (Onion) Monitor. Re air at o portuni R2/M Deck 37 Misc 37 Bent 38 Span 38 Bents 28-38 Corrosion on Bolts Onion) Monitor. Repair at opportuni R2/M Deck 38 Misc 38 Bent 39 Pile 39D -Top Wrap Lose above waterline Repair R1 Pile 39B -Top 18' of wrap missing Re lace/Re air R1 Span 39 Deck 39 Misc 39 Bent 40 San 40 Termites in Life uard tower Pertorm full inspection of building O Deck 40 Misc 40 Bent 41 San 41 Deck 41 Misc 41 Charred south rail Monitor M ent 42 Span 42 Previous - 2' crack in wrap42:8 -NOT OBSERVED NOBS) Deck 42 Misc 42 Bent 43 S n 43 Deck 43 Misc 43 Bent 44 San 44 Deck 44 Misc 44 Charted south rail Monitor M Bent 45 Pile 45E Missin Wre Re lace/Repair R1 San 45 Deck 45 Misc 45 Inspectlon Summery-Final.xls 4 Of 6 Seal Beach Pier Inspection Summary October 2008 Location Issue Recommendation Comment ent 46 Previous Pile 46E Wrap start 1' above mudline (ML) NOBS S an 46 Deck 46 Misc 46 Isolation Valve Monitor M Bent 47 San 47 Deck 47 Misc 47 Bent 48 Span 48 Deck 48 Misc 48 Bent 49 Span 49 Deck 49 Misc 49 Bent 50 San 50 Deck 50 Misc 50 Bent 51 Pile 51E Damaged Wra Replace/Repair R1 S n 51 Deck 51 Misc 51 Bent 52 San 52 Deck 52 Misc 52 Bent 53 San 53 Deck 53 Misc 53 North Rail 30-33 Termites Treat R1 Bent 54 San 54 Deck 54 Misc 54 Bent 55 Pile 55E tom wrap above waterline R1 Bent 55 Blockin Slit? M S n 55 Deck 55 Loose deck boards over utilities Replaces ikes R1 Misc 55 Bent 56 Pile 56G -Loose Wra Re airwra R1 Span 56 Deck 56 Misc 56 Split in Rail Post Monitor. Replace at next opportuni M Bent 57 San 57 Deck 57 Mlsc 57 Bent 58 Inspection Summery-Fnal.xla 5 of 8 Seal Beach Pier Inspection Summary October 2008 Location Span 58 Issue Recommendation Comment Deck 58 Misc 58 Bent 59 San 59 Deck 59 Misc 59 Bent 60 Span 60 Deck 60 Misc 60 Bent 61 Plate at Fender Chaffed Monitor M S an 61 Deck 61 Misc 61 Bent 62 Span 62 Deck 62 Misc 62 Unsup orted Waterline Provide Support R1 Bent 63 Gangway Pile (north) dry rot undersea) Monitor extent of rot. M Wrap on furthest fender pile dams ed from ram Monitor M San 63 Deck 63 Misc 63 Bent 64 Gangway Pile (north) dry rot under seal Monitor extent of rot. M Span 64 Deck 64 Misc 64 Bent 65 San 65 Deck 65 Misc 65 Bent 66 S n 66 Deck 66 Misc 66 Bent 67 Span 67 Deck 67 Misc 67 Bent 68 San 68 Deck 68 Misc 68 Bent 69 Span 69 Deck 69 Misc 69 Bent 70 San 70 Deck 70 Inapechan Summery-Final.xla 6 of 8 Seal Beach Pier Inspection Summary October 2008 Location Issue Recommendation Comment Misc 70 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair damages. R1 Bent 71 San 71 Deck 71 Misc 71 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair dama es. R1 Bent 72 Discoloration at cap and stringer near ile 72E. Could bed rot. Suggest remove deck to check. Else monitor close) M Span 72 Deck 72 Misc 72 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair dama es. R1 Bent 73 Span 73 Deck 73 Misc 73 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair dama es. R1 Bent 74 San 74 Deck 74 Gap in Deck boards is about 1" at trensition Fill with board or other to narrow gap. R1 Misc 74 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair dama es. R1 Bent 75 San 75 Deck 75 Misc 75 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair dama es. R1 Bent 76 San 78 Deck 76 Several loose bcards Re air R1 Misc 76 Rece tacle is missin cover Re lace Cover R1 Bents 70-82 evidence of termite infestation in many locations of rail and benches. Treat all locations repair dama es. R1 Bent 77 Shoreward fender pile damaged wre Monitor M S an 77 Loose wires below deck Remove inactive or attached to ier. R1 No blockin Install blockin R2 Deck 77 Misc 77 Bent 78 Span 78 No blockin Install blockin R2 Active Water Leak Re it Deck 78 Varying deck levels at utility access Level out R1 InspeNon Summary-Finalxls 7 Of 8 Seal Beach Pier Inspection Summary October 2008 Location Issue Recommendation Comment Bents 70-82 evidence of termite infestation in many locations of Treat all locations repair Misc 78 rail and benches. damages. R1 Ruby's appears to have termite Perform full inspection of dama a and some d rot building O Bent 79 Remove inactive or attached to S an 79 Loose wires below deck pier. R1 Deck 79 Bents 70-82 evidence of termite infestation in many locations of Treat all locations repair Misc 79 rail and benches. dama es. R1 Bent 80 San 80 North Bracing S lit Re lace R1 Deck 80 Bents 70-82 evidence of termite infestation in many locations of Treat all locations repair Misc 80 rail and benches. damages. R1 Bent 81 Span 81 Loose and missing Blockin Toenail and re lace missin R1 Deck 81 Bents 70-82 evidence of termite infestation in many locations of Treat all locations repair Misc 81 rail and benches. dama es. R1 Fishing Platform Pile -Top dry Bent 82 rot M S an 82 Deck 82 Bents 70-82 evidence of termite infestation in many locations of Treat all locations repair Misc 82 rail and benches. dama es. R1 Inapecfion Summary-Fnaixls 8 of 8 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix D -Inspection Procedures The purpose of the Pier Evaluation Survey and Assessment was to determine the condition of the Pier and identify any needed restoration or potential improvements. This assessment included the inspection of all pier components, both above- and below-water, to develop information needed to prepare construction documents. A field Work Plan was prepared for each aspect of the site inspection based on available information and on Moffatt & Nichol's general inspection reporting standards. • Topside inspection included the pier decking, curbs, railings, and appurtenances. It is anticipated that the City building officials will conduct any necessary inspection of the building structures above the pier. Underside inspection included inspection of the stringers, caps, bracing, connections, concrete approach structures, piles above-water, utility housings and supports, recessed platforms, and floating facilities. • Underwater inspection included inspection of the submerged portion of the Pier including bracing and piles. Underwater inspection was done in accordance with the ASCE Standard Practice Manual for Underwater Investigations. Diving practices were regulated by the Moffatt & Nichol Diving Manual. Above-Water Inspection -Topside The topside inspection included inspections/observations of the entire length of the Pier. The topside inspection was performed on awalk-through reviewing structural elements, accessible facilities and utilities, including lighting. Buildings were not included in the Scope of Work; however, termite damage was observed in the buildings. Above-Water Inspection -Underside The above-water inspection involved all pier utilities, structural members and appurtenances. The underside inspection included structural components, appurtenances, and utilities below the deck. STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PEER 2008 The above-water inspection of the substructure was performed similar to a routine inspection in accordance with ASCE Standard Practice Manual for Underwater Investigations. Inspection was preformed from ground and water level from a boat at a relatively high tide (+6.0) for bents 41-82. Bents within the surf zone (29-41) were observed from the water by free divers. Shoreward Bents (1-29) were observed from land. The focus was on visible signs of deterioration or damage. If the team had found any areas of critical concern, the City would have been immediately contacted to discuss options for a more extensive inspection. However, no critical issues wen: observed. The inspection was documented with field notes and digital photography. Underwater Inspection Prior to mobilizing dive operations, the Dive Supervisor completed a Job Safety Analysis (JSA) in addition to technical preparation. The JSA assesses diving objectives/operations and the project's physical environment to determine potential hazards and mitigation measures. The underwater inspection was performed as a Routine Inspection (Condition Assessment) based on the ASCE's Underwater Investigations Standard Practice Manual. The underwater inspection was performed from the mudline to the high tide line and included the following three levels of effort: • Level I - On 100% of the piles. Visual and/or tactile examination of all surfaces, without removing marine growth. Tactile examination will provide an indication of the integrity of the exterior of the piles. • Level II - On 10% of the piles. Removal of marine growth at three levels (mudline, low tide zone, and mid-height), and detailed examination of the exposed substrate. For piles in less than 15-feet of water, only the mudline and low tide zone levels will be examined. Based on the generally favorable conditions observed, coring of the timber piles (Level II I effort) was not performed. STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix E -Cost Estimates Summary 2ooa Project: 3874-24 Seal Beach Pier Phase Inspec8on Pre aced B Greer/O'Donnell Date : 11/1512008 ITEM QUANTITY UNIT REM DESCRIPTION UNIT PRICE TOTAL COST 1 '3; LS 20000 $20,000.00 Mob/Demob 2 ~ 800 $0.00 Timber Strin ers Y 3 ~r 5$ SF 50 $2,500.00 Timber Deckin 4 8 E'0` 500 $3,000.00 Timber Cross Bracin 5 ~ 2000 $24,000.00 Re air Pile Wra 8 ~~ : LF furnish Pile (2 -Tentative) 30 $3,600.00 7 ~ ,,.2• EA Drive Pile (2 -Tentative) 5000 $10,000.00 Appurtenance Re air 8 -'.' A1: ~. ~ °4 LS 5000 $5,000.00 - - • Miscellaneous hardware 9 ~1.' LS 10000 $10,000.00 ,^if i.rs Termite Treatment `~ 10 LF 100 $30,000.00 ~ Re lace Handrail 11 ~ LF Re lace Bench 150 $15,000.00 12 !. ~ LS 5000 $5,000.00 Leakin Water line re air 13 LS 5000 $5,000.00 ~ U81i8es Re airs 14 LS 5000 $5,000.00 Misc re alr SUB-TOTAL $138,100.00 Contingencies 20% $27,820.00 Construction Management 10% $13,810.00 TOTAL $179,530.00 Inflation/Area Factors (5 years) 3% $28,594.47 Miscellaneous 10% $17,953.00 SUB-TOTAL $226,077.47 PROJECT TOTAL COST $230,000.00 STRUCTURAL SAFETY ASSESSMENT INSPECTION REPORT SEAL BEACH PIER 2008 Appendix F -List of Key Personnel Citv of Seal Beach David Spitz, Project Manager Tel: 562-431-2577 x1331 Moffatt & Nichol. Lon4 Beach Elizabeth Greer, PE, SE Tom Spencer, PE, SE James Crumpley, PE, SE Michael Breitenstein, PE Michael O'Donnell Julia Hornby, PE Off: 562-426-9551 Project Manager Principal in Charge Quality Control Dive Coordinator Cost Estimates Mechanical Engineer Moffatt & Nichol Inspection Team Rod Whitsel, PE Bob Sherwood, PE Rob Sloop, PE AJ Lee Elizabeth Greer, PE, SE Dan Martin Diver/Tender Diver/Tender/ Substructure Diver/Tender DiverlTender/Substructure Super/Substructure Super/Substructure/Utilities Appendix G -References ASCE (2001) ASCE Manuals and Reports on Engineering Practice No. 101. "Underwater Investigations Standard Practice Manual. 2. Don Hellmers Engineering (1983) "Seal Beach Municipal Pier Restoration" 3. Han-Padron Associates (Jan. 2003). "Condition Assessment Report of the Seal Beach Municipal Pier for the City of Seal Beach, CA. 4. Great Piers of Cal'dornia; Jean Fleming. Capra Press 1984.