HomeMy WebLinkAboutPC Res 03-25 - 2003-06-18
ORIGINAL
RESOLUTION NO. 03 - 25
A RESOLUTION OF THE PLANNING
COMMISSION OF THE CITY OF SEAL BEACH
RECOMMENDING TO THE CITY COUNCIL
APPROVAL OF GENERAL PLAN
AMENDMENT 03-2 (LAND USE, OPEN
SP ACE/RECREA TION/CONSERV ATION,
HOUSING AND CIRCULATION ELEMENTS -
, BOEING IINTEGRATED DEFENSE SYSTEMS
SPECIFIC PLAN)
THE PLANNING COMMISSION OF THE CITY OF SEAL BEACH DOES
HEREBY RESOLVE:
Section 1. Boeing Realty Corporation ("Applicant") has submitted
applications for general plan amendments, specific plan, zoning map amendment, vesting
tentative tract map and precise plan approvals for the Boeing Integrated Defense Systems
(BIDS) property (collectively "application") with the City of Seal Beach. The Applicant
seeks amendments to the General Plan to allow the implementation of the proposed BIDS
Specific Plan, dated December 2002, on the land described in "Exhibit A", attached hereto
and incorporated herein by this reference.
Section 2. Pursuant to 14 Calif. Code of Regs. ~ 15025(a) and ~~ ILC
and III of the City's Local CEQA Guidelines, staff prepared an Initial Study and a Draft
Environmental Impact Report, which was circulated for public review and comment from
December 27, 2002 to February 10, 2003, in compliance with the provisions of the
California Environmental Quality Act and the City's Local CEQA Guidelines. Upon
completion of the public review period, a Final Enviromnentallmpact Report was reviewed
by the Planning Commission at a public hearing held on May 21,2003.
Section 3. A duly noticed public hearing was held before the Planning
Commission on May 21,2003 and continued to June 4 and June 18, 2003, to consider the
applications. At the public hearing, Applicant's consultants and representatives, and several
other persons spoke in favor of the request. Persons also spoke in opposition to the requests,
on various grounds.
Section 4.
The record ofthe hearings indicates the following:
(a) Applicant seeks to establish the following uses as part of the BIDS
Specific Plan:
Z \My Oo(,umenls\RESO\GPA 03-2 (Boemg) PC Reso doc\LW\06-23-03
Planlllng CommISSIOn ResolutIOn Number 03-25
General Plan Amendment 03-2
Boel1lg Integrated Defense Systems Specific Plan
June 18, 2003
PROPOSED PROJECT LAND USES
Planning Area Size Proposed Use(s) Maximum Floor Area (Gross)
(acres)
,
1 41 Existing Boeing Space aud Communications 1,150,000 square feet
facilities. Allows for up to 345,000 square
feet of additional building area.
2 16 All or portions of the existing buildings to 345,000 square feet
remain and/or reused. New business park
uses would require relocation and/or
demolition of existing buildings and
facilities.
3 45 New business park uses. Portions of the 628,000 square feet
drainage ditches to be used for wetland
restoration and water quality treatment
purposes.
4 5 Business park, 120-room hotel, and 120-1'0001 (hotel)
conunercial (retail, restaurant and similar 32,500 square feet (commercial))
commercial uses).
(Alternate - 87,500 square feet-
Business Park)
TOTAL 107 acres 2,210,500 square feet
(b) The project also includes new internal streets (Apollo Drive, Apollo
Court and Saturn Way). Apollo Drive will provide access from Westminster Avenue and Seal
Beach and is proposed to cul-de-sac with the potential for through extension depending on
building design and locations within Planning Areas 1 and 2. All three streets are proposed to
be publicly dedicated.
(c) The surrounding land uses and zoning are as follows:
NORTH:
Retirement Community.
Westminster Avenue and the Leisure World
SOUTH: Industrial (Accurate Metals); and City Police Station,
City Public Works yard and other City facilities, and Animal Care Center on the south side
of Adolfo Lopez Drive.
WEST: Los Alamitos Retarding Basin and Island Village
residential community within the City of Long Beach.
EAST: Retail commercial center, Seal Beach Boulevard and
Seal Beach Naval Weapons Station.
Section 5. Based upon substantial evidence in the record ofthe Planning
COlmnission hearing regarding the application, including the facts stated in ~ 4 of this
resolution, and in the environmental documentation prepared in conjunctIOn with this
project, and pursuant to ~~ 28-2600 and 28-2602 of the City's Code, the Planning
Commission hereby finds that General Plan Amendment, consistmg of Land Use Element
Amendment 03-2, Open Space/Recreation/Conservation Element Amendment 03-2,
Housing Element Amendment 03-2 and Circulation Element Amendment 03-2, will be
beneficial to the short term and long tenn land use goals of the City of Seal Beach. The
Planning Commission further finds that approval of the subject applications will promote
the public health, safety and welfare. Therefore, the Planning Commission finds that the
requested amendments to the General Plan Land Use, Open Space/Recreation/Conservation,
GPA 03-2 (Boemg) PC Reso
2
Plannl11g CommlSSlO1l ResolutlOll Number 03-25
General Plan Amendment 03-2
Boeing Integrated Defense Systems Specific Plan
June 18, 2003
Housing and Circulation Elements of the City of Seal Beach will be in the public interest,
and makes the following findings of fact:
(a) The proposed General Plan Amendments will conform land uses to
those set forth within the Land Use, Open Space/Recreation/Conservation, Housing and
Circulation Elements for the subject area, and provides a comprehensive development which
accomplishes the following goals of the City in achieving sustainable development on the
subject property:
1.
a consistent project theme.
2.
Creates a comprehensive land use and infrastructure plan with
Provides for improvements to the street and circulation system
within the area.
3. Creates a comprehensive development program for under-
utilized and vacant properties.
4. Provides development that is at least fiscally neutral and, more
likely, fiscally beneficial to the City.
5. Adequately mitigates project-related traffic and noise impacts
to the extent feasible.
(b) The proposed project will allow for a reasonable range of land uses on
the subject property, recognizing the various site constraints discussed in the EIR, with the
provision of various land uses to address the identified objectives of the City.
(c) The proposed BIDS 'Specific Plan, and the necessary General Plan
Amendments, will not be detrimental to the short tenn or long tenn goals or objectives of
the City of Seal Beach and are in the interest of the public health, safety and welfare. The
proposed amendments are consistent with the General Plan, as amended.
Section 6. Based on the foregoing Sections 1 through 5, the Planning
Commission hereby recommends that the City Council approve Land Use Element
Amendment 03-2 as set forth below:
1. Page 22 of tile Land Use Element is revised to read as follows:
"INDUSTRIAL LAND USE
Categories for light industry and for oil extraction are the only industrial land
use categories that are felt appropriate for the City of Seal Beach.
1. EXISTING LIGHT INDUSTRY
The light industry land use category is represented by the North i\merican
Rockv..cll Boeing Integrated Defense Systems (BIDS) facility at the intersection of Seal
Beach Boulevard and Westminster Avenue.
1.1 Proposed Light Industrial Uses
Two areas within the City are proposed to provide additional light industrial
sites. The first is the parcel of land located directly adjacent to the North Amcrican
Rock\....cll Boeing facility. Thc existing facility and futurc cxpansion will occupy
approximately 90 aercs of thc total 120 acrc sitc. It is rccommended that the rcmaining
30 vacant acrcs be dcsignated for light industrial use, hopcfully in thc form of an
"industrial park" imtcad of being pcrmitted to dcvelop in a haphazard manner. An
"industrial park" is thc countcrpart to a .....cll desigRCd, landscapcd rcsidential
subdivision. Thc ad"v'antagc of this typc of planned approach is that the community can
compete for industry by offering fully scrviccd, protected sitcs for quality industry. }..n
cxcellent example of this coneept is thc IrviRC Industrial Park in Irvine, Calif-ornia. The
Boeing Integrated Defense Systems (BIDS) Specific Plan is being proposed. The
proposed BIDS Specific Plan will consist of 107-acre site containing approximately
2.210.500 square feet of office. research and development. manufacturing. and support
GPA 03-2 (Boemg) PC Reso
3
Planning COml111SSlOn ResolutIOn Number 03-25
General Plan Amendment 03-2
Boemg Integrated Defense Systems Specific Plan
June 18, 2003
operations space. The BIDS Specific Plan is designed to allow for development in a
manner that is compatible with the surrounding land uses. within. and adiacent to. the
City of Seal Beach. The BIDS Specific Plan will be divided into four (4) Planning Areas.
three of the four will be designated as Business Park/Light Industrial use with the fourth
planning area designated as Hotel/Commercial use.
The second proposal for additional industrial sites is for the parcel of land
directly adjacent to and north of the San Diego Freeway and west of Seal Beach
Boulevard. It is also recommended that this area be planned as an industrial park."
2. Section 5, "Specific or Precise Plans" of the Land Use Element is revised to add
a new subsection 5.4 to read as follows:
"5.4 Boeing Integrated Defense Systems (BIDS) Facility
The Boeing Integrated Defense Systems (BIDS) Specific Plan encompasses 1 07 acres
in the central western portion of the CIty. The specific plan is surrounded by Westminster
Avenue to the north. Adolfo Lopez Dnve to the south. Seal Beach Boulevard to the east. and
the Los Alamitos Retarding Basin to the west. This plan provides for development of a
business park. combined with hotel and cOlmnercial uses. within the existing framework of the
existing BIDS headquarters operations.
. BIDS Planning Area 1 - Business Park (Existing Boeing Campus)
Planning Area 1 (P A-I) is approximately 41 acres and comprises the existing core
campus use of the property. This includes Buildings 80. 81. 82. and 90. the
surface parking fronting Westminster Avenue (also known as parking lots 3
through 6). and other facilities and structures. The existing office. research and
development. warehouse and distribution. manufactunng. and support operations
land uses in this Planning Area WIll be preserved and maintained. P A-I currently
supports 805.000 square feet of gross floor area. To respond to potential
government and business contracts. developing communication and space
technologies. and to support general business demands. P A-I is designated for a
maximum of 1.150.000 square feet of gross floor area (an additional 345.000
square feet). The maximum F.A.R. for PA- 1 is 0.75.
. BIDS Planning Area 2 - Business Park
Planning Area 2 (PA-2) is approximately 16 acres and includes a range of BIDS
facilities and buildings. including Buildings 84. 85. 86. 91. 93. 94. 96. and 100. a
fire system tank farm. and an electrical substation. The existing gross floor area is
approximately 345.000 square feet. Existing buildings and facilities in P A-2 may
be maintained. reused. relocated. or elnninated. depending on BIDS business
requirements. P A-2 is designated for business park purposes with a maximum of
345.000 square feet of new and/or existing gross floor area. The maximum F .A.R.
for P A-2 is 0.60.
. BIDS Plannmg Area 3 - Business Park
Planning Area 3 (P A-3) is approximately 45 acres of vacant land. This Planning
Area provides for the maiority of new development on the BIDS site. New light
industrial buildings with up to 628.000 square feet of gross floor area are
designated for this Planning Area. The maximum F.A.R. for PA-3 is 0.60. PA-3
will include a new road system mcluding ingress/egress from Seal Beach
Boulevard and Westminster Avenue via Apollo Drive. providing access to the
new industrial park and existing facilities.
. BIDS Planning Area 4 - Hotel/Commercial Area
GPA 03-2 (Boemg) PC Reso
4
Planning CommisslOll Re!!.olutlOn Number 03-25
General Plan Amendment 03-2
Boelllg Integrated Defense Systems Specific Plan
June 18, 2003
Planning Area 4 (PA-4) is approximately 5 acres consisting primarily of(unused)
parking lot 7 at the eastern end of the property between W estminster Avenue and
Seal Beach Boulevard. This area is planned for hotel and/or commercial uses.
allowing for up to 120 hotel rooms and 32.500 square feet of commercial.
including retail. restaurant. and/or other similar commercial uses. Business park
uses are also pennitted in this Planning Area."
Section 7. Based on the foregoing Sections 1 through 5, the Planning
Commission hereby recommends that the City Council approve Open
Space/Conservation/Recreation Element Amendment 03-2 as set forth below:
1. Page 8 of the Open Space/Recreation/Conservation Element are revised to
read as follows:
"EXISTING Acreage PROPOSED Acreage
Regional Parks
Beaches 52.01 Los Alamitos Retarding 34.7
Basin, Ph. 1
Sunset Aquatic Park 28.01 Sunset Aquatic Park 67.0
Community Parks
Edison 26.01,2
Arbor Park 13.02
Tennis Facility 6.7
Neighborhood Parks
Almond 1.8
Marina Community 2.4 L.A. Water & Power Property 7.06
Eisenhower 1.4
Schooner 0.8
Bluebell 1.3
Heather 1.6
Aster 0.6
Bixby Village 2.5
Greenbelt
Pacific Electric Right-of-way 8.21 San Gabriel River 2.3
Bixby Old Towne Center 6.4 Boeing Specific Plan Open Space 4.7
Bixby Village 0.3
Special Use Facilities
Gum Grove Nature Park 10.21
North Seal Beach Center 0.51
McGaugh School 6.81,7
Zoeter School 2.41,7
TOTAL 173.0 TOTAL H-8H 15.7
GRAND TOTAL (existing and proposed) = ~ 288.7 Acres"
Section 8. Based on the foregoing Sections I through 5, the Planning
Commission hereby recommends that the City Council approve Housing Element
Amendment 03-2 as set forth below:
1. Table 17 of the Housing Element is revised to read as follows:
GPA 03-2 (Boemg) PC Reso
5
Name
1.
2.
3.
4.
5.
6.
Planlllng CommISSIOn ResolutIOn Number 03-25
General Plan Amendment 03-2
Boel1lg Integrated Defeme Systems Specific Plan
June 18, 2003
"TABLE 17
Vacant Site Analysis
Acres
General Plan!
Zoning
Status
Proposed
Specific Plan
Application for
Residential
Uses
Submitted
General Plan!
Zoning
amendments
approved in
1999 that
mclude a 13
acre residential
component
Amendment to
Specific Plan
Required
Necessary
zonmg
in place
General Plan
Amendment~
Specific Plan.
tmti Zone
Change. and
Rcq uired
Precise Plan
approved in
2003 that did
not include
residential
land uses
Specific Plan
for Visitor
Serving
Commercial!
Park uses in
Effect
Specific Plan
for Visitor
Serving
COlmnerclal
use in Effect
2. Section 5.2.1.2.E of the Housing Element is revised to read as follows:
HeUman Ranch
(Mola Project)
Specific Plan
(RLD, 329
DUs on 74
acres, 41.4
acres of wetland)
l49
Bixby Old Ranch* 20
(See note on following page)
C-2 and R-G
Leisure Wodd 4
RHD
Lot at NE
corner of
12th and PCH
.55
RLD
Rockwell
International
Boeing
Integrated
Defense
Systems
50
M-I
**
DWP Property
9.9
C-P
7.
***
State Lands
2.74
SPR
GPA 03-2 (Boemg) PC Reso
6
Planlllng CommISSIOn ResolutIOn Number 03-25
General Plan Amendment 03-2
Boeing Integrated Defense Systems Specific Plan
June 18, 2003
"E. Program: Conduct public hearillgs to determine the appropriateness and
benefits ofredesignatillg a pol1ion of a 50 acre ullder-utilized site on the R6ckwell
lntematimltll Boeing Integrated Defense Systems property for uses illcludillg
residential developmellt, with a portion of the site considered for higher dellsity
housing affordable to lower income households, and other portions desigllated for
sillgle family detached residential uses, to promote a more balanced housing
inventory within the commullity.
Anticipated Impact: The possible redesignation of approximately 50 acres of thc
Roek.....ell International property to residential and othcr appropriate land uses, to
pcnnit the dc',clopment of up to 250 units of low density housing on such parccl,
including the redesignation of approximately 5 of the 50 acres to mcdium or high
dcnsity residential (17 to 25 unIts/acre). If redesignated, the 5 acre portion of thc
Roekv..cll International site will be developed with 25 very 10'N mcome, 50 low
income and 50 modcrate income housing units. 'The de',clopmCflt and maintenance
of these housing units in these proportioll3 and ineomc categories will be encouraged
and facilitated through application of Programs 5.2.2.2(.\) and 5.2.2.2(B).
In 2003 the City held numerous public hearings regarding the appropriateness and
benefits of redesignating portions of the Boeing Integrated Defense Systems
property for uses including some component of higher density housmg. Such
hearings were the culmination of a lengthy fact-finding process. and included
hearings on the merits of two separate development proiects. In 2003. the City
Council approved a "Specific Plan" for continued use of the property for an
integrated business park development. In evaluating the adoption of the Specific
Plan. the environmental impact report evaluated an alternative proiect. the
"Residential Component" Alternative. The City determined that residential uses
were inappropriate on the site due to the following factors:
1) This land use alternative would not meet the proposed proiect's plannmg and
enviromnental design obiectives.
2) A residential alternative would place additional demands on public safety
providers and on public services greater than a business park development.
3) A residential alternative would limit the expansion of a range of employment
opportunities within the City by limiting the development of currently zoned M-
1 properties and uses by developing residential uses instead.
4) The fiscal benefits associated with the proposed proiect would not occur since
the hotel and cOlmnercial uses would not be developed under tIlis alternative.
Impact Area: Census Tract 995.04.
Respollsible Agencies: Planning Department, Planning Commission, City
Council.
Fin all cing: Planning Department budget.
Schedule: The preparation of a A Specific Plan for the Rockwell International
Boeing Integrated Defense Systems site will be undertaken by was submitted to the
City in ~ 2002. As part of the Specific Plan preparation process, all appropriate
land uses, including low and modcrate income housing, will was be considered as
part of the plan preparation and enviromnental analysis process. The City acted in
2003 to approve various General Plan amendments. zone changes. the Boeing
Integrated Defense Systems Specific Plan. a tentative subdivision map and precise
plans for a 973.000 square business park development. a 120-room hotel facility.
and up to 32.500 square feet of cOlmnercial development. "
Section 9. Based on the foregoing Sections 1 through 5, the Planning
Commission hereby recommends that the City Council approve Circulation Element
Amendment 03-2 as set forth below:
1. Page 11 of the Circulation Element is revised to read as follows:
GPA 03-2 (Boemg) PC Reso
7
Plan11l11g CommISSIOn ResolutIOn Number 03-25
General Plan Amendment 03-2
Boel1lg Integrated Defense Systems Specific Plan
June 18, 2003
"Capital Improvements Program
An important instrument of implementing the Circulation Element is a program of capItal
improvements, that is, based on a perceived prionty of areas of concern these may be
specifically planned for in the future. What ought to be established then is a system through
which these concerns may be practically approached. Pnorities for the construction of
improvements to the circulation systems need to be established. Areas of concern that ought
to be considered follow (in no priority):
o Seal Beach Boulevard --- San Diego Freeway interchange improvement.
o Continued bicycle route development.
o Specific study of the Main Street/commercial area.
o FIrst Street Extension from Pacific Coast High'.vay to Vlcstminstcr Bh'd."
2. The Circulation Element Map is revised by eliminating the proposed First Street
Extension from Pacific Coast Highway to Westminster Boulevard.
PASSED, APPROVED AND ADOPTED by the Planning Commission ofthe City
of Seal Beach at a meeting thereofheld on the 18th day of June, 2003, by the
following vote:
AYES: Commissioners
DEATON, HOOD, LADNER, SHANKS, AND SHARP
NOES: Commissioners
ABSENT: Commissioners
ABSTAIN: Commissioners
David Hood, Ph.D.
Chairman, Planning Commis
Wluttenberg, Secretary
Planning Commission
GPA 03-2 (Boemg) PC Reso
8
Planlllng CommISSIOn ResolutIOn Number 03-25
General Plan Amendment 03-2
Boemg Integrated Defense Systems Specific Plan
June 18, 2003
"EXHIBIT A"
BOEING INTEGRATED DEFENSE SYSTEMS SPECIFIC
PLAN
LEGAL DESCRIPTION OF SUBJECT PROPERTIES
PARCEL 2, IN THE CITY OF SEAL BEACH, COUNTY OF ORANGE, ST ATE OF
CALIFORNIA, AS SHOWN ON A MAP FILED IN BOOK 139, PAGE 4 OF PARCEL
MAPS, IN THE OFFICE THE COUNTY RECORDER OF SAID COUNTY.
EXCEPT ALL MINERALS, GAS, OIL, PETROLEUM, NAPHTHA AND OTHER
HYDROCARBON SUBSTANCES ETC., BELOW THE DEPTH OF 500 FEET FROM
THE SURFACE OF SAID LAND WITHOUT THE RIGHT OF SURFACE ENTRY AS
RESERVED BY DEEDS OF RECORD, ONE OF THEM BEING RECORDED IN
BOOK 7662, PAGE 442, OFFICIAL RECORDS.
GPA 03-2 (Boemg) PC Reso
9