HomeMy WebLinkAboutEQCB Min 1989-04-18
.
ENVIRONMENTAL QUALITY CONTROL BOARD
MINUTES OF MEETING
APRIL l8, 1989
1.
CALL TO ORDER
Chairman Fortner called the meeting to order at 7:40 p.m.
in the City's Council Chambers.
2.
PLEDGE OF ALLEGIANCE
The Pledge of Allegiance was led by Don Eisenberg.
ROLL CAT.T.
3.
Present: Ray Fortner, Chairman, District One
Gayle Knapp, District Three
Don Eisenberg, District Four
Staff
Present: Ed Knight, Director, Development Services Dept.
Absent: Lowell Kolb, District Two
Stephen Gavlick, District Five
.
4.
DISCUSSION OF SUPPLEMENTAL EIR FOR THE HELLMAN SPECIFIC PLAN
Ed Knight delivered the staff report. Staff's recommendation is
to receive and file the Supplemental EIR and to provide input to
the City Council regarding the document. Mr. Knight noted
representati ves from LSA and Michael Brandman Associates (MBA)
were present to answer questions tonight. LSA worked on the
wetlands and traffic issues for the EIR and MBA was' the lead
agency in preparation of the supplemental EIR.
Mr. Knight said that Mola's proposed alternatives were studied in
the Supplemental EIR. The City did certify the EIR and approved
a project. That project did not include any on-site wetlands
restoration. Subsequently, Mola (thru LSA) did additional work
on the wetlands issue and met with Corps of Engineers, CA Dept.
of Fish & Game, u.s. Fish & Wildlife Service. The tentative
conclusion was that on-site restoration would be a requirement.
At that point Mola came back with their tentative tract map plus
an amendment to add twenty acres of wetlands. LSA found there
may be additional wetlands out there --- in addition to the
twenty acres identified in the Subsequent EIR; that might require
additional wetlands mitigation to the proposed project.
.
.
Page 2 - Minutes of EQCB Meeting on April l8, 1989
PUBLIC HEARING OPENED
Kirk Evans * Nola Development Corporation
Mr. Evans, replying to Mr. Fortner's question about another Mola
alternative not covered in the Supplemental EIR, said Mola has
had further meetings with various community groups within the
City, City staff, Fish & Game, National Marine Fisheries, Fish &
Wildlife services, Corps of Engineers, EPA, and the Coastal
Commission. As a result of those meetings, Mola further massaged
alternative liB" which resulted in an alternative to liB" termed in
these Minutes as "B.l". Mr. Evans said Mola does not look at
this as a separate al ternati ve but as a change to al ternati ve
liB" . Mola would like to have this plan considered in the
comments to the Supplemental EIR tonight. Mr. Evans posted a map
of alternative B.1, which shows:
Reduction of 433 units to 412 units (21 units reduced).
Relocation of some single family homes which have been
replaced with l2 townhomes near Gum Grove Park. This has
opened up a much larger area for potential wetlands
restoration.
.
The community park has been expanded from 3.5 acres to 6
acres. This is at 40.4 acres of wetlands.
There will be less traffic.
Ms. Knapp asked who hired LSA? Mr. Evans replied MBA hired LSA
as their sub-consultant. The City hired MBA.
Mr. Knight stated staff's approach to alternative "B.1" would be
to advise MBA that the City wants liB .l" examined under the
mitigation measures thru alternative "B".
.
Walton Wright * Consultant for the Wetlands Restoration Society
Mr. Wright stated the Wetlands Restoration Society'S position on
the proposed Mola alternatives is still the same as their
position on the original Mola proposal --- they are still looking
at the historic wetlands on the site and restoration of wetlands.
He submitted, for the Record, two maps he prepared. One map is
marked "1894 U.S. Geological Survey Topo(graphical) Survey" map
and shows channels cutting across the site, tidal channels on-
site, histor~c channel of the San Gabriel River, a ten-foot
contour interval. The second map reflects a development area, if
there should be any development on this site, showing 79 units in
a shaded area with adequate buffers for a restored wetlands area.
(Both maps are marked Tentative Parcel Map No. 86-349 in the City
of Seal Beach in the upper right hand corner).
.
Page 3 - Minutes of EQCB Meeting on April l8, 1989
Anything below the ten foot area reflects historic wetlands.
These maps are in addition to the Wetlands Restoration Society
map which shows existing wetlands on the site; the City already
has a copy of this map.
Ms. Knapp said the consultants apparently didn't have this map
information when they prepared the EIR; they went from aerial
views going back to 1980. Mr. Wright said there has not been an
adequate analysis of the historic wetlands on the Hellman
property. Ms. Knapp asked Mr. Wright if there were some reason
MBA didn't have this information and he said "No. These maps are
around". Mr. wright stated also that degraded wetlands can be
restored and that the subject property presents a good
opportuni ty for wetlands restoration because there are no oil
wells or major development on the property.
Ms. Knapp asked Mr. Wright what the value his maps are for a lay
person trying to decide if that's the map they should go by
instead of the 1980 aerial maps, how valid are these maps, where
did he get these maps? Mr. Wright said the aerial photos show
much more wetlands in the 1920's. He said it may not have been
in MBA's interest to describe what the historic wetlands were.
There has never been an acknowledgement that 105 acres of
historic wetlands were ever on this site. The 105 acres has
aprox. 20 acres of a buffer zone around it --- the bluffs that
border this area also have Gum Grove Park on them.
.
Mr. Eisenberg asked Mr. Wright if his group had considered
whether it's feasible to restore the wetlands if there isn't a
development of some kind in the Hellman Ranch property?
Mr. Wright said yes, it's possible. He said that in talking to
the Harbor authorities, under their 20/20 plan, they will spend
up to $80,000 per" acre for restoration of wetlands. Proposition
70 passed which obtains money for acquiring and working on open
space areas. state license plate funds has money for habitat and
habitat restoration and enhancement.
Galen ~mhrose * Wetlands Restoration Society
Mr. Ambrose said his group is going to submit a complete package
on the Supplemental EIR on April 24, 1989. He said the species
list within the Supplemental EIR is not complete. He also spoke
on Walter Wright's qualifications.
Sally Hirsch * l325 Crestview * Save Gum Grove Park GrOUD
Ms. Hirsch spoke on the "B.1 " al ternati ve and said she was
pleased with the lO.4 acres for Gum Grove, the 6 acre additional
park, the trail system, fewer homes that will be two stories,
reduced traffic (from 6210 to 3800 trips), a thirty foot buffer
zone. She'd like to see a wetlands plan before building began.
.
.
Page 4 - Minutes of EQCB Meeting of April 18, 1989
Laird Mueller * 142 1lth street
Mr. Mueller stated he wants Seal Beach to stay as it is. If
that's not possible he wants building to have minimum impact.
Mitzie Horton * 153 13th street
Ms. Morton favors alternative
restoration plan in place. Forty
nothing has been definitely planned
liB" but wants a wetlands
acres will be set aside but
to restore them.
Mr. Knight noted the Hellman property contains severely degraded
wetlands with very little biological value and virtually no
wildlife value. Problems on those wetlands include dredge spoil
which was brought on the site 20 years ago arid elevated the site
above what would normally be functional as a salt water wetlands,
tidal action is represented in fractions of an inch.
Regarding wetlands restoration, Mr. Knight said wetlands
restoration depends on how certain Federal and State agencies
view this site. The Corps of Engineer'S Clean Water Act of 1972,
Section 404.bl talks about avoidance of existing wetlands.
Avoiding existing wetlands is the goal of the Corps of Engineers,
the California Department of Fish & Game and CA Coastal
Commission thru their various codes and statutes.
.
Mr. Knight said further that Mola alternatives "A" and liB" avoid
disruption of the wetlands; neither the Corps of Engineers nor
National Fish & wildlife require any restorations to "preserved
in place" wetlands.
Mola is working with the Port of Long Beach to bring about a
restoration plan but it hasn't been approved to date. The Port
of Long Beach has just started their own process and they have
not identified what their budget is, they have no idea what kind
of mitigation potential they can get out of this. It might be
awhile before the City can find out if the Port is interested in
restoring the Hellman wetlands. If the City of Seal Beach wants
the Hellman wetlands restored the city will have to depend on
another agency financially to restore these wetlands --- not the
City of Seal Beach, not Mola Development. A restoration project
like this carries a $2 - $3 million price tag; about $80,000 per
acre. For example, there's one culvert serving that site now.
To provide adequate flushing two or three pipes might be needed
under the cooling channel into the San Gabriel in order to
provide an adequate tidal fluctuation. Removing the dredge spoil
would require testing and would be expensive to do.
Mr. Eisenberg asked about alternative "C". Mr. Knight explained
that Mola would restore 25 wetlands acres. Again, it's a
question whether this plan would be acceptable to the Corps of
.
.
Page 5 - Minutes of EQCB Meeting of April 18, 1989
Engineers. They'd completely destroy the wetlands on site and
relocate the restored wetlands elsewhere on the site. Mola would
do the restoration and therefore they would approach the other
agencies to get the required permits.
Rob Schoenhultz * LSA Associates * Consultant to Nola
Alternative "B.l" represents a refinement of alternative liB" and
this would create the opportunity for a better restored wetlands
in the biological sense than alternative "B". Absent
participation by the Port authorities, there would be restoration
of approximately four (4) acres of wetlands on-site by Mola.
This would be their proportional share to the amount of wetlands
that would be impacted by al ternati ve liB .l". It would be
impossible to say exactly what the Coastal Commission would
require. LSA is working jointly with the Ports in looking at
ways to do a joint restoration in here.
.
Based on LSA's experience in wetlands restoration the Coastal Act
puts strict requirements on leaving wetlands alone but there is
some relaxation of rules in the case of a severely degraded
wetlands. He said he thinks the Coastal Commission would prefer
to see the existing wetlands left alone to maximize future
potential for wetland restoration on this site.
The EQCB asked what's the environmental impact to the City of
Seal Beach versus leaving it in its present degraded state?
wildlife values would go up which is what the Coastal
Commission and the Federal agencies would like as the ultimate
end.
Mr. Schoenhul tz said he thought there are about 105 acres of
historic wetlands. However, the reason LSA went back to 1969 is
both the Coastal Act and the Corps of Engineers program
considered the existing resource; this area has been so degraded
for so long that that is the time those programs went into
effect. Anything that happened before that was "grandfathered".
There's been so much dredge soil placed on this site that the
bulk of this area is not wetlands and has not been wetlands for
twenty plus years. Removing five to ten feet of fill from this
site would cost $80,000 to $100,000 per acre. This would get the
elevations down to where you could restore the tidal salt marsh.
This doesn't include new siphons and other work necessary to
restore wetlands. The restoration would be so expensive it would
be beyond the means of the Ports of Long Beach and Los Angeles.
Mario Voche * 730 Catalina Avenue
Mr. Voche wanted to know if there requirements for a scoping
session before the preparation of this Supplemental EIR?
.
.
Page 6 - Minutes of EQCB Meeting of April l8, 1989
Mr. Knight said there was no legal requirements for this plus
there were no new impacts involved in this Supplemental EIR.
There are still opportunities for citizens and agencys to respond
to this EIR and have their comments included in the Response to
Comments.
Walt Wriqht
Mr. Wright said the Port Authority looks to $80,000 per acre to
do restoration. The Port's 20/20 plan requires restoration of
acreage that mitigates for open water habitat loss. The
restoration here is salt marsh vegetation. We could pull in open
water habitat but the maximum credit received is for .. in kind"
restorations. It would be better to do the restoration in a
package.
.
It was explained that on a 4 acre parcel of wetlands it could
fall under the Army Corps of Engineers definition of a "nation-
wide permit", thus not requiring any further action from the Army
Corps of Engineers. Regarding wetlands restoration, the Army
Corps of Engineers has the least stringent regulations, the Fish
and Game Department more stringent and the EPA the most stringent
requirements. The Port does not restore other peoples
liabilities; they work only on their projects. The opportunity
footprints for the Port Authority are the same opportunity
impacts for Mola Development for not impacting wetlands. If we
have development there we severely tie up the ability to do
restoration in the future. We could get a fully functioning salt
marsh out of it.
Kirk Evans * Kola Development
Mr. Evans clarified the alternative "B.l" plan. There are 328
single family homes and 84 townhomes, making a total of 412.
EOCB Comments
Gayle Knap'p
Ms. Knapp had comments on the following issues:
GUM GROVE PARK - She's very pleased Gum Grove Park
will remain at 10.4 acres.
HOUSES - She's concerned that 412 housing units may
be too many houses. Traffic and noise elements are
her main concerns.
EARTHOUAKE - She's extremely concerned that these
houses are too close to the fault line even though
setbacks have been provided.
.
NOISE - Pumps on the oil wells will be changed from
gas to electric to keep noise down. Will a masonry
, .
.
Page 7 - Minutes of EQCB Meeting of April 18, 1989
wall of 8' or 10' mitigate the noise? will a masonry
wall reduce the dog barking noise for these homes
near the animal shelter? Don't put houses that close.
GOLF COURSE - She wants a regulation nine-hole golf
course. She wants Kola to contact Ben Brown in
Laguna Beach re his experience in this area. Also,
night lighting is not opposed by the EQCB.
WATER - There may not be enough water for this development.
Mr. Knight said the EIR was technically ,correct but doesn't
look at the whole picture for a reserve that the City needs.
A master plan is to be done and funded by the developer to
look at the water needs of the whole community as it would
be impacted by this project. If there is a requirement for
addi tional water facilities they would be funded at the
developer's expense. police, fire and other services
are examined in the EIR. Mr. Knight said a Mello Roos
district would be formed to meet the $70,000 to $90,000
deficit.
.
Don Eisenberg
Mr. Eisenberg said he didn't understand the wetlands restoration
issue as any of the people has discussed it. He thinks it has a
negative economic impact to Mola potentially in selling units if
it remains degraded wetlands. He thinks it's an issue of the
economics of development versus the economics of restoration.
He'd like to see as much restoration as possible.
Ray Fortner
Mr. Fortner stated his concerns re updated traffic study figures
and levels of service at various intersections that were not
addressed in the Supplemental EIR. He said he favored
alternative "C" because of developer restoration.
.
Ray Mull * LSA Associates
Traffic count figures are based on the 1987 study so LSA has used
the original EIR base. They have compared the differential of
the 760 dwelling unit counts to the "A", liB" and "C"
alternatives. Alternative "C" does include the golf cour~e ~nd
the trips generated in association with that. Alternative "C"
itself has about 3300 daily trips out of which 750 of those are
associated with the golf course itself. The difference between
the studies is the differential in the original alternative ...
indicated that there were 6200 daily trips ... alternative "B"
generates about 3800 and "B.1" is about 3700 trips. The impacts
to the roadway systems are unchanged regardless of which
alternative ... given the volume of traffic on major arterials,
this is a relatively small project. The same basic mitigation
measures apply to all alternatives. The threshold has been met
. .
.
.
.
Page 8 - Minutes of EQCB Meeting of April 18, 1989
at Pacific Coast Highway and westminster ... it's already at
capacity right now. The mitigation measure of a left turn lane
will help ... it significantly offset the contribution that the
project itself will add to the "over capacity situation" existing
right now.
MOTION by Knapp: SECOND by Eisenberg to receive and file the
Supplemental EIR and that the secretary and Director of
Development Services are instructed to transmit all comments
received here tonight to the City Council (as part of the
environmental process) and that we strongly urge that the City
Council require, as a condition to certification of the EIR, or
specifically address within the EIR, the following issues:
1. RESTORATION - A mitiqation measure for a restoration
plan be a component of the EIR.
2. TRAFFIC - That numbers be updated from 1987
or that it is shown they are sufficient to still be
used for this EIR. We will look at one or two
representative intersections to see what, if anything,
new impact from 1987 might be upon that and what this
new information may have on this project ... raising
"DRs to "E"s.
3.
NOISE - Primarily the housing units adjacent to the
oil wells on Seal Beach Blvd. and those adjacent to
the City'S Animal Shelter. will the use of masonry
walls mitigate the noise?
4.
ALTERNATIVE C - This alternative includes the golf
course. This committee wants Nola Development to
contact Ben Brown in Laguna Beach and look at the
he's done as a possible model toward a nine-hole
course alternative. Also, night lighting is
approved of by the EQCB.
work
golf
not
5. STUDY ON FOOTPRINT ANALYSIS and STUDY ON WATER
6. EARTHOUAKE The Committee had no specific
recommendations but emphasized their concerns of houses
being built so close to the Newport-Inglewood
earthquake fault.
VOTE: 3 - o.
. ' t ·
.
.
.
Page 9 - Minutes of EQCB Meeting of April l8, 1989
5. BOARD CONCERNS
There were no EQCB concerns.
6. STAFF CONCERNS
There were no staff concerns.
7. ADJOURNKENT
Chairman Fortner adjourned the meeting at 10:07 p.m.
Respectfully Submitted,
~~ ~--=--, - ~-
Joan Fillmann
Secretary
Department of Development Services
City of Seal Beach
THESE MINUTES ARE TENTATIVE AND SUBJECT TO THE APPROVAL OF THE
EQCB.
MINUTES OF APRIL l8, 1989 EQCB MEETING APPROVED
1989
Copy Distribution:
Council Members:
victor Grgas
Edna Wilson
Joyce Risner
Frank Laszlo
Joe Hunt
EQCB Members:
Ray Fortner
Gayle Knapp
Don Eisenberg
Lowell Kolb
Stephen Gavlick
By Request:
Ray Fortner