The Clean Water Act (officially known as the Federal Water Pollution Control Act
Amendments of 1972) was passed into law to restore and maintain the chemical, physical,
and biological integrity of the Nation's waters, and where attainable, to achieve a level of
water quality that provides for the protection and propagation of fish, shellfish, and wildlife,
and for public recreation in and on the water. The first goals of the Clean Water Act are
zero discharge of pollutants and the protection of "fishable /swimmable" water quality.
Since 1993, the City has been a co- permittee with the County of Orange to meet the
requirements of the various regulations associated with the Act. After each permit renewal,
the City is required to continue to implement storm water quality management programs
and develop additional programs in order to control pollutants in storm water discharges.
On January 18, 2002, the SARWQCB adopted Order No.R- 2002 -001 entitled "Waste
Discharge Requirements for the County of Orange, Orange County Flood Control District,
and the Incorporated Cities of Orange County within the Santa Ana Region Area Urban
Storm Water Runoff Orange County" known as "the Permit ".
As part of the permit, the City must make certain that none of its facilities are in violation
of the permit requirements. The City's Maintenance Yard ( "Yard ") is treated as an
industrial facility within the permit and all wash water from vehicles or equipment must
be collected and properly disposed. The Yard's current wash rack system is in need of
replacement and major upgrade. The Department investigated various options and
determined it would be more cost effective to purchase an "off the shelf' unit. The system
would need to accommodate large vehicles and equipment of the Department.
Additionally, the specifications require that the unit be movable, pre -filter and treat wash
water collected in the system so that it is acceptable for discharge into the sewer as well
Agenda Item P
as mud and oil separator filtering systems. The water used would also be recycled and aid
in the City's water conservation efforts.
After request for proposal is circulated, a contract for purchase will be brought forward in
the spring. The system is expected to cost $70,000 and funds are available within the
Council approved Capital Improvement Program specifically for storm water quality
upgrades to the Maintenance Yard for compliance with the permit.
FISCAL IMPACT:
Funding is available within the Capital Improvement Program.
RECOMMENDATION:
Receive and File.
Submitted By:
`- /
Dougl %.!! M! . • > . r
Public Works Department
ED ' 1JAPPROVE'
4 6 4
John B ahorski, Ci anager
. chments:
Exhibit "A" — Technical Specifications
Agenda Item
Exhibit "A" — Technical Specifications
Agenda Item
CITY OF SEAL BEACH
"WASH RACK SYSTEM, MODULAR, RO SYSTEM"
The City is requesting bids on a recycling wash rack system which contains the following
functions: portable, prefilters and treats wash water collected in the system and prepares
for sewer discharge within acceptable discharge limits, has steel racks, on site storage
tank, mud /oil separator with filtering systems, RO spot free rinse production system.
TECHNICAL SPECIFICATIONS
Bidders must return the original or a photocopy of this form and make an entry for each item in
the space provided to the right, indicating conformance to the specification. Use additional
paper if needed. The City reserves the right to reject any bid proposal that does not conform to
this requirement.
Pressure Washer
1. 991 SS -208 Hotsy Hot Water Pressure Washer or
equivalent
minimum 4.0 GPM @2000 PSI
minimum 5 HP Electric Motor, 208 Volt, 3 Phase, 18
amps
Hawk Triplex Ceramic Plunger Pump, Belt Drive
Adjustable Temperature Control or equivalent
Vertical Burner, LP Gas Fired
Stainless Steel Coil Wrap
Rust -Proof Fuel Tank with Fuel Gauge
Minimum 50 ft High Pressure Hose
Trigger Gun Control, with Wand and Adjustable
Nozzle
Powder coat Finish,
2. Pressure washer must carry ETL certification label
Filtration Chamber
A Must be located remotely from containment area.
Simple one button operation with automatic shut
down for full filter.
1. Contains two (2) 8" x 30" Patented RPA- Process
Systems Zero - Bypass Stainless Steel Filter housings
with:
Patented R -P Products Certa -Seal® Bags or
equivalent. One re- usable high pressure filter
element (25p) and one high dirt load polypropylene
polishing filter, and maximum 5 micron absolute
filter with pressure gauges.
1
CITY OF SEAL BEACH
"WASH RACK SYSTEM, MODULAR, RO SYSTEM"
NOTE: No system with nominal filtration will be
accepted. Must have stainless steel filter housings
due to corrosive environment.
Each housing is certified to a minimum of 125 PSI.
2. Continuous ozone injection and re- circulation system.
Ozone injection must use high diffusion direct
injection system and Corona Discharge Ozone
generator or equivalent, with minimum output of 1.5
Grams /hour
3. Two HP Siemens Motor with Nash -Elmo regenerative
blower /suction pump or equivalent with minimum 85"
lift and 100 SCFM. Includes vacuum relief port and
maximum 1 micron air filter, 25000 hour rating and
less than 75 dB operational levels. System MUST
utilize vacuum lift pick up. No systems will be
accepted that utilize sump pumps to transfer water
from wash rack.
4. All Welded Stainless Steel construction with fork
pocket skid base. Entire housing must be 304
Stainless Steel with polished finish for corrosive
environment. All TIG welded construction.
5. Internal mud /oil separator with minimum 149 gallon
clarifying chamber.
6. NEMA 4 electrical enclosure and components. All
motors must be individually fused and protected from
power surge and thermal overload. All components
and wiring must be in compliance with UL1776
standards. A complete wiring schematic with
component listing and certifications (UL, CE, and
ETL) must be supplied with bid specs.
7. Stainless steel Z- plate® separator coalescer or
equivalent with all stainless steel and 120 sq. ft
surface area min.
8. Belt type stainless steel oil skimmer operating at a
minimum of 1 GPH.
9. Internal polypropylene oil filter.
10. PLC controlled oil skimmer and all pumps with real
time clock and integrated safety /overpressure
regulation with indicator light and LCD troubleshoot
display
Hour Meter for system operation.
18 I/O PLC controlled for custom software with
day /date /time pre - programmed and simple to update
chip based program from Allen Bradley.
2
CITY OF SEAL BEACH
"WASH RACK SYSTEM, MODULAR, RO SYSTEM"
11. High pressure and overfill protection.
12. All hoses and accessories required for operation.
13. 0- bypass absolute filtration to a maximum of 5
microns.
14. Minimum 200 gallon settling reservoir capacity with a
1.5 cu.ft. minimum oil absorbing media filter.
15. 1 HP Goulds high flow filtration pump or equivalent
16. NEMA 4 Hoffman enclosure with all NEMA 4 electrical
connections and wet environment TEFC motors.
17. 208V 3 PH 50A service with NEMA 6 -50 Plug
18. NO PVC plumbing or valves
19. Minimum 12 GPM @ 100 PSI Flow Rate for filtration
system, high load filters with 100 PSI full load and
104 PSI solid state pressure sensors for system shut
down and filter replacement warning light
illumination.
Water Storage Tank
1. Minimum 300 gallon polypropylene bottom water
storage tank with gallon markings and dual outlet
including brass ball valves, PVC valves and tanks are
NOT acceptable.
Steel Racks
1. Overall length of the wash rack shall be a minimum
of 18' (feet)
Overall width of the wash rack shall be a minimum of
17' (feet)
2. Minimum 15,000 Ib. Wheel Load bearing capacity.
No electrical devices or pumps on or in containment
racks.
No water reservoirs may be incorporated into the
containment racks. System must pump racks dry at
conclusion of each wash event.
Multiple debris trapping screens and easy clean -out
provided by grating removal.
System must accommodate expansion or relocation
of racks without welding.
All bolt together construction must be water tight.
Smooth diamond plate top surface with no surface
grating.
3
CITY OF SEAL BEACH
"WASH RACK SYSTEM, MODULAR, RO SYSTEM"
3. 8' x 6' all steel construction with fork pockets in 3
sides, in 17" x 24' configuration. 7" overall height
with 1" x 3" bar grating & diamond plate top. No
surface grates with gapped grating will be accepted
to prevent trapped wheels or feet on cleaning
surface. NO wash rack height over 9" will be
acceptable as per OSHA regulations
4. Low angle approach ramps with diamond tread
surface and bolt on construction for drive on and off
of wash rack.
Wash Rack Walls
1. Walls must be permanently attached to wash rack
structure
Walls shall run the length of the wash pad on two
sides
Walls shall be 6' in height
Walls must be galvanized steel panels with steel
support structures
Reverse Osmosis System
1. Complete self contained system
Chlorine carbon pre - filter with auto back wash
Minimum 200 gallon storage tank with auto shut off
RO Production Unit shall have:
Stainless Steel Frame
Flowmeters for concentrate and permeate levels
Maximum 10 micron prefilter
Automatic and manual backwash for RO membrane
Replaceable thin film composite RO membrane
Pre - plumbed and pre -wired
180 psi pressure to membrane
39 "H x 15'W x 13 "D
Transfer System shall have:
Stainless Steel Transfer pump
Stainless Steel Solenoid Valves
Stainless Steel Frame
115/230 Electrical Connections
minimum 4 GPM @ 200 PSI Output
11" W x 18" D x 38" H
System must be tied into remote operation box for
start/stop from wash rack remote station
Automatic Vacuum Start (for filter weir)
1. I Automatic float switch activates flow of filter weir I II
4
CITY OF SEAL BEACH
"WASH RACK SYSTEM, MODULAR, RO SYSTEM"
Senses water level on pad and begins pick up
Activates during overflow or storm event
Remote Operation Station
1. All systems will be controlled from single remote box
in wash bay
Single point of operation control box with the
following controls
Wash 1- Hot Water /Pressure Washer
Rinse -Low pressure /Cold RO Spot free rinse
Wired solenoid switch to control spot free rinse
Hose Reel Station
1. (2) Two wall mount hose reels. Reels shall be
mounted side by side on galvanized wash rack wall.
Hose reel #1 shall be rated at 3,000 psi/ hot water
for wash line and filled with 50' single wire pressure
hose rated for 3,000 psi 240F with insulated gun, 15"
wand, and 40 degree spray nozzle. Hose reel #2
shall be rated at 3,000 psi /cold water for RO rinse
line and filled with 50' single wire hose rated at 3,000
psi cold water with insulated gun, 15" wand, and 40
degree nozzle.
Both hose reels shall be equipped with replaceable
brass swivel, brake, and locking pin.
Both hose reels shall have a wand holder mounted
beside the hose reel for holding wand and gun.
All Necessary Plumbing
1. Vendor responsible for all interconnecting plumbing
between system components and from filtration
equipment to sanitary sewer discharge point.
Installation and Training
1. Vendor responsible for installation of all equipment
and original setup. City or assigned contractor will
provide all necessary electrical disconnects and
conduit runs for remote control box. City will provide
water bibs for connection to the system and sanitary
sewer discharge port within 3' of discharge location.
Vendor responsible for all interconnecting plumbing
between system components.
2. Vendor responsible for training of City personnel on
use and maintenance of equipment. Vendor will
provide (2) training sessions with written manuals (4)
provided at time of training
5
CITY OF SEAL BEACH
• "WASH RACK SYSTEM, MODULAR, RO SYSTEM"
Manuals
1. Minimum Four (4) complete training manuals with
operating and troubleshooting of all system
components. Each manual will contain spare parts
lists of all system components.
Warranty
1. Minimuml year warranty, parts only on all recycling
system components
Minimuml year parts and labor on pressure washer
Minimum 4 year parts only on pressure washer coil.
Minimum 7 year parts only against catastrophic failure
of pressure pump.
Provide copy of written warranty on all components.
6